ML23202A016

From kanterella
Revision as of 21:00, 8 August 2023 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating
ML23202A016
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/20/2023
From: Siva Lingam
NRC/NRR/DORL/LPL4
To: Cox M
Arizona Public Service Co
References
L-2023-LLA-0098
Download: ML23202A016 (3)


Text

From: Siva Lingam Sent: Thursday, July 20, 2023 4:09 PM To: Matthew.Cox@aps.com Cc: Jennifer Dixon-Herrity; Brian Wittick; Phillip Sahd; Vic Cusumano; Derek Scully; David Nold; Jo Ambrosini (She/Her); Ahsan Sallman; Matthew Hamm; Carl.Stephenson@aps.com

Subject:

Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs -

Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098)

By letter dated June 29, 2023 (Agencywide Documents Access and Management System Accession No. ML23180A222), Arizona Public Service Company submitted a license amendment request (LAR) for U.S Nuclear Regulatory Commission (NRC) approval for Palo Verde Nuclear Generating Station, Units 1, 2, and 3, by requesting the following changes:

  • Limiting Condition for Operation (LCO) for TS 3.5.2, and
  • LCO for TS 3.6.5, Containment Air Temperature.

The purpose of this e-mail is to provide the results of the NRC staffs acceptance review for the LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.

The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment.

Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this LAR will take approximately 370 hours0.00428 days <br />0.103 hours <br />6.117725e-4 weeks <br />1.40785e-4 months <br /> to complete. The NRC staff expects to complete the review of this LAR by June 29, 2024, or earlier. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, or unanticipated addition of scope to the review.

If you have any questions, please contact me at (301) 415-1564.

Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Grand Gulf Nuclear Station Entergy Fleet Location: O-9E22; Mail Stop: O-9E03 Telephone: 301-415-1564 E-mail address: Siva.Lingam@nrc.gov

Hearing Identifier: NRR_DRMA Email Number: 2174 Mail Envelope Properties (SJ0PR09MB6109A1B62CACEFDC6A9BB029F63EA)

Subject:

Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs -

Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098)

Sent Date: 7/20/2023 4:09:24 PM Received Date: 7/20/2023 4:09:00 PM From: Siva Lingam Created By: Siva.Lingam@nrc.gov Recipients:

"Jennifer Dixon-Herrity" <Jennifer.Dixon-Herrity@nrc.gov>

Tracking Status: None "Brian Wittick" <Brian.Wittick@nrc.gov>

Tracking Status: None "Phillip Sahd" <Phillip.Sahd@nrc.gov>

Tracking Status: None "Vic Cusumano" <Victor.Cusumano@nrc.gov>

Tracking Status: None "Derek Scully" <Derek.Scully@nrc.gov>

Tracking Status: None "David Nold" <David.Nold@nrc.gov>

Tracking Status: None "Jo Ambrosini (She/Her)" <Josephine.Ambrosini@nrc.gov>

Tracking Status: None "Ahsan Sallman" <Ahsan.Sallman@nrc.gov>

Tracking Status: None "Matthew Hamm" <Matthew.Hamm@nrc.gov>

Tracking Status: None "Carl.Stephenson@aps.com" <Carl.Stephenson@aps.com>

Tracking Status: None "Matthew.Cox@aps.com" <Matthew.Cox@aps.com>

Tracking Status: None Post Office: SJ0PR09MB6109.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3122 7/20/2023 4:09:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: