ML22341A139

From kanterella
Revision as of 17:55, 11 December 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Eos Amendment 3 - RAI Letter (New Scope Addition 3)
ML22341A139
Person / Time
Site: 07201042
Issue date: 12/08/2022
From: Christian Jacobs
Storage and Transportation Licensing Branch
To: Narayanan P
TN Americas LLC
Shared Package
ML22341A136 List:
References
CAC 001028, EPID L-2021-LLA-0055
Download: ML22341A139 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 8, 2022 Prakash Narayanan Chief Technical Officer TN Americas LLC 7135 Minstrel Way, Suite 300 Columbia, MD 21045

SUBJECT:

TN AMERICAS LLC APPLICATION FOR CERTIFICATE OF COMPLIANCE NO.

1042, AMENDMENT NO. 3, TO NUHOMS EOS SYSTEM (DOCKET NO. 72-1042, CAC NO. 001028, EPID: L-2021-LLA-0055) - REQUEST FOR ADDITIONAL INFORMATION (NEW SCOPE ADDITION #3 - ASME NOG-1 EXCEPTIONS)

Dear Prakash Narayanan:

By letter dated March 31, 2021, as supplemented June 23, 2021, August 4, 2021, September 3, 2021, October 22, 2021, November 30, 2021, February 25, 2022, June 7, 2022, June 29, 2022, September 30, 2022, October 31, 2022, and November 14, 2022, TN Americas LLC submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for Certificate of Compliance No. 1042, Amendment No. 3, to the NUHOMS EOS System, pursuant to the requirements of Part 72 of Title 10 of the Code of Federal Regulations.

The staff has determined that further information is needed on the new scope addition #3 (submitted September 30, 2022), to complete its technical review. Note that the new scope addition has caused further delays to the original schedule to complete the review for this amendment. The request for additional information (RAI) is attached. Your response should be provided no later than January 4, 2023. If you are unable to meet this deadline, please notify us in writing, at least one week in advance, of your new submittal date and the reasons for the delay. The NRC staff will then assess the impact on the revised schedule (due to the new scope addition) to complete the preliminary safety evaluation report by March 2023 and notify you if the schedule needs to be revised again. The estimated effective date for this amendment is now September 2023.

P. Narayanan Please reference Docket No. 72-1042, CAC No. 001028 and EPID: L-2021-LLA-0055 in future correspondence related to the acceptance review for this licensing action. If you have any questions, please contact me at (301) 415-6825.

Sincerely, Signed by Jacobs, Christian on 12/08/22 Christian Jacobs, Senior Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 72-1042 CAC No.: 001028 EPID: L-2021-LLA-0055

Enclosure:

RAI for New Scope Addition #3

ML22341A136(pkg), ML22341A139(ltr),

ML22341A137 (enclosure)

OFFICE DFM DFM DFM DFM NAME PKoch TBoyce JGoodridge for YDiazSanabria ELee DATE 12/08/2022 12/07/2022 12/08/2022 12/08/2022 OFFICE DFM NAME CJacobs DATE 12/08/2022