Provides Annual Update of Status of Region III Response to Staff Actions Resulting from Diagnostic Evaluation at Quad Cities Nuclear Power Station
ML20217A184
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 11/01/1996
From: Beach A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Taylor J
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
NUDOCS 9709190091
Download: ML20217A184 (6)


Text

'

"k ./ fNwr

.O O Novmber 1,1996 i

I l MEMORANDUM TO: James M. Taylor, Executive Director for Operations FROM: A. Bill Beach, Regional Administrator, Region lli

REFERENCES:

James M. Taylor Memorandum, " Staff Actions Resulting from the Diagnostic Evaluation at Quad Cities Nuclear Power Station," dated December 29,1993 Edward L. Jordan Memorandum, " Status of Staff Actions,"

dated September 11,1995

SUBJECT:

ANNUAL REPORT OF REGION lll RESPONSE TO STAFF ACTIONS RESULTING FROM THE DIAGNOSTIC EVALUATION .

AT QUAD CITIES NUCLEAR POWE9 STATION I am writing to provide Region lil's (Rill) annual update o' ine status of assigned tasks from th9 referenced memoranda. In addition to the s%rf action items, we issued Rill >

Inspection Report (IR) 50 254/265 94004 in March 1994 to track individual findings of the DET to completion. -The attachment provides the current status of those findings.

Inspection efforts at Quad Cities continue to focus on areas of engineering and maintenance performance weaknesses. Current issues at Quad Cities include plant material condition, work control, root cause effectiveness, and corrective actions, in addition, station progress on improvement initiatives are continuously evaluated by our resident inspection staff (N +1) and region based specialists. The Quad Cities Focus -

Group initiative, discussed in the November 1994 update, was disbanded in October 1996 in order to better focus Rlliinspec an resources. Specific DET follow up items identified in Attachment 1 will continue to be audited as a matter of rcutine follow up.

The current status and schedule of staff actions assigned to Region 111 are summarized below.

Issue 1: Adequacy of ASME Section XI Pump and Valve Testing Program. The inservice Test (IST) program has shown some improvement due to recent program revisions as discussed in inspection Report 50 254/265 95004, dated July 6, 1995. However, the licensee has not yet fully implemented the planned revisions.

The licensee reduced the number of IST and non-IST components with vibration measurements in the alert range. Closecut of the remaining portions of this item is planned for. December 1996.

CONTACT: James L. Ca'idwell, Rill /DRP

,' }; )

v (630) 829-9600 9709190091 961101 ltlE!Elllllihlli!!Ulll PDR ADOCK 050002S4 g P PDR

[ s

). '

, J. M. Taylor 2-Issue 9: Quad Cities SEP Action Plan Not Yet Developed. Action inw were developed to evaluate and assign priorities to the Dresden Unit 2 by.witic Evaluation Program (SEP) issues identified as applicable to Quad Cities. The licensee stated in a November 1,1995, letter that all Quad Cities SEP action items were complete as of June 15,1995. Our review of the licensee's completed actions was necessarily delayed by assignment of our principle inspector to the i agency's recent inspection effort at Maine Yankee Final review of this issue is in l progress and expected to be completed this year.

As stated in Mr. Jordan's memorandum referenced above, a written status report will be provided by the end of October each year on the disposition of each item assigned to Rill.

Should you have any comments regarding these matters, please call me or James Caldwell of my staff.

Attachment:

As stated cc w/ attachment: S. Rubin, AEOD DOCUMENT NAME: a:\96qc.ar To receive a copy of this document. Indicate in the box: "C" = Copy without attachment / enclosure "E" = Copy with attachment / enclosure *N' = No cop;.

OFFICE RIII lE RIIh, t J\ j l RIII t h // , l E l NAME Hiland 8L d Cald %IQ Grobe Beach VVifV W DATE 1o/3/ /96 lo/dt/96 1o/3 /96 OFFICIAL RECORD COPY

~'

._)

UDelTO STATES y

    • "%'s* NUCLEAR REGULATORY COMMISSION E REGION lli 801 WARRENVill.E ROAD 1 (e ess,

/ UsLE GNOIScord2-4351

! Novencer 1,1996

!- 4 MEMORANDUM TO: James M. Taylor, Executive Director for Operations FROM: A. Bill Beach, Regional Administrator, Region til fu

REFERENCES:

Janies M. Taylor Memorandum, " Staff Actiotis Resulting from the Diagnostic Evaluation at Quad Cities Nuclear Power Station," dated December 29,1993 Edward L. Jordan Memorandum, " Status of Staff Actions,"

dated September 11,1995 .

SUBJECT:

ANNUAL REPOP.T OF REGION 111 RESPONSE TO STAFF t ACTIONS REFULTING FROM THE DIAGNOSTIC EVALUATION AT QUAD CITIES NUCLEAR POWER STATION I am writing to provide Region Ill's (Rill) annual update of the status of assigned tasks from the referenced memoranda, in addition to the staff action items, we issued Rlit inspection Report (IR) 50 254/265-94004 in March 1994 to track individual findings of the DET to completion. The attachment provides the current status of those findings.

Inspection efforts at Quad Cities continue to focus on areas of engineering and maintenance performance weaknesses. Current issues at Quad Cities include plant material condition, work control, root cause effectiveness, and corrective actions. In addition, station progress on improvement initiatives are continuously evaluated by our resident inspection staff (N + 1) and region based specialists. The Quad Cities Focus Group initiative, discussed in the November 1994 update, was disbanded in October 1996 in order to better focus Rlliinspection resources. Specific DET follow up items identified in Attachment 1 will continue to be audited as a matter of routine follow up.

The current status and schedule of staff actions assigned to Region 111 are summarized below, issue 1: Adequacy of ASME Section XI Pump and Valve Testing Program. The inservice Test (IST) program has shown some improvement due to recent program revisions as discussed in inspection Report 50-254/265-95004, dated July 6, 1995. However, the licensee has not yet fully implemented the planned revisions.

The licensee reduced the number of IST and non-IST components with vibration meacurements in the alert range. Closecut of the remaining portions of this item is planned for December 1996.

CONTACT: James L. Caldwell, Rill /DRP (630)829-9600

/ o; .

o g J. M. Taylor 2-Issue 9: Quad Cities SEP Action Plan Not Yet Developed. Action plans were devel'ope'd to eval 6 ate and assign priorities to the Dresden Unit 2 Systematic Evaluation Program (SEP) issues identified as applicable to Quad Cities. The licensee stated in a November 1,1995, letter that all Quad Cities SEP action items were complete as of June 15,1995. Our review of the licensee's completed t

actions was necehsarily delayed by assignment of our principle inspector to the agency's recent inspection effort at Maine Yankee Final review of this issue is in progress and expected to be completed this year.

As stated in Mr. Jordan's memorandum referenced above, a written status report will be provided by the end of October each year on the disposition of each item assigned to Rill.

Should you have any comments regarding these matters, please call me or James Caldwell of my staff.

Attachment:

As stated .

cc w/ attachment: S. Rubin, AEOD

Qutd Citioc DET CroSc Referenca o -

O Attachment IR 50-254/265-94004 INSPECTION ITEMS CROSS REFERENCE 36 ITEMS CLOSED G 26 UNDER REVIEW REPORT ITEM- REPORT STAFF SUBJECT STATUS 94004 TYPE PAR NO. ITEM NO. RPT #

-01 URI 3.a #5* CNTMT. VENT CLOSED 94010

-02 IFI 3.a GRP 1 ISOLATIONS CLOSED 96004

-03 IFt 3.a ERV FAILURES

-04 IFI 3.a

  • FEED REG LOCKUP CLOSED 94010

-05 IFI 3.a 02 ANALYEER

-06 IFI 3.a VALVE LEAKAGE

-07 IFI 3.b TIMELY NWRs

-08 IFI 3.b MAINT TIME CLOSED 95003

-09 IFI 3.c BACKLOO/PIs CLOSED 96004

-10 IFI 3.d BROKE RCIC BOLTS CLOSED 95004

-11 IFI 3.d C.R.HVAC CLOSED 95003

-12 IFI 3.d BLDG VENT TRIP CLOSED 95003

-13a NOV 3.d SEISMIC MOUNT I CLOSED 96004

-13b NOV 3.e ELMS CALC CLOSED 95005

-14 IFI 3.d DC GROUNDS CLOSED 96002

-15 IFI 3.e OPERABILITY CLOSED 96004

-16 URI 3.e 2 OVER 1

-17 URI 3.e SBLC HEAT TRACE

-1Ba NOV 3.e #6* FW NOZZLE CLOSED 95003

-18b NOV 3.f VALVE VIBRATION CLOSED 95003

-19 IFI 3.g GREEN ALARMS

-20 IFI 3.h UNIT SUP CLOSED 94010

-21 IFI 3.h- SIMULATOR CLOSED 95004

-22a NOV 3.1 OPS PROCEDURES CLOSED 95003

-22b NOV 3.1 MAINT PROCEDURES CLOSED 95003

-23 URI 3.j TS REQMT MISSED

-24 IFI 4.a #1* IST SECTION XI CLOSED 94008

r....

o Qutd Citico DET Croso Refersnes O

Attachm3nt

, -~25 IFI 4.a #1*

PUMP VIBRATION CLOSED

-26 95004 IFI 4.a #1* PUMP VIB TREND CLOSED

-27 95004 IFI 4.a PUMP HEAD DATA

-28 IFI 4.a N/A HPCI TEST RESULTS CLOSED

-29 94010 IFI 4.a EDGCW HX HI FLOW

-30 URI 4.a #1*

i RELIEF VALVE TEST CLOSED 94008

-31 URI 4.a STROKE TIMES CLOSED 94008

-32 URI 4.a #1* CNTMT VLV TEST

-33 IFI 4.a FIRE VLV TEST CLOSED

-34

-94008 IFI 4.b MAINT IMPLEM

-35 IFI 4.b MAINT SUPPORT CLOSED

-36 96004 IFI 4.b #8* MOV TEST PROGRAM CLOSED 94016

-37 IFI 4.b PM PROGRAM CLOSED

-38 95005 IFI 5.a THERMAL BINDING CLOSED

-39 95005 URI 5.b MAG ALLOY USE

-40 IFI 5.c EQPMT VIBRATION

-41 IFI 5.c HPCI TORUS MOD CLOSED

-42 95003 IFI 5.d ENG SUP TO MAINT CLOSED

-43

-95007 IFI 5.d SYS ENGINEERING

-44 IFI 5.d SESRs

-45 IFI 5.d SNGL ELE / FEED REG

-46 URI 5.e RHR SPRING CANS

-47 IFI 5.e DEGRADED GRID

-48 IFI 5.f OERs CLOSED

-49 96002 IFI 5.g CORP ENG SUPPORT

~50 IFI 5.g #9* VAT /SEP

-51 IFI 5.g DPDs

-52 IFI. 5.g IPE CLOSED

~53 95003 IFI 5.h MOD PROGRAM

-54 NOV 5.h- 50.59 REVIEWS

-55 IFI 5.1 #3c* INVOLV-TEMP MOD CLOSED

-56 95003 URI 5.1 #3c* BELZONA CLOSED

-57 94028 IFI 6.a IRP

-58 IFI 6.b SITE SQV

-59 IFI 6.c STAFFING CLOSED 95003

.