MONTHYEARML19317D0762019-11-18018 November 2019 Summary of Meeting Near Vermont Yankee Power Station Regarding Establishment and Opration of Community Advisory Boards ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML17143A1552017-06-0606 June 2017 Memorandum to C. Bladey Notice of Availability of Exemption for Entergy Energy Operations, Inc., Vermont Yankee Nuclear Power Station Independent Spent Fuel Storage Installation ML17045A5282017-05-25025 May 2017 Memo to C. Bladey Notice of Availability of Environmental Assessment and Finding of No Significant Impact for Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station, Independent Spent Fuel Storage Installation Exemption Requ ML17055A5042017-03-0101 March 2017 Revision of the NRC Vermont Yankee Decommissioning Webpage ML16176A3392016-10-28028 October 2016 Decommissioning Lessons Learned Report and Transmittal Memorandum ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML14209A7052014-08-0606 August 2014 Letter to FEMA Requesting Review and Concurrence of Certain Proposed Entergy Nuclear Operations, Inc. Emergency Response Organization Changes to the Vermont Yankee Site Emergency Plan ML14209A9352014-07-24024 July 2014 1st Quarter 2014 Performance Review ML13150A2182013-05-31031 May 2013 6/12/13 Notice of Conference Call with Entergy Nuclear Operations, Inc. to Discuss Draft Request for Additional Information for Vermont Yankee NRC Order Number EA-12-049 Related to Mitigation Strategies ML13108A3282013-04-22022 April 2013 Notice of Forthcoming Meeting with Petitioners Requesting Action Against Entergy Nuclear Operations, Inc., Regarding Operations at FitzPatrick, Pilgrim, and Vermont Yankee Nuclear Power Stations (TAC Nos. MF1092, MF1093, and MF1094) ML12298A0882012-10-24024 October 2012 Forthcoming Meeting to Discuss Proposed License Amendment Request to Revise 10 CFR 50.63 Alternate AC Power Source to SBO EDG ML13219A0472012-03-15015 March 2012 Memo from M. Murphy to G. Wilson, Subj: Safety Evaluation Regarding Vermont Yankee Nuclear Power Station Core Plate Hold Down Bolt Inspection Plan and Analysis ML13127A3692012-03-15015 March 2012 Memo from M. Murphy to G. Wilson, Subj: Safety Evaluation Regarding Vermont Yankee Nuclear Power Station Core Plate Hold Down Bolt Inspection Plan and Analysis ML11321A2282011-11-17017 November 2011 Third Quarter 2011 Performance Review Memorandum ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML1115704052011-06-0606 June 2011 Notice of Meeting with Entergy Operations, Inc., to Discuss Implementation of Quality Oversight and Verification Programs at Entergy Sites Including Actions Being Taken to Enhance Effectiveness ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML1107504052011-03-21021 March 2011 Notice of Meeting with Entergy Operations, Inc., to Discuss Fleetwide Submittal for Proposed Technical Specification and Quality Assurance Program Manual Changes Related to Unit Staff Qualification Requirements ML1100502522011-02-0909 February 2011 Memo to Chairman Jaczko Fm R. W. Borchardt, EDO Initiatives for Improved Communication of Groundwater Incidents ML1030101362010-10-28028 October 2010 Memorandum and Order (Ruling on Motion to Reopen Proffering New Contention) (LBP-10-19) ML1009904582010-04-0808 April 2010 Deviation from the Reactor Oversight Process to Provide Increase NRC Oversight to Specific Issues at Vermont Yankee Nuclear Power Station ML1009603212010-04-0505 April 2010 Request for Deviation from the Reactor Oversight Process Action Matrix to Provide Increased NRC Oversight of Specific Issues at Vermont Yankee ML1006401882010-03-0505 March 2010 Charter for the Groundwater Contamination Task Force ML0927301372009-10-0909 October 2009 Safety Evaluation by the Office of Nuclear Reactor Regulation Corporate Restructuring Conversion of Companies and Stock Split-Off by Entergy Nuclear Operations, Inc and Subsidiaries ML0915200092009-06-0808 June 2009 Forwarding of Supplement 1 to NUREG 1907 to the ACRS ML0913308232009-05-13013 May 2009 Summary of Annual Assessment Mtg - Vermont Yankee - 4/16/09 ML0904005422009-02-17017 February 2009 Audit Plan for Review of Confirmatory Analyses for the Core Spray and Reactor Recirculation Outlet Nozzles at the Vermont Yankee Nuclear Power Station ML0820601722008-08-0808 August 2008 Docketing of Additional Information Pertaining to the License Renewal Application of the Vermont Yankee Nuclear Power Station ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0805606272008-02-27027 February 2008 Advisory Committee on Reactor Safeguards Review of the Vermont Yankee Nuclear Power Station License Renewal Application - Safety Evaluation Report ML0802205082008-01-31031 January 2008 01/08/2008 Summary of Meeting Between the NRC Staff and Entergy Nuclear Operations, Inc. to Discuss the Response to a Request for Additional Information Pertaining to the Vermont Yankee License Renewal ML0801505932008-01-17017 January 2008 December 2007 Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations (10 CFR) Section 2.206 ML0733001522007-11-26026 November 2007 Summary of Telephone Conference Call Held on October 16, 2007, Between U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Audit Questions Pertaining to the Vermont Yankee Nuclear Power Station License Renewa ML0721804332007-08-0808 August 2007 Summary of Telephone Conference Call Held on July 18, 2007, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Requests for Additional Information Pertaining to the Vermont Yankee Nuclear Power S ML0721805222007-08-0808 August 2007 Summary of Telephone Conference Call Held on June 29, 2007, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Vermont Yankee Nuclear Power St ML0718301872007-07-10010 July 2007 06/01/2007 Summary of Telephone Conference Call Between the NRC and Entergy Nuclear Operations, Inc., Concerning Items Pertaining to the Vermont Yankee License Renewal Safety Evaluation Report ML0716303702007-07-10010 July 2007 Trip Report Summarizing May 29, 2007 Visit to Vermont Yankee Nuclear Power Plant Regarding the License Renewal Environmental Review ML0713103192007-05-0808 May 2007 FRN - Plant License Renewal, June 5, 2007 ML0706101802007-05-0101 May 2007 Trip Report for a Trip Taken to Vermont, Massachusetts and New Hampshire ML0714104342007-04-25025 April 2007 Handouts to Applicants (Folder 3) ML0707406912007-04-0303 April 2007 ACRS Review of the Vermont Yankee Nuclear Power Station, License Renewal Application - Safety Evaluation Report ML0705305612007-02-20020 February 2007 Y020070028 - E-mail Hoch, NRR, to Becker, State of Vermont, Seismic and Flood Questions from Anr ML0704000852007-02-13013 February 2007 G20070068/LTR-07-0060/SECY-2007-0019 - Draft Supplemental Environmental Impact Statement for License Renewal of Vermont Yankee - Letters to Senator Leahy, Senator Sanders, Representative Welch from Luis Reyes ML0703605602006-11-0808 November 2006 Y020070028 - Informal Vermont Yankee Seismic and Hydrology Questions ML0627900712006-10-12012 October 2006 2006/10/12-Summary of a Telephone Conference Call Held on September 14, 2006, Between the U.S. NRC and Entergy Nuclear Operations, Inc, Concerning Information Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Applicatio ML0627202182006-09-29029 September 2006 2006/09/29-Summary of a Telephone Conference Call Held on August 10, 2006, Between the U.S. NRC and Entergy Nuclear Operations, Inc., Concerning Information Pertaining to the Vermont Yankee Nuclear Power Station License Renewal Application ML0625801872006-09-14014 September 2006 2006/09/14-Audit Trip Report Regarding Entergy Nuclear Vermont Yankee, LLC, License Renewal Application for Vermont Yankee Power Station, Dated January 29, 2006 ML0617303972006-07-11011 July 2006 2006/07/11-Summary of Environmental Site Audit Related to the Review of the License Renewal Application for Vermont Yankee Nuclear Power Station 2019-11-18
[Table view] |
Text
October 13, 2004 MEMORANDUM TO: Chairman Diaz Commissioner McGaffigan Commissioner Merrifield FROM: Luis A. Reyes /RA/
Executive Director for Operations
SUBJECT:
VERMONT YANKEE NUCLEAR POWER STATION - EXTENDED POWER UPRATE REVIEW SCHEDULE PURPOSE:
This memorandum notifies the Commission that the staffs scheduled review completion date for the Vermont Yankee Nuclear Power Station (VYNPS) extended power uprate (EPU) license amendment request will be delayed primarily due to concerns regarding the steam dryer analysis. In addition, supplemental information is needed from the licensee to address technical issues raised during the engineering inspection recently performed at VYNPS.
BACKGROUND:
On September 10, 2003, Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (Entergy or the licensee), submitted an EPU license amendment request to the Nuclear Regulatory Commission (NRC) for VYNPS. The proposed amendment would allow an increase in the maximum authorized power level from 1593 megawatts thermal (MWt) to 1912 MWt (i.e., an increase of approximately 20 percent). In a letter dated February 20, 2004, the NRC staff informed Entergy that the staff had completed its acceptance review of the VYNPS EPU license amendment application and established a forecast review completion date of January 31, 2005.
REVIEW STATUS:
From the early stages of the VYNPS EPU review, the NRC staff has emphasized that steam dryer integrity was an area receiving a very high level of attention by the NRC due to industry operating experience with steam dryer failures following EPU implementation. Although the steam dryer performs a non-safety-related function, it must maintain its structural integrity to prevent the occurrence of loose parts in the reactor pressure vessel or attached piping systems that could degrade the ability of safety-related components to perform their safety function.
CONTACT: Rick Ennis, NRR/DLPM 301-415-1420
The Commissioners During the course of the review, in order to resolve the steam dryer concerns, the NRC staff has requested additional information, held three public meetings with Entergy, and performed an audit of the steam dryer analysis at the General Electric office in San Jose, California.
Based on review of the information provided in the application, the supplements received through October 7, 2004 (Supplements 1 through 19), and the results of the audit, the NRC staff has determined that the information submitted by the licensee to date does not yet provide sufficient assurance that the VYNPS steam dryer will remain capable of maintaining its structural integrity under EPU conditions. During the audit and the most recent public meeting, Entergy staff indicated that further information will be submitted to address the NRC staff concerns related to steam dryer integrity.
In addition to the steam dryer concerns, information is needed from the licensee to address technical issues raised during the engineering inspection recently performed at VYNPS.
Entergy has recently submitted some of this information. The remaining information is expected to be submitted in the near future.
SCHEDULE IMPACT:
The next major milestone in the VYNPS EPU review schedule is for the staff to provide a draft Safety Evaluation (SE) to the Advisory Committee on Reactor Safeguards (ACRS). This milestone supports an ACRS subcommittee meeting that is presently scheduled for November 2004, and an ACRS full-committee meeting in December 2004. Based on the current status of the review, the draft SE cannot be completed in time to support the ACRS meetings. Therefore, the staff has notified the ACRS that the November and December meetings need to be rescheduled.
Following receipt and review of the supplemental information, the staff will coordinate with the ACRS to reschedule the meetings. At that time, the staff will also further assess the overall review schedule and establish a new forecast review completion date. At present, it is clear that the forecast review completion date of January 31, 2005, will be delayed by at least several months. The NRC staff will not approve the VYNPS EPU, or any other changes to a reactors license, unless we can conclude that the proposed change can be executed in a manner that ensures the publics health and safety.
The Commissioners NEXT STEPS:
Following receipt of this memorandum by the Commission, the NRC staff will contact senior management at Entergy to inform them of the schedule impact and issue a letter to Entergy documenting the review status.
cc: SECY OGC DOC OCA OPA CFO
The Commissioners NEXT STEPS:
Following receipt of this memorandum by the Commission, the NRC staff will contact senior management at Entergy to inform them of the schedule impact and issue a letter to Entergy documenting the review status.
cc: SECY OGC DOC OCA OPA CFO DISTRIBUTION:
Public REnnis TScarbrough TMadden, OCA PDI-2 Reading DSkay CWu RBores, OCA JDyer WRuland RJasinski CAnderson, RGN-I RBorchardt JStang TJKim, EDO DFlorek, RGN-I BSheron RBarrett CMiller, EDO DPelton, RGN-I TMarsh CGrimes RVirgilio, STP ACRS JLyons EImbro SBurnell, OPA BPoole, OGC CHolden KManoly DScrenci, OPA VBucci, OIG AHowe DTerao NSheehan, OPA ADAMS Accession No: ML042640055 OFFICE PDI-VY/PM PDI-2/LA TECH ED EMEB/BC PDI-III/D OGC NAME REnnis CRaynor PKleene EImbro WRuland BPoole DATE 10/07/04 10/07/04 9/21/04 9/22/04 9/23/04 10/5/04 OFFICE PDI-VY/SC PDI-D DLPM/D NRR/D EDO NAME AHowe CHolden JLyons for JDyer LReyes TMarsh DATE 9/29/04 09/23/04 09/24/04 10/12/04 10/13/04