MONTHYEARML22314A0752022-11-10010 November 2022 2B - Exam Administrative Items - Normal Release ML22034A3992022-02-16016 February 2022 Enclosure 1 - IP 71130.03 Cy 2021 - IR 8 Baseline Inspection Completion ML22034A3952022-02-16016 February 2022 Enclosure 3 - IP 96001 CY2021 - IR 8 Baseline Inspection Completion ML22034A3972022-02-16016 February 2022 Enclosure 2 - IP 92707 CY2021 - IR 8 Baseline Inspection Completion ML18338A0882018-12-0404 December 2018 Attachment FormerFAQResponses_11302018 ML18180A2602018-06-29029 June 2018 NFPA 805 FAQ 10-0059 - NFPA 805 Monitoring ML18073A3582018-03-15015 March 2018 NRC Staff Comments FAQ 18-0015 ML17235B1482017-08-23023 August 2017 U.S. Nuclear Regulatory Commission - Tornado Missile Risk Evaluator (TMRE) Methodology Topics and Methodology Feedback ML16315A2892016-11-10010 November 2016 Attachment 5 EPRI RETRAN-3D Computer Code Manuals, NP-7450(A) RA-16-003, Attachment 5 EPRI RETRAN-3D Computer Code Manuals, NP-7450(A)2016-11-10010 November 2016 Attachment 5 EPRI RETRAN-3D Computer Code Manuals, NP-7450(A) ML18039A8562016-06-0202 June 2016 Fpra FAQ 16-0011 - Cable Tray Ignition - Draft ML14191B2622014-07-10010 July 2014 NFPA 805 Transition FAQ 14-0070, Revision 0 ML13170A3282013-06-13013 June 2013 Special Inspection Question & Answers ML1214300352012-05-21021 May 2012 NFPA 805 Transition FAQ 12-0062, Revision 1 ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML1204105892012-02-10010 February 2012 NFPA 805 Transition FAQ 10-0059, Revision 5 ML1204105852012-02-10010 February 2012 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 4 ML1203201932012-02-0101 February 2012 NFPA 805 Transition FAQ 10-0059, Revision 4 ML1202603842012-01-13013 January 2012 FAQ Revision NFPA 805 Monitoring ML1201903132012-01-13013 January 2012 NFPA 805 Transition FAQ 10-0059, Rev 3 ML1202603722012-01-13013 January 2012 NFPA 805 Monitoring ML1202604252012-01-13013 January 2012 FAQ-1 - NFPA 805 Monitoring ML1202604402012-01-13013 January 2012 FAQ - NFPA 805 Monitoring ML1128600532011-09-30030 September 2011 NRC Staff Comments on FAQ 59R2 ML1127304102011-09-30030 September 2011 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 2 RA-11-025, Enclosure 1, Attachment 2 - Duke Energy Corporation and Progress Energy, Inc. Organization Charts Post Merger2011-09-0202 September 2011 Enclosure 1, Attachment 2 - Duke Energy Corporation and Progress Energy, Inc. Organization Charts Post Merger ML1123401522011-08-19019 August 2011 NFPA 805 Transition FAQ 10-0059, Rev 2 ML1111804812011-04-21021 April 2011 NFPA 805 Transition FAQ 10-0059, Rev 1 ML1109105082011-03-31031 March 2011 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 0 (Part 2) ML0933507512010-01-14014 January 2010 Temporary Instruction 2515/180, Managing Fatigue ML0916101892009-06-0303 June 2009 NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 2, Bus Duct Counting Guidance for High Energy Arcing Faults ML0909905112009-04-29029 April 2009 Enclosure 1: Shearon Harris Regulatory Audit Participants ML1020301612009-04-12012 April 2009 Tritium Concern Talking Points ML1019402162009-04-12012 April 2009 Offsite Notification to State/Local Agencies Regarding Tritium Release Onsite - EN 44951 ML0909305002009-04-0303 April 2009 Afpb Staff Response to NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 1 ML1020301722009-04-0101 April 2009 Tritium Questions and Answers ML0908500122009-03-26026 March 2009 NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 1, Bus Duct Counting Guidance for High Energy Arching Faults ML0902902182009-01-22022 January 2009 NFPA 805 Transition Pilot Plant FAQ 07-0030 ML1019402762008-12-0202 December 2008 Nuclear Condition Report for Tritium in Groundwater NEI 04-02, NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2, Lessons Learned - NEI 04-02 B-2 Table2008-09-12012 September 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2, Lessons Learned - NEI 04-02 B-2 Table ML0825904662008-09-12012 September 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2, Lessons Learned - NEI 04-02 B-2 Table ML0914201382008-09-0909 September 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2 - Clean Version ML0821000342008-07-24024 July 2008 NFPA 805 Transition Pilot Plant FAQ 07-0038, Revision 1 ML0813006972008-05-0909 May 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 2 ML0809101362008-03-28028 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 1, Lessons Learned - NEI 04-02 B-2 and B-3 Tables ML0807004112008-03-10010 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 1, Clarification of 10 CFR 50.48(c), 50.48(a), and GDC 3. ML0807001572008-03-10010 March 2008 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 5 ML0806704192008-03-0707 March 2008 CDBI Findings ML0735500252007-12-20020 December 2007 NFPA 805 Transition Pilot Plant FAQ 07-0036, Revision 1 ML0735500212007-12-20020 December 2007 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 4 2022-02-16
[Table view] |
Text
FAQ Number 07-0035 FAQ Revision 0 FAQ Title Bus Duct Counting Guidance for High Energy Arching Faults Plant: Harris Date: June 1, 2007
Contact:
Dave Miskiewicz Phone: 919.546.7588 Email: David.Miskiewicz@pgnmail.com Distribution: (NEI Internal Use) 805 TF FPWG FRATF RIRWG BWROG PWROG Purpose of FAQ:
Clarification/enhancement of Ignition Source counting guidance for High Energy Arcing Faults (HEAF) in NUREG/CR-6850, supporting NFPA-805 Fire PRA application.
Is this Interpretation of guidance? Yes / No Proposed new guidance not in NEI 04-02? Yes / No Details:
NEI 04-02 guidance needing interpretation (include section, paragraph, and line numbers as applicable):
New attachment on interpretation issues Circumstances requiring guidance interpretation or new guidance:
Pilot discussions and benchmarking of NUREG/CR-6850 for Task 6, Fire Ignition Frequency, has shown inconsistency in the treatment of High Energy Arcing Faults (Bin 16).
There is a need to resolve these issues to prevent future rework and to reduce burden associated with uncertainty treatment. This topic has impact on the NFPA-805 pilots, non-pilots and other users of NUREG/CR-6850.
The guidance provided in NUREG/CR-6850 for Task 6, Fire Ignition Frequency (Section 6.5.6, Bin 16), states:
Bin 16 - High-Energy Arcing Faults (Plant-Wide Components): High-energy arcing faults are associated with switchgear and load centers. Switchyard transformers and isolation phase buses are not part of this bin. For this bin, similar to electrical cabinets, the vertical segments of the switchgear and load centers should be counted. Additionally, to cover potential explosive failure of oil filled transformers (those transformers that are associated with 4.16 or 6.9kV switchgear and lower voltage load centers) may be included in vertical segment counts of the switchgear.
Page 1 of 2 FAQ 07-0035 Rev. 0
FAQ Number 07-0035 FAQ Revision 0 FAQ Title Bus Duct Counting Guidance for High Energy Arching Faults The current guidance is silent regarding the treatment of bus duct. Preliminary discussions between the user community and the NUREG authors indicate that some specific guidance is needed to assure more consistent treatment of bus duct.
Detail contentious points if licensee and NRC have not reached consensus on the facts and circumstances:
Potentially relevant existing FAQ numbers:
This guidance is specific to the characterization of bus duct for Bin 16 HEAF determination.
The characterization and counting of electrical cabinets for Bin 16 determination is addressed by FAQ 06-0017.
Response Section:
Proposed resolution of FAQ and the basis for the proposal:
Because bus duct terminates at electrical cabinets, the HEAF counted for the electrical cabinet would also include those bus duct events and no further counting is necessary.
Basis:
The response is consistent with the guidance currently provided in NUREG/CR-6850.
Without additional guidance provided by the authors of NUREG/CR-6850, there is no basis for when or how to count bus duct.
If appropriate, provide proposed rewording of guidance for inclusion in the next Revision:
Page 2 of 2 FAQ 07-0035 Rev. 0