IR 05000275-11-406 and IR 05000323-11-406, on 06/30/2011, Diablo Canyon, Units 1 & 2, NRC Special Inspection (Cover Letter)
ML112232269
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 08/11/2011
From: Hay M
Plant Support Branch-1
To: Conway J
Pacific Gas & Electric Co
References
IR-11-406
Download: ML112232269 (4)


Text

UNITED STATES NUC LEAR REGULATOR Y C OMMISSI ON ust 11, 2011

SUBJECT:

DIABLO CANYON POWER PLANT - NRC SPECIAL INSPECTION REPORT 05000275/2011406 AND 05000323/2011406

Dear Mr. Conway:

On June 30, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed the onsite portion of a Special Inspection pursuant to Inspection Procedure 93812 at your Diablo Canyon Power Plant, Units 1 and 2, to follow up on a May 15, 2011, event involving a potential security issue.

The enclosed inspection report documents the inspection results, which were discussed at an exit meeting on June 30, 2011, with Mr. K. Peters, Vice President, Engineering and Projects, and other members of your staff.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system, ADAMS.

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. Pacific Gas and Electric -2-In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,

/RA/

Michael C. Hay, Chief Plant Support Branch-1 Division of Reactor Safety Docket Nos.: 50-275, 50-323 License Nos.: DPR-80, DPR-82 Nonpublic Enclosure: NRC Inspection Report 05000275/2011406 and 05000323/2011406 w/Attachment:

Supplemental Information cc w/o enclosure:

Thomas R. Baldwin Manager, Regulatory Services Pacific Gas and Electric Company Diablo Canyon Power Plant Mail Code 104/5/536 P.O. Box 56 Avila Beach, CA 93424 James R. Becker Site Vice President Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 3, Mail Station 104/6/601, Avila Beach, CA 93424 Mr. Kenneth J. Peters Vice President, Engineering Services Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 3, Mail Station 104/6/603 Avila Beach, CA 93424 Pacific Gas and Electric -3-Jennifer Post, Esq.

Pacific Gas & Electric Co.

77 Beale Street, Room 2496 Mail Code B30A San Francisco, CA 94105 Pacific Gas and Electric -4-Distribution w/enclosure:

Ronald Albert (Ronald.Albert@nrc.gov), Chief, Reactor Security Oversight Branch Shyrl Coker, (Shyrl.Coker@nrc.gov) NSIR/DSO/DDSO, TWFN Mail Stop: T-3A5M Clay Johnson, (Clay.Johnson@nrc.gov), NSIR/DSO/DDSO/SPEB, TWFN 3D43 Branch Chief, RI DRS (James.Trapp@nrc.gov)

Branch Chief, RII DRS/PSB2 (Michael.Ernstes@nrc.gov)

Branch Chief, RIII DRS/PSB (Richard.Skokowski@nrc.gov)

Senior Resident Inspector (Michael.Peck@nrc.gov)

Electronic distribution by RIV:

Distribution w/o enclosure:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

Acting DRP Deputy Director (Jeff.Clark@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

Acting DRS Deputy Director (Robert.Caldwell@nrc.gov)

Resident Inspector (Laura.Micewski@nrc.gov)

Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov)

Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov)

Project Engineer, DRP/B (Greg.Tutak@nrc.gov)

Project Engineer, DRP/B (Nestor.Makris@nrc.gov)

DC Administrative Assistant (Agnes.Chan@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Alan.Wang@nrc.gov)

Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource RIV/ETA: OEDO (John.McHale@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

Security-Related Complete Report - OUO:

SUNSI Review Completed: JRL ADAMS: Yes Initials: JRL Non-Publicly Available Sensitive Letter Only:

SUNSI Review Completed: JRL ADAMS: Yes Initials: JRL Publicly Available Non-Sensitive RIV:PSB Peer Review C:PSB1 C:DRP/B C:PSB1 JRLarsen WSifre MHay GMiller MHay

/RA/ /RA/ /RA/ /RA/ /RA/

8/8/11 8/3/11 8/9/11 8/9/11 8/11/11 OFFICIAL COPY T=Telephone E=E-Mail F=FAX