Notice of Intent to Reinitiate Scoping Process for Diablo Canyon Power Plant, Units 1 and 2 License Renewal Application
ML15140A564
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 07/01/2015
From: Brian Wittick
License Renewal Projects Branch 2
To: Halpin E
Pacific Gas & Electric Co
Wentzel M, 415-6459
References
FOIA/PA-2016-0438
Download: ML15140A564 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 1, 2015 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA 93424

SUBJECT:

NOTICE OF INTENT TO REINITIATE THE ENVIRONMENTAL SCOPING PROCESS FOR THE REVIEW OF THE DIABLO CANYON POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. Halpin:

On November 23, 2009, the U.S. Nuclear Regulatory Commission (NRC) received the Pacific Gas & Electric Company (PG&E) application for renewal of Operating Licenses DPR-80 and DPR-82 for Diablo Canyon Power Plant (DCPP), Units 1 and 2. In support of the application and in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, PG&E also submitted an environmental report for DCPP. This letter provides information related to the NRC staffs environmental review of the application.

By letter dated January 20, 2010, the NRC staff notified PG&E of its intent to prepare a plant-specific supplement to the NRCs Generic Environmental Impact Statement for License Renewal of Nuclear Plants, (NUREG-1437), related to the review of the DCPP license renewal application. In conjunction with that notice, the NRC staff initiated an environmental scoping process, which ended on April 12, 2010. By letter dated May 31, 2011, prior to issuance of a draft plant-specific supplement to NUREG-1437, the NRC delayed all further milestones associated with the environmental review of the DCPP license renewal application to allow PG&E time for the completion of certain seismic studies to address concerns raised during the State of Californias Coastal Zone Management Act consistency review. On December 22, 2014, and February 25, 2015, PG&E amended its environmental report to incorporate additional information necessary for the NRC staff to complete its review of the DCPP license renewal application.

Because of the length of time since the completion of the original scoping period, the NRC staff has prepared a Notice of Intent advising the public that the NRC intends to reopen the scoping process to aid in the identification of issues that may have emerged since completion of the last scoping period. Enclosed is a copy of the Notice of Intent, which has been forwarded to the Office of the Federal Register for publication.

E. Halpin Pursuant to 10 CFR 51.28, PG&E is invited to participate in the environmental scoping process.

As discussed in the enclosed notice, the NRC staff is providing the public with the opportunity to participate in two environmental scoping meetings to be held on August 5, 2015. The meetings will be held at the Courtyard by Marriott San Luis Obispo, 1605 Calle Joaquin Road, San Luis Obispo, CA 93405. The first session will be held in the afternoon, and the second session, covering the same subjects, will be held in the evening. The NRC will present an overview of the environmental review process and will describe how the process will be implemented for the review of the DCPP license renewal applications. A separate NRC meeting notice with a more detailed agenda is forthcoming. You will be provided a copy of that notice.

In the interim, should you have any questions regarding the scoping process, please contact the NRCs Environmental Project Manager, Mr. Michael Wentzel, at 301-415-6459, or by e-mail at michael.wentzel@nrc.gov.

Sincerely,

/RA/

Brian D. Wittick, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

As stated cc w/encl: Listserv

ML15140A6601 (PKG)

ML15140A564 (LTR)

ML15140A594 (FRN) *concurrence via email OFFICE LA:DLR* PM:RPB2:DLR OGC BC:RPB2:DLR NAME SWoods MWentzel SUttal BWittick (NLO)

DATE 5/29/15 6/1/15 6/3/15 7/1/15

Letter to Edward D. Halpin from Brian D. Wittick dated July 1, 2015

SUBJECT:

NOTICE OF INTENT TO REINITIATE THE ENVIRONMENTAL SCOPING PROCESS FOR THE REVIEW OF THE DIABLO CANYON POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsOgcMailCenter Resource RidsNrrPMDiabloCanyon Resource


MWentzel BWittick RPlasse YDiaz-Sanabria SLingam SUttal, OGC JLindell, OGC EWilliamson, OGC THipschman, SRI JReynoso, RI GMiller, RIV WWalker, RIV DMcIntyre, OPA VDricks, OPA WMaier, RIV AMoreno, OCA MWaters, EDO