Category:Letter
MONTHYEARIR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20243012023-05-15015 May 2023 Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 ML22271A6202022-09-29029 September 2022 Notification of Shearon Harris Nuclear Power Plant Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000400/2023010 ML22258A1262022-09-14014 September 2022 NRC Operator Licensing Examination Approval 05000400/2022301 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22227A0682022-09-0202 September 2022 Alternative to Certain Inservice Testing Requirements in the American Society of Mechanical Engineers Code for Operation and Maintenance for Certain Target Rock Solenoid Valves IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) IR 05000400/20224032022-08-23023 August 2022 Security Baseline Inspection Report 05000400/2022403 ML22126A0082022-08-0909 August 2022 Issuance of Amendment No. 194 Revise Technical Specifications Related to Reactor Protection System Instrumentation P7 IR 05000400/20220022022-08-0505 August 2022 Integrated Inspection Report 05000400/2022002 ML22161B0332022-07-28028 July 2022 Issuance of Amendment No. 193 Regarding Revision of Surveillance Requirements to Remove Shutdown Limitation IR 05000400/20220112022-07-20020 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000400 2022011 IR 05000400/20224022022-06-30030 June 2022 Material Control and Accounting Program Inspection Report 05000400/2022402 (OUO Removed) IR 05000400/20220102022-06-13013 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010 ML22138A4012022-05-26026 May 2022 Project Manager Reassignment ML22101A2822022-05-0606 May 2022 Regulatory Audit Summary Related to the Review of License Amendment Regarding Revising the Flood Hazard Protection Scheme IR 05000400/20220012022-05-0404 May 2022 Integrated Inspection Report 05000400/2022001 IR 05000400/20224012022-03-24024 March 2022 Security Baseline Inspection Report 05000400/2022401 ML22020A0072022-03-10010 March 2022 Issuance of Amendment No. 192 Regarding Removal of Extraneous Content and Requirements from the Renewed Facility Operating License and Technical Specifications ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) ML21351A4722022-02-10010 February 2022 Issuance of Amendment No. 190 Regarding Revision to Containment Spray Nozzle Test Frequency IR 05000400/20210042022-02-0404 February 2022 Integrated Inspection Report 05000400/2021004 ML22034A5352022-02-0202 February 2022 Notification of Licensed Operator Initial Examination 05000400/2022301 2024-01-30
[Table view] Category:License-Operator
MONTHYEARML22258A1262022-09-14014 September 2022 NRC Operator Licensing Examination Approval 05000400/2022301 ML22034A5352022-02-0202 February 2022 Notification of Licensed Operator Initial Examination 05000400/2022301 ML21167A3352021-06-16016 June 2021 301 ADAMS 2A-3 ML21167A3162021-06-16016 June 2021 301 ADAMS 2A-1 ML21167A2922021-06-16016 June 2021 301 ADAMS 2B ML21167A3272021-06-16016 June 2021 301 ADAMS 2A-2 ML21111A3502021-04-21021 April 2021 March 2021 GFE- Public.Docx ML21106A2142021-04-0707 April 2021 301 Retake Approval Letter ML21060B1762021-03-0101 March 2021 301 Retake Corporate Notification Letter ML21028A4052021-01-25025 January 2021 301 ADAMS 2A-2 ML21028A4472021-01-25025 January 2021 301 ADAMS 2A-3 ML21028A3392021-01-25025 January 2021 301 ADAMS 2A-1 ML21028A1002021-01-18018 January 2021 301 ADAMS 2B ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML21004A2352021-01-0404 January 2021 301 Exam Report Items - RO as Given Written Exam ML21004A2362021-01-0404 January 2021 301 Exam Report Items - SRO as Given Written Exam ML20311A1042020-11-0606 November 2020 Operator Licensing Written Examination Approval 05000400/2020301 RA-20-0075, Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19058A6322019-07-0101 July 2019 Issuance of Amendments to Revise Emergency Action Level Schemes to Incorporate Clarifications Provided by Emergency Preparedness FAQs RA-19-0237, Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations2019-05-15015 May 2019 Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations ML19100A1872019-04-10010 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for Shearon Harris Nuclear Plant ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 ML18240A1592018-08-28028 August 2018 301 Exam Administrative Items (ADAMS-2D) ML17192A4472017-07-11011 July 2017 301 Admin Items (ADAMS-2C)- Delay Release 2 Yrs ML17192A4452017-07-11011 July 2017 301 Final Items (ADAMS-2B)- Delay Release 2 Yrs ML17192A4432017-07-11011 July 2017 301 Draft Items (ADAMS-2A)- Delay Release 2 Yrs ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16218A4992016-08-30030 August 2016 Initial Exam 2016301 Final SRO Written with Answer Key - Delay Release 2 Years ML16218A4942016-08-30030 August 2016 Initial Exam 2016301 Final RO Written with Answer Key - Delay Release 2 Years ML16197A5772016-07-12012 July 2016 Operator Licensing Written Examination Approval 05000400/2016301 ML16054A5432016-02-19019 February 2016 Notification of Licensed Operator Initial Examination 05000400/2016301 ML15013A2492015-01-13013 January 2015 Initial Exam 2014-302 Draft Administrative JPM ML15013A2752015-01-13013 January 2015 Initial Exam 2014-302 General Correspondence ML15013A2712015-01-13013 January 2015 Initial Exam 2014-302 Final Administrative JPMs ML15013A2672015-01-13013 January 2015 Initial Exam 2014-302 Final Sim_IN-Plant JPMs ML15013A2622015-01-13013 January 2015 Initial Exam 2014-302 Final Simulator Scenarios ML15013A2512015-01-13013 January 2015 Initial Exam 2014-302 Final Administrative Documents ML15013A2452015-01-13013 January 2015 Initial Exam 2014-302 Draft Sim_IN-Plant JPMs ML15013A2412015-01-13013 January 2015 Initial Exam 2014-302 Draft Simulator Scenarios ML15013A2382015-01-13013 January 2015 Initial Exam 2014-302 Draft SRO Written Exam ML15013A2352015-01-13013 January 2015 Initial Exam 2014-302 Draft RO Written Exam ML15013A2312015-01-13013 January 2015 Initial Exam 2014-302 Draft Administrative Documents ML15013A5232015-01-0808 January 2015 December 2014 - Shearon Harris Generic Fundamentals Examination Results IR 05000400/20143022014-12-30030 December 2014 NRC Operator License Examination Report 05000400/2014302 ML14338A0362014-12-0303 December 2014 302 Final RO Written Exam ML14338A0382014-12-0303 December 2014 302 Final SRO Written Exam ML14262A3262014-09-18018 September 2014 Notification of Change in Licensed Operator Initial Examination 05000400/2014302 Date RA-14-0012, Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations2014-06-0303 June 2014 Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations ML14090A4552014-03-31031 March 2014 301 Retake Final Administrative Documents 2022-09-14
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML22258A1262022-09-14014 September 2022 NRC Operator Licensing Examination Approval 05000400/2022301 ML22034A5352022-02-0202 February 2022 Notification of Licensed Operator Initial Examination 05000400/2022301 ML21167A3162021-06-16016 June 2021 301 ADAMS 2A-1 ML21167A3352021-06-16016 June 2021 301 ADAMS 2A-3 ML21167A2922021-06-16016 June 2021 301 ADAMS 2B ML21167A3272021-06-16016 June 2021 301 ADAMS 2A-2 ML21106A2142021-04-0707 April 2021 301 Retake Approval Letter ML21060B1762021-03-0101 March 2021 301 Retake Corporate Notification Letter ML21028A4052021-01-25025 January 2021 301 ADAMS 2A-2 ML21028A4472021-01-25025 January 2021 301 ADAMS 2A-3 ML21028A3392021-01-25025 January 2021 301 ADAMS 2A-1 ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML21004A2362021-01-0404 January 2021 301 Exam Report Items - SRO as Given Written Exam ML21004A2352021-01-0404 January 2021 301 Exam Report Items - RO as Given Written Exam ML20311A1042020-11-0606 November 2020 Operator Licensing Written Examination Approval 05000400/2020301 RA-20-0075, Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations2020-03-16016 March 2020 Response to NRC Regulatory Issue Summary 2020-01 Preparation and Scheduling of Operator Licensing Examinations RA-19-0237, Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations2019-05-15015 May 2019 Catawba Station, Shearon Plant, McGuire Station, Oconee Nuclear Station and H.B. Robinson Plant - Response to NRC Regulatory Issue Summary 2019-02 Preparation and Scheduling of Operator Licensing Examinations ML19100A1872019-04-10010 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for Shearon Harris Nuclear Plant ML18240A1592018-08-28028 August 2018 301 Exam Administrative Items (ADAMS-2D) ML17192A4472017-07-11011 July 2017 301 Admin Items (ADAMS-2C)- Delay Release 2 Yrs ML17192A4452017-07-11011 July 2017 301 Final Items (ADAMS-2B)- Delay Release 2 Yrs ML17192A4432017-07-11011 July 2017 301 Draft Items (ADAMS-2A)- Delay Release 2 Yrs ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16218A4992016-08-30030 August 2016 Initial Exam 2016301 Final SRO Written with Answer Key - Delay Release 2 Years ML16218A4942016-08-30030 August 2016 Initial Exam 2016301 Final RO Written with Answer Key - Delay Release 2 Years ML16197A5772016-07-12012 July 2016 Operator Licensing Written Examination Approval 05000400/2016301 ML16054A5432016-02-19019 February 2016 Notification of Licensed Operator Initial Examination 05000400/2016301 ML15013A2512015-01-13013 January 2015 Initial Exam 2014-302 Final Administrative Documents ML15013A2752015-01-13013 January 2015 Initial Exam 2014-302 General Correspondence ML15013A2712015-01-13013 January 2015 Initial Exam 2014-302 Final Administrative JPMs ML15013A2672015-01-13013 January 2015 Initial Exam 2014-302 Final Sim_IN-Plant JPMs ML15013A2622015-01-13013 January 2015 Initial Exam 2014-302 Final Simulator Scenarios ML15013A2352015-01-13013 January 2015 Initial Exam 2014-302 Draft RO Written Exam ML15013A2492015-01-13013 January 2015 Initial Exam 2014-302 Draft Administrative JPM ML15013A2452015-01-13013 January 2015 Initial Exam 2014-302 Draft Sim_IN-Plant JPMs ML15013A2412015-01-13013 January 2015 Initial Exam 2014-302 Draft Simulator Scenarios ML15013A2312015-01-13013 January 2015 Initial Exam 2014-302 Draft Administrative Documents ML15013A2382015-01-13013 January 2015 Initial Exam 2014-302 Draft SRO Written Exam ML15013A5232015-01-0808 January 2015 December 2014 - Shearon Harris Generic Fundamentals Examination Results IR 05000400/20143022014-12-30030 December 2014 NRC Operator License Examination Report 05000400/2014302 ML14338A0382014-12-0303 December 2014 302 Final SRO Written Exam ML14338A0362014-12-0303 December 2014 302 Final RO Written Exam ML14262A3262014-09-18018 September 2014 Notification of Change in Licensed Operator Initial Examination 05000400/2014302 Date RA-14-0012, Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations2014-06-0303 June 2014 Response to NRC Regulatory Issue Summary 2014-05, Preparation and Scheduling of Operator Licensing Examinations ML14090A4552014-03-31031 March 2014 301 Retake Final Administrative Documents ML14090A4572014-03-31031 March 2014 301 Retake Final Admin JPMs ML14090A4562014-03-31031 March 2014 301 Retake Final Simulator In-plant JPMs ML14090A4522014-03-31031 March 2014 301 Retake Draft Admin JPMs ML14090A4452014-03-31031 March 2014 301 Retake Draft Sim In-plant JPMs ML14090A4392014-03-31031 March 2014 301 Retake Draft Administrative Documents 2022-09-14
[Table view] |
See also: IR 05000400/2016301
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
July 12, 2016
Duke Energy Progress, Inc.
ATTN: Mr. Donald L. Griffith
Training Manager
Harris Energy & Env. Center
Shearon Harris Nuclear Power Plant
P. O. Box 327, State Road 1127
New Hill, NC 27562-0165
SUBJECT: SHEARON HARRIS NUCLEAR POWER PLANT - OPERATOR LICENSING
WRITTEN EXAMINATION APPROVAL 05000400/2016301
Dear Mr. Griffith:
The purpose of this letter is to confirm the final arrangements for the upcoming operator
licensing written examination at Shearon Harris Nuclear Power Plant.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator
license applications submitted in connection with this examination and separately provided a list
of approved applicants to your office. The NRC staff administered operating tests to these
individuals, as applicable, the week of July 11, 2016.
The NRC has approved the subject written examination and hereby authorizes you to
administer the written examination on July 19, 2016, in accordance with Revision 10 of NUREG-
1021, Operator Licensing Examination Standards for Power Reactors.
This examination has undergone extensive review by my staff and representatives responsible
for operator training at your facility. Based on this review, I have concluded that the
examination meets the guidelines of NUREG-1021 for content, operational, and discrimination
validity. By administering this examination, you also agree that it meets NUREG-1021
guidelines, and is appropriate for measuring the qualifications of licensed operators at your
facility. If you determine that this examination is not appropriate for licensing operators at your
facility, do not administer the examination and contact me at (404) 997-4662.
Please contact your Chief Examiner, Mr. Michael Donithan, at (404) 997-4538, if you have any
questions or identify any errors or changes in license level (RO or SRO) or type of examination
(partial or complete written examination and/or operating test) specified for each applicant on
the list of approved applicants.
Sincerely,
/RA/
Eugene F. Guthrie, Chief
Operations Branch 2
Division of Reactor Safety
Docket No.: 50-400
License No.: NPF-63
July 12, 2016
Duke Energy Progress, Inc.
ATTN: Mr. Donald L. Griffith
Training Manager
Harris Energy & Env. Center
Shearon Harris Nuclear Power Plant
P. O. Box 327, State Road 1127
New Hill, NC 27562-0165
SUBJECT: SHEARON HARRIS NUCLEAR POWER PLANT - OPERATOR LICENSING
WRITTEN EXAMINATION APPROVAL 05000400/2016301
Dear Mr. Griffith:
The purpose of this letter is to confirm the final arrangements for the upcoming operator
licensing written examination at Shearon Harris Nuclear Power Plant.
The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator
license applications submitted in connection with this examination and separately provided a list
of approved applicants to your office. The NRC staff administered operating tests to these
individuals, as applicable, the week of July 11, 2016.
The NRC has approved the subject written examination and hereby authorizes you to
administer the written examination on July 19, 2016, in accordance with Revision 10 of NUREG-
1021, Operator Licensing Examination Standards for Power Reactors.
This examination has undergone extensive review by my staff and representatives responsible
for operator training at your facility. Based on this review, I have concluded that the
examination meets the guidelines of NUREG-1021 for content, operational, and discrimination
validity. By administering this examination, you also agree that it meets NUREG-1021
guidelines, and is appropriate for measuring the qualifications of licensed operators at your
facility. If you determine that this examination is not appropriate for licensing operators at your
facility, do not administer the examination and contact me at (404) 997-4662.
Please contact your Chief Examiner, Mr. Michael Donithan, at (404) 997-4538, if you have any
questions or identify any errors or changes in license level (RO or SRO) or type of examination
(partial or complete written examination and/or operating test) specified for each applicant on
the list of approved applicants.
Sincerely,
/RA/
Eugene F. Guthrie, Chief
Operations Branch 2
Division of Reactor Safety
Docket No.: 50-400
License No.: NPF-63
x PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE x NON-SENSITIVE
ADAMS: Yes ACCESSION NUMBER: ML16197A577 X SUNSI REVIEW COMPLETE
OFFICE RII:DRS RII:DRS RII:DRS
SIGNATURE JHK MD/EFG EFG
NAME JKIRBY MDONITHAN EGUTHRIE
DATE 7/12/2016 7/12/2016 7/12/2016 7/ /2016 7/ /2016 7/ /2016
E-MAIL COPY? NO NO YES NO YES NO YES NO YES NO
OFFICIAL COPY