IR 05000263/2011010

From kanterella
Revision as of 19:51, 15 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
IR 05000263-11-010; on 9/12/2011-12/15/2011: Monticello Nuclear Generating Plant; Special Inspection
ML11363A182
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/29/2011
From: Reynolds S
Division of Reactor Safety III
To: O'Connor T
Northern States Power Co
References
IR-11-010
Download: ML11363A182 (32)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 December 29, 2011 Mr. Timothy J. O'Connor Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota

2807 West County Road 75 Monticello, MN 55362-9637 SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT NRC SPECIAL INSPECTION TEAM (SIT) REPORT 05 000263/20110 10 Dear Mr. O'Connor

On December 15, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a Special Inspection at your Monticello Nuclear Generating Plant (MNGP)

to evaluate the facts and circumstances surrounding the September 2, 2011, identification of substantial blockage in the intake building fire protection pipin The determination to initiate a Special Inspection was made on September 12, 2011 , based on the risk and deterministic criteria specified in Management Directive 8.3, "NRC Incident Investigation Program," and due to the equipment performance issues that occurre The Special Inspection began on September 12, 2011

, and was conducted in accordance with Inspection Procedure 93812, "Special Inspection." The basis for initiating the special inspection and the focus areas for review are detailed in the Special Inspection Charter (Attachment 2 of the enclosure). The enclosed inspection report documents the inspection results, which were discussed at the interim meeting on October 1 4, 2011, and at the exit meeting on December 15, 2011, with yourself and other members of your staf The inspection examined activities conducted under your license s as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license The inspectors reviewed selected procedures and records, observed activities, interviewed plant personnel, and evaluated the facts and circumstances surrounding the event, as well as actions taken by your staff in response to the unexpected equipment conditions. Based on the results of this inspection, one NRC-identified finding of very low safety significance was identifie The finding was not associated with a violation of regulatory requirement Additionally, four licensee-identified violations which were determined to be of very low safety significance are listed in this repor The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Polic T. O'Connor-2- If you contest th e subject or severity of the NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission

- Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Monticello Nuclear Generating Plant

. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Steve n A. Reynolds, Director Division of Reactor Safety Docket No. 50-263 License No. DPR-22

Enclosure:

Inspection Report 05000263/201 1010 w/Attachment s: 1. Supplemental Information 2. Special Inspection Team Charter 3. Timeline of Events

REGION III==

Docket No.: 50-263 License No

.: DRP-22 Report No.: 05000263/201 1010 Licensee: Northern States Power Company, Minnesota Facilities

Monticello Nuclear Generating Plant Location: Monticello, Minnesota Dates: September 12 through December 15, 2011 Inspectors:

C. Tilton, Senior Reactor Engineer, DRS D. Szwarc, Reactor Engineer, DRS P. Voss, Monticello Resident Inspector, DRP Approved by:

A. M. Stone , Chief Engineering Branch 2 Division of Reactor Safety

1 Enclosure

SUMMARY OF FINDINGS

IR 05000263/201101 0; 9/12/2011-12/15/2011: Monticello

Nuclear Generating Plant; Special Inspection.

This report covers a 5-week period of inspection by two regional inspectors and a resident inspector. One Green finding was identified by the inspectors. The finding was not associated with a violation of regulatory requirements

. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not apply may be (Green) or be assigned a severity level after NRC management review.

The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.

A. N RC-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

Green.

The inspectors identified a finding of very low safety significance (Green) involving the licensee's failure to accomplish activities affecting quality in accordance with procedures. Specifically, the licensee failed to incorporate operating experience in accordance with procedures. This impacted the licensee's ability to implement an effective aging management program for the fire protection system. No violation of NRC requirements was identified.

The performance deficiency was determined to be more than minor because it was associated with the Mitigating Systems cornerstone attribute of Protection Against External Factors (Fire) and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Using IMC 0609, Appendix F, Fire Protection SDP, and the Monticello SPAR model, the inspectors determined that this finding had very low safety significance. The inspectors did not identify an associated crosscutting aspect for this finding. (Section 4OA5

.7b.(1))

B. Licensee-Identified Violations

Four violations of very low safety significance identified by the licensee were reviewed by the inspectors.

Corrective actions planned or taken by the licensee were entered into the licensee's corrective action program.

These violations and corrective action tracking numbers are listed in Section 4OA7 of this report.

REPORT DETAILS

Event Summary Local fire suppression in the intake structure consists of an automatic pre

-action sprinkler system. When the deluge valve, located in the intake tunnel, actuates, water enters the sprinkler system piping. The Intake Structure Sprinkler System Drain valve, FP 1, is located within a short distance downstream of the deluge valve.

During testing, water passing through this open valve demonstrates the deluge valve opened as expected. The Sprinkler Inspectors Test valve, FP-171-10, is located a distance downstream, at the opposite end of the Intake Structure.

On August 26, 2011, during the performance of Surveillance Test 0323-01, "Fire Protection System Sprinkler Functional Tests," the licensee found blockage at valve FP-171-10. At this time , the shift manager declared the fire system non

-functional.

The licensee established a 14-day fire protection system impairment (consistent with Procedure 0323-01) and the previously established continuous compensatory fire watch with backup suppression remained in effect. Maintenance personnel confirmed the valve was plugged with debris and removed the blockage. On August 28, 2001, when the licensee performed Surveillance Test 0323-0 1 as the Post Maintenance Test (PMT) to verify the blockage was removed from valve FP 10, additional blockage was found in the piping.

After further investigation, the licensee found significant blockage in the fire sprinkler line up stream of valve FP-17l-10 , as well as in three vertical risers to sprinkler heads.

The majority of the blockage was on the west end of the intake structure which is above Division 2 residual heat removal service water (RHRSW) pumps and motors

. Laboratory analysis performed later determined the blockage consisted of internal pipe corrosion byproducts.

The fin e corrosion byproducts resulted in a clay-like substance.

On September 2, 2011, after additional inspections of the subject fire system piping, the licensee concluded the sprinkler suppression piping was not capable of operating per its design due to the significant fouling.

The condition was reported to the NRC under I0 CFR Part 50.72(b)(3)(ii)(B) as an unanalyzed condition affecting plant safety systems.

4OA5 Other Activities

- Special Inspection (93812)

Inspection Scope A Special Inspection was initiated following the NRC's review of the deterministic and conditional risk criteria specified in Management Directive 8.3, "NRC Incident Investigation Program." The inspection was conducted in accordance with NRC Inspection Procedure (IP)93812, "Special Inspection." The Special Inspection Charter, dated September 12, 2011, is included as Attachment 2. The team reviewed technical and design documents, procedures, maintenance records, corrective action documents, interviewed station personnel, gathered information from the plant computers and event recorders with alarm printouts, and performed physical walkdowns of plant equipment. A list of specific documents reviewed is provided in Attachment 1.

3 Enclosure As detailed in the Special Inspection Charter (Attachment 2), the following items were reviewed and associated results obtained.

.1 Perform a walkdown of the

intake structure to evaluate the condition of the fire suppression system, identify any potential impact on safety-related equipment and c omponents, and evaluate the adequacy of compensatory measures.

a. Inspection Scope

The inspectors performed a walkdown of the intake structure with the licensee on September 13, 2011

, in order to determine if a credible fire could develop in the room that could affect multiple safety

-related systems, structures, or components. The inspectors evaluated the location of safe shutdown equipment, the extent of fixed and transient combustibles, and the adequacy of other existing fire protection features in the area. The inspectors also assessed the suitability of compensatory measures taken by the licensee following identification of the degradation of the sprinkler system.

b. Findings and Observations

The intake structure comprises Fire Area IX / Fire Zone 23A and contains various pumps and associated motors

two circulating water pumps, four RHRSW pumps, electric fire pump, screen wash/fire pump, four emergency service water pumps, two makeup pumps, two seal water pumps, and the fire system jockey pump. The area also contains motor control center 123/113, the electric fire pump control panel, and the screen wash/fire pump control panel. Two parallel non-safety-related cable trays run in the north/south direction and two cable trays run in the east/west direction in the area.

Most of the pump motors in the room contain small amount s of lubricating oil (five to nine quarts each). The circulating water pump motors contain 38 gallons of lubricating motor oil; however, these motors are not located on the main floor. The four RHR SW pump motors each contain 13 gallons of lubricating oil and are separated from other equipment by a shroud. The area as a whole has a very low fire load of approximately 13,000 British Thermal Units per square foot (Btu/ft2).

Based on the walkdown of the intake structure

, the inspectors determined due to the low fire loading, the most likely fire scenario in the area would be limited to the ignition source (e.g. pump motor) and not spread throughout the area.

The inspectors verified the licensee implemented appropriate compensatory measures in the area for the fire impairment. The compensatory measures included a continuous fire watch and verifying the functionality of hose stations located in the area.

.2 Evaluate the licensee's actions to correct the current condition.

This includes assessing the licensee's extent of condition review and subsequent inspection or testing of affected piping.

a. Inspection Scope

The inspectors reviewed the licensee's actions pertaining to restoring the intake structure pre

-action sprinkler system to service. The inspectors reviewed the licensee's post maintenance testing, engineering evaluation for restoring functionality (EC 18475),

4 Enclosure and the as-left hydraulic analysis. The inspectors also reviewed the licensee's extent of condition review of other similar systems.

b. Findings and Observations

The licensee declared the intake structure pre

-action sprinkler system non

-functional on September 2, 2011 upon discovery of silting and corrosion products in the piping. Subsequently

, the licensee test ed the sprinkler system branch lines in the intake structure to determine the extent of the clogging. The licensee performed visual inspections by removing portions of the piping and sprinklers, examining the pipe internals through the use of a video borosc ope, and using radiography. Through these examinations

, the licensee concluded a significant portion of the piping had blockage, with the most severe blockage occurring at the west end of the room where portions of the sprinkler system piping at the far west end of the room were 100% block ed. In order to return the system to service

, the licensee flushed all of the sprinkler system branch lines, replaced the piping at the far west end of the room, and replaced all of the sprinklers in the room. After flushing the lines, the licensee performed confirmatory inspections using a video boroscope and radiography. These additional inspections showed no loose material remained in the piping.

The licensee performed an engineering evaluation (EC 18745) to evaluate the intake structure fire protection system piping capability following restoration activities. The evaluation included a revised hydraulic analysis that concluded the sprinkler system could provide a sufficient amount of water to the area.

The licensee's extent of condition review identified dry

-pipe pre-action sprinkler system s were also installed in the emergency diesel generators (EDG) 11 and 12 rooms. The inspectors reviewed work order (WO) 00341476 which documented flushing of debris found in the EDG 11 sprinkler system in 2007. However, the licensee did not have documentation showing a flush was also performed for the EDG 1 2 sprinkler system. Following questions from the inspectors

, the licensee inspected the piping in the EDG 12 sprinkler system on September 21, 2011 and confirmed it was free of obstructions.

.3 Evaluate the function of the fire protection system in the degraded condition.

a. Inspection Scope

The inspectors discussed with the licensee the functionality of the intake structure pre

-action sprinkler system in the degraded condition.

b. Findings and Observations

To evaluate the as

-found condition of the intake structure pre

-action sprinkler system, the licensee performed a hydraulic analysis (MN11 160-100). This analysis considered the reduced piping diameter which existed on September 2, 2011, based on piping blockage measurements taken by the licensee. The licensee also performed a transport analysis (0067

-0039-01) to determine whether the debris discovered in the intake structure pre

-action sprinkler system would be transported through the system and block water flow through the sprinklers.

Based on the results of these analyses, the licensee concluded the system would have remained function al in the degraded state and the debris in the system would have pass ed flow through the sprinkler heads.

5 Enclosure The inspectors challenged the licensee's conclusion that the debris in the piping would likely have been transported through the piping as particles and would hav e been flushed out through the sprinkler heads. The inspectors believed the debris would likely have caused the sprinkler heads to become clogged and not pass water through. As a result of the inspectors concerns

, the licensee did not take credit for past functionality of the sprinkler system

.

.4 Evaluate the adequacy of the design of the fire protection sprinkler system.

a. Inspection Scope

The inspectors reviewed the licensee's original system design and hydraulic analysis to determine if the system had been appropriately designed. The inspectors compared the design of the system to applicable NFPA standards.

b. Findings and Observations

The licensee installed a combined dry

-pipe and pre

-action sprinkler system in the intake structure in 1983. This system contains sprinklers attached to piping designed to be kept dry. Heat detectors were installed in the area and would actuate (open) a deluge valve to fill the piping with water. The sprinklers would also react to a heat source due to a fire and operate to allow water to flow.

The inspectors determined the original system design met the requirements of National Fire Protection Association (NFPA) 13, "Standard for the Installation of Sprinkler Systems." The licensee had committed to the 1983 edition of this standard. However, the licensee determined through their Root Cause Evaluation (RCE) that the system was not installed per design. Specifically, the licensee determined the slope of the piping was not correct and therefore

, resulted in water not draining properly. A licensee identified violation related to this deficiency is discussed in Section

4OA7 of this report.

However, the inspectors identified a properly designed dry

-pipe system would also be susceptible to corrosion. The inspectors noted the NFPA standards do not specify the gas to be used to pressurize the dry portion of the system nor the piping material. The piping in the sprinkler system was constructed of carbon steel and the licensee pressurized the dry

-pipe portion of the system with oxygen. Since 1983, the system was filled with water numerous times due to inadvertent actuation or testing. Each of these times, the system was drained and pressurized with oxygen. The corrosion resulting from the interaction of the oxygen and water with the carbon steel piping was accelerated by the numerous wetting and drying cycles. In conclusion, the system was designed properly but the improper installation and multiple actuations lead to a buildup of corrosion products in the piping

.

.5 Determine if there are potential generic implications for other plants relying upon raw water sources for their fire protection systems.

a. Inspection Scope

The inspectors reviewed industry standards and requirements for testing dry-pipe pre-action systems. The inspectors also reviewed operating experience information related to these type s of systems

.

6 Enclosure

b. Findings and Observations

The inspectors identified potential generic implications for other plants with a combined dry-pipe and pre

-action sprinkler system. These insights will be submitted to regional management for further consideration.

.6 Determine whether verifying water flow through the fire protection piping is require

d by industry standards or NRC requirements. Evaluate whether the licensee's current and past surveillance procedures meet these industry standards or NRC requirements.

a. Inspection Scope

The inspectors reviewed the licensee's fire protection program commitments, NRC regulations and requirements, and applicable NFPA standards to determine requirements for verifying the functionality of water

-based fire suppression systems.

b. Findings and Observations

The licensee installed the pre

-action sprinkler system in 1983 in accordance with NFPA 13, the standard in effect at the time of installation. Section 1-11.2 of NFPA 13 , only required a hydrostatic test to be performed on a new system. The inspectors verified the licensee did perform a hydrostatic test (WRA 83

-02978) when the system was installed. The standard did not contain any requirements for conducting periodic flow tests or obstruction examinations.

The inspectors noted the licensee used procedure 0324, "Fire Protection System

- Sprinkler System Tests," to test the functionality of the intake structure sprinkler system. Step 45 of this procedure , required the licensee to open the intake structure sprinkler system test valve FP 10. Step 45 further stated that discharge of water from test valve verified operation of the deluge valve and confirmed the piping was not blocked. The requirement to observe water flow from the inspectors test valve was added to Procedure 0324 on June 4, 2010. The required frequency for performing the test was once every 24 months and August 26, 2011 was the first time the test had been conducted using the new requirements. The inspectors determined that prior to the August 26, 2011 event, the licensee did not have a requirement for verifying water flow through the inspectors test valve in the intake structure.

Therefore, the inspectors determined that there were no specific NRC requirements for verifying water flow in sprinkler systems. The NRC approved the licensee's fire protection program in which the licensee committed to installing and maintaining the system in accordance with applicable NFPA standards (NFPA 13

- 1983 edition in MNGP case).

In addition, the inspectors noted NFPA 25, "Standard for the Inspection, Testing, and Maintenance of Water

-Based Fire Protection Systems" contained additional inspection and testing requirements for periodic obstruction investigations. Specifically, Table 5.1.1.2 of NFPA 25 (2011 edition) requires an internal obstruction inspection of piping to be conducted every five years. Section 14.3.3 of NFPA 25, further requires a complete flushing be performed if sufficient obstructions are found. The licensee was not committed to this standard and therefore was not performing periodic obstruction investigations. However, as stated in the root cause evaluation as an extent of conditi on corrective action, the licensee planned to conduct a gap analysis of NFPA 25 and 7 Enclosure current plant requirements. The licensee created a preventative maintenance change request (PMCR) # 00024867 on October 4, 2011 to perform an inspection of the sprinkler main in the intake structure at the flushing valves. The PMCR stated that if significant blockage is found, further branch inspections are to be performed and to flush the sprinkler main and the branches. The inspectors noted that this would meet the intent of NFPA 25.

.7 Evaluate license renewal requirements/commitments completed to date and those which could be potentially affected by fouling in the fire protection piping.

a. Inspection Scope

The inspectors reviewed the License Renewal Application (LRA), Aging Management Programs related to Fire Water and Open Cycle Cooling Water (OCCW), implementing procedures, surveillance results and work orders

. The inspectors also interviewed individuals responsible for the programs.

b. Findings and Observations

(1) Failure to Follow Fire Water Aging Management Program Implementing Procedure Introduction
The inspectors identified a finding of very low safety significance (Green) involving the licensee's failure to accomplish activities affecting quality in accordance with procedures. Specifically, the licensee failed to incorporate operating experience in accordance with procedures. This impacted the licensee's ability to implement an effective aging management program for the fire protection system. No violation of NRC requirements was identified.

Description

The NRC approved the Monticello Nuclear Generating Plant License Renewal Application (LRA) on November 8, 2006. As part of the LRA, the licensee committed to manag e the effects of aging of their structure, systems and components by implementing aging management programs (AMPs.) Appendix B of LRA describes in detail the purpose and implementing strategies of the AMPs. The Fire Water AMP is defined in Section B.2.1.18. Each AMP has ten elements, which jointly, effectively and efficiently provide reasonable assurance that aging effects will be managed so that the systems and components within the scope of th e program will continue to perform their intended functions consistent with the current licensing basis through the period of extended operation. Operating experience is one of the elements listed in each AMP.

Section 3.10 of PBD/AMP

-014, "Fire Water System Aging Management Program Basis Document," describes the licensee's approach in implementing operating experience. It states, in part:

"Industry and plant experience is evaluated for system performance impacts. Performance issues are documented and evaluated in the site Corrective Action Program. With regard to items that potentially affect the Fire Water System Program, the OE [Operating Experience] is forwarded to the program owner for evaluation and potential action that may include incorporating the issue into existing inspection or test procedures. Consequently, aging related issues are captured and evaluated within the corrective action system."

8 Enclosure The period of extended operation for the Monticello site began September 9, 2010 which corresponds to the date the aging management programs became effective.

On September 12, 2011, while reviewing PBD/AMP

-014 and a sample of corrective actions, the inspectors noted the licensee did not incorporate seven instances of internal and external operating experience. These included: (external) In 2006, Nine Mile Point identified an obstruction of sprinkler heads in fire water pre-action fire zones caused by lake water sediment and corrosion products as documented in an external operating experience report.

(external) In 2006, Forsmark (Sweden) reported clogged fire protection sprinkler nozzles as documented in an external operating experience report.

(internal) In 2007, the licensee identified blockage caused by corrosion products in the emergency diesel generator (EDG) sprinkler system. The EDG sprinkler is a dry

-pipe pre-action system similar to the one located in the intake structure. The licensee initiated a CAP document to evaluate the condition in the intake structure sprinkler system; however, the licensee did not initiate actions to assess the Fire Water AMP.

(external) In 2008, Prairie Island (also a Northern States Power Company licensee)identified silting and plugging of their turbine

-generator bearing fire protection system. (external) In 2008, Crystal River identified internal corrosion and slime buildup in their pre-action sprinkler system as documented in an external operating experience report. (internal) In 2009, the licensee identified blockage in the intake structure sprinkler system while performing a PMT. The licensee initiated a CAP document to evaluate the condition; however, the licensee did not initiate actions to assess the Fire Water AMP. (external) In 2010, La Salle reported clogging of the pre-action spray system located in a laboratory as documented in an external operating experience report.

The inspectors were concerned because as of September 9, 2010, the licensee had not incorporated the previously discussed operating experience in their Fire Water Aging Management Program. Procedure PBD/AMP-014 required an evaluation of industry and plant experience for system performance impacts. In addition, the licensee failed to evaluate and take action of incorporating these issues into existing inspections and/or test procedures.

Specifically, the licensee originally believed no aging mechanism existed for the suppression piping inside of the intake building because the system was a dry system. Therefore, they assessed locations susceptible to degradation for further sampling and inspection without taking into account this section of the fire protection system. However, the piping in the sprinkler system was constructed of carbon steel and the licensee pressurized the dry

-pipe portion of the system with oxygen. Since 1983, the system was filled with water numerous times due to inadvertent actuation or testing. Each of these times, the system was drained and pressurized with oxygen. The 9 Enclosure corrosion resulting from the interaction of the oxygen and water with the carbon steel piping was accelerated by the numerous wetting and drying cycles. As indicated in the operating experience above and in the actual operation of the suppression system, dry systems have experience aging effects, specifically internal corrosion, due to periodic wetting of the internal surfaces. As required by the aging management program, th e licensee should have assessed this operating experience with respect to equipment aging effects and establish appropriate corrective or followup actions to be taken.

In addition, the inspectors noted the licensee did not identify aging as a contributing cause in the root cause evaluation for the most recent blockage in the intake building sprinkler system. Therefore, no CAP documents were initiated to address and correct the effects of aging. Moreover, the licensee failed to identify this incident as a potential operating experience needing to be addressed as required by PBD/AMP

-014.

The licensee acknowledged the inspectors' concerns and initiated corrective action program document AR 1308266 to address the issue. As part of their corrective actions, the licensee plans to perform an evaluation of the Fire Water AMP to ensure aging is managed and systems are capable of performing their intended functions. The inspectors reviewed the licensee's action request and had no concerns.

Analysis:

The inspectors determined the failure to incorporate operating experience was contrary to the requirements of procedure PBD/AMP

-014, "Fire Water System Aging Management Program Basis Document" and was a performance deficiency. This impacted the licensee's ability to implement an effective aging management program for the fire protection system. The performance deficiency was determined to be more than minor because it was associated with the Mitigating Systems cornerstone attribute of Protection Against External Factors (Fire) and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, the availability and reliability of the fire suppression system were affected because by not incorporating operating experience, the aging management program could not provide reasonable assurance that aging effects will be managed so that the systems will continue to perform its intended functions consistent with the current licensing basis through the period of extended operation.

The inspectors determined the finding could be evaluated using risk-assessment tools of IMC 0609, Appendix F, "Fire Protection Significance Determination Process," and performing bounding analyses using the Monticello Standard Plant Analysis Risk (SPAR Model), Version 8.15. The inspectors reviewed and discussed the licensee's bounding risk-assessment documented in Probabilistic Risk

-Assessment (PRA) Memo 11

, Revisions 0 and 1, "Risk

-Assessment of Intake Fire Suppression System Plugging." The inspectors determined the finding was of very low safety significance (Green) because the risk increase using bounding assumptions was below 1E

-6. The inspectors determined the cause of the performance deficiency (failure to incorporate operating experience) was not associated with a crosscutting aspect as defined in IMC 0310, "Components Within the Cross

-Cutting Areas."

Enforcement

No violation of regulatory requirements occurred. (FIN 05000263/2011010

-01, Failure to Follow Fire Water Aging Management Program Implementing Procedures).

10 Enclosure

.8 Determine

if there is a performance deficiency through a review of the licensee's corrective a ction program to identify prior occurrences of fire protection system blockage or silting and applicable operating e xperience.

a. Inspection Scope

The inspectors independently searched the corrective action program (CAP) for CAP documents, work orders

, and action requests potentially related to the event.

These CAPs included documentation of previous instances where the licensee may have had indications of the condition of the intake structure fire protection sprinkler system, and documentation of several spurious actuations of the system.

In addition, the inspectors reviewed copies of procedures related to the events described in the CAP documents, to determine whether the licensee's actions were in compliance with their procedures. The inspectors also reviewed CAP documents generated by the licensee's root cause evaluation team to determine whether the team had identified these deficiencies during the course of their own review.

b. Findings and Observations

The inspectors identified several instances where the licensee had opportunities to recognize the condition of the intake structure fire protection system, but failed to take appropriate actions.

The inspectors determined the licensee's root cause team had independently identified the same performance deficiencies; therefore, the performance deficiencies described below and documented in Section

4OA7 of this report were

determined to be licensee

-identified:

On August 11, 2007

, the licensee performed work order (WO) 341476 to flush the emergency diesel generator (EDG) sprinkler system.

Maintenance personnel noted that no water flowed through the inspectors test valve and the licensee took corrective actions (AR 01106463) to determine the cause of the blockage and to remove the obstructions

. The licensee developed a corrective action (WO 342675

-02) to flush the intake structure sprinkler system because both systems were of the same design.

This work order was postponed ten times and was not performed as of the August 26, 2011 blockage discovery in the intake structure sprinkler system inspectors test valve.

The inspectors determined that this was a licensee identified violation of 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Action," for the failure to promptly identify and correct this condition.

The obstructions in the intake structure sprinkler system would likely have been identified sooner had the licensee completed WO 342675

-02 to flush the sprinkler system.

In April 2009, the licensee performed work on the RHRSW system under WO 381724, which required the removal of portions of the fire protection sprinkler piping in the intake structure. Following the work, the fire protection piping was reinstalled, and on April 30, 2009, during the post-maintenance test (PMT), workers again found blockage in the piping which prevented the water from reaching the test valve. When the condition was identified, CAP 01180222 was written to document the blockage condition that was found during the PMT. However, when the condition was evaluated during a functionality assessment of the system, the assessment was limited and narrowly focused.

The inspectors determined that this was a licensee identified NCV for a failure to follow 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the inadequate Fire Protection System 11 Enclosure functionality assessment. Had the assessor properly pursued this information during the functionality assessment, the extent of the blockage in the piping would have been identified.

On April 30, 2009, when site personnel were unable to complete the step which required water flow through the inspector test, the PMT should have been documented as a failed PMT. Instead, all procedure steps and acceptance criteria were marked off as being complete, and the test documentation contained no information about the blockage condition and its adverse impact on the ability to complete the test. As a result, individuals reviewing the completed test did not recognize that the acceptance criteria had not been met, and the procedure was processed as a successfully completed procedure. The inspectors determined this was a licensee

-identified NCV for a failure to follow 10 CFR Part 50, Appendix B, Criterion XI, "Test Control." The inspectors concluded that correctly controlling and documenting the results of this test, including documentation of the failure to meet the acceptance criteria, would have allowed the organization to recognize the impact of the blockage on the equipment.

.9 Review the licensee's

r oot cause evaluation plan and schedule. Evaluate whether t he root cause evaluation plan is of sufficient depth and breadth. Confirm that the time allowed to perform the root cause evaluation is commensurate with the safety significance of this issue.

a. Inspection Scope

The inspectors reviewed the licensee's root cause evaluation for this condition and associated corrective actions. The inspectors performed an independent root cause analysis before reviewing the licensee's root cause.

b. Findings and Observations

The licensee began a root cause evaluation (RCE) for this condition on September 12, 2011. The RCE was completed on October 6, 2011. The licensee identified improper installation of the pipe as the root cause of the condition as the system was not able to drain properly and therefore corrosion byproducts accumulated towards the end of the intake building fire protection header.

The inspectors determined this was a licensee

-identified NCV of License Condition 2.C.4 for the failure to implement and maintain in effect all provisions of their approved fire protection program. Specifically, the installation of the intake structure pre

-action sprinkler system did not comply with NFPA 13 (1983) section 3-11.1.1, which requires that all sprinkler pipe and fittings shall be so installed that the system may be drained and resulted in the plugging of the sprinkler system. This prevented water from flowing through sprinkler heads and caused the system to be non

-functional. This licensee identified NCV is further documented in Section

4OA7 of this inspection report.

Although, the inspectors agree improper installation caused the material to remain in the system, the inspectors identified numerous weaknesses in the licensee's root cause analysis and subsequent corrective actions

The inspectors determined the licensee failed to identify other possible causes that contributed to this condition and potentially exacerbated it. The fire protection sprinkler in the intake building is a pre-action type system which is kept dry and 12 Enclosure pressurized with air. Pressurization with air create d an oxygen-rich environment which accelerates corrosion in carbon steel pipe.

In addition, system actuation

- either planned or unplanned

- fill ed the pipe with water, resulting in a wetting and drying cycle. This condition increases the rate of oxidation in the pipe as it strips off the layer of corrosion formed (which acted as a barrier between the oxygen and the metal and therefore minimized additional corrosion) and exposes new metal to oxygen. Neither of these two possible contributing causes was analyzed or assessed in the licensee's root cause evaluation.

The licensee identified seven instances where Operating Experien ce from traditional industry sources was relevant to the condition at Monticello, but was not implemented at the site using their existing OE program. The inspectors noted that the corrective action for this item was to benchmark industry guidance on the threshold for evaluating industry OE, such as the seven examples identified during the root cause evaluation.

While benchmarking can be a very useful tool to assess consistency with industry, the inspectors were concerned the licensee was not evaluating how their current program failed, resulting in insufficient reviews of the identified seven OEs previously described.

The licensee initiated AR 01308276 to evaluate this issue.

The inspectors noted the extent of cause should result in the identification of other equipment, programs, processes, organizational factors, or performance areas that are vulnerable to the same or similar causes. In addition, it should identify the extent to which these areas have been impacted by those causes. The inspectors observed that the licensee's extent of cause was narrowly focused in its review of these areas. Specifically,

(1) the licensee's extent of cause was limited to evaluating other dry pipe sprinkler systems for improper pipe slope

, and

(2) did not include a review of other equipment installed during the same time period (subject to the same modification process

) as the affected fire protection piping. In addition, the inspectors noted that recent examples of the failure to translate design requirements into the installation of equipment were not evaluated in the extent of cause section of the report, such as the early 2011 failure to install fire protection piping for the main transformer in accordance with design requirements. At th at time, this installation error was discovered, not by a process the licensee had in place, but by an individual new to the project performing a system walkdown for orientation purposes.

The inspectors noted the licensee assessed the as

-left condition of the intake structure fire protection pipe using radiography test (RT) results they conducted to evaluate as

-found blockage when they initially discovered this incident. The inspectors questioned the adequacy of using RT results for determining wall thickness of pipes as the licensee's procedures dictate the preferred method to establish wall thickness of pipes is ultrasonic testing (UT). In addition, the RT indicated barely any degradation of pipe wall. The inspectors were concern because the extent of blockage found during this incident did not correspond to the insignificant degradation identified in the RTs. This discrepancy could lead to potentially undetected degradation in the intake structure fire protection pipe or somewhere else in the system. In addition, the inspectors were concern because for this specific application, UT gives a more accurate measurement of wall thickness than RT. As a result of the inspector's concern, the licensee conducted UT measurements and discovered significant degradation in the lower region of the pipe 13 Enclosure where water tended to form "puddles."

However, the degradation on these sections of pipe did not exceed the ASME minimum wall thickness requirements.

The inspectors also noted that the licensee's extent of condition actions included using NFPA 25 and NFPA 12a as references to perform a gap analysis, and using the results to revise inspection and testing methods. The NFPA code also includes specific sections on appropriate maintenance and related items. Following completion of the inspection, it remained unclear to the inspectors whether or not the licensee's gap analysis would include review and incorporation of relevant NFPA maintenance practices. Inclusion of a review of maintenance practices in the gap analysis would aid the identification of methods to further mitigate piping corrosion due to periodic wetting and drying of the pipe.

The inspectors concluded the licensee's root cause evaluation was not comprehensive. The licensee's approach was too focused therefore did not identify broader causes described in the weaknesses above. In addition, as stated in Section 4OA5.7, the licensee did not identify an aging mechanism as a contributing cause. After performing a detailed review of the licensee's corrective actions initiated as a result of the root cause evaluation, the inspectors determined the proposed corrective actions bounded the root cause evaluation weaknesses. Therefore, the inspectors concluded that weaknesses associated with the licensee's root cause evaluation did not represent a violation of NRC requirements.

4OA6 Management Meetings

1. Interim Meeting Summary On October 14, 2011, the inspectors presented the preliminary inspection results to Mr. T. O'Connor and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that proprietary information reviewed as part of this inspection was returned to the licensee

. 2.

Exit Meeting Summary

O n December 1 5, 2011, the inspector s presented the inspection results to Mr. T. O'Connor and other members of the licensee staff. The licensee acknowledged the issues presented.

4OA7 Licensee-Identified Violations

The following four violations of very low safety significance (Green) were identified by the licensee and are violations of NRC requirements which meet the criteria of Section 2.3.2 of the NRC Enforcement Policy for being dispositioned as an NCV.

The licensee identified a finding of very low safety significance (Green) and associated NCV of License Condition 2.C.4 through a planned surveillance test for the failure to implement and maintain in effect all provisions of their approved fire protection program. Specifically, the installation of the intake structure pre

-action sprinkler system did not comply with NFPA 13 (1983) section 3-11.1.1, which requires that all sprinkler pipe and fittings shall be so installed that the system may be drained and resulted in the plugging of the sprinkler system. This prevented water from flowing through sprinkler heads and caused the system to be no n-14 Enclosure functional. The performance deficiency was determined to be more than minor because it was associated with the Mitigating Systems cornerstone attribute of Protection Against External Factors (Fire) and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). The Region III Senior Risk Analyst (SRA)used the risk assessment tools of IMC 0609, Appendix F, Fire Protection SDP, and performed bounding analyses using the Monticello Standard Plant Analysis Risk (SPAR Model), Version 8.15. The SRA also reviewed and discussed the licensee's bounding risk assessment documented in PRA Memo 11-01-, Revisions 0 and 1, "Risk Assessment of Intake Fire Suppression System Plugging." The finding was determined to be of very low safety significance (green) because the risk increase using bounding assumptions was below 1E

-6. The licensee entered this issue into their corrective action program as AR 01305183, "Intake Fire Sprinkler Configuration Discrepancy," and restored the functionality of the sprinkler system by flushing the piping and replacing system components. The licensee further planned to modify the system to allow proper drainage in accordance with the design requirements.

The licensee identified a finding of very low safety significance (Green) and associated NCV of License Condition 2.C.4 for the failure to implement and maintain in effect all provisions of their approved fire protection program.

This includes adhering to the 10 CFR 50, Appendix B Quality Assurance Program requirements for the design, procurement, installation, testing and administrative controls for the fire protection program

. Title 10 CFR Part 50, Appendix B, Criterion XVI, "Corrective Action," requires, in part, that measures shall be established to assure that conditions adverse to quality, such as deficiencies are promptly identified and corrected. Contrary to the above, from August 21, 2007 until August 26, 2011, the licensee failed to promptly identify and correct a condition adverse to quality that resulted in the plugging of the intake structure sprinkler system.

Specifically, the licensee failed to perform corrective actions (work order 342675

-02) to flush the intake structure sprinkler system following a blockage event in the EDG rooms in 2007. The performance deficiency was determined to be more than minor because the plugging in the intake structure pre

-action sprinkler system was left uncorrected for four years and became a more significant safety concern.

The inspectors concluded that this finding was associated with the Mitigating Systems cornerstone.

The Region III SRA used the risk assessment tools of IMC 0609, Appendix F, Fire Protection SDP, and performed bounding analyses using the Monticello Standard Plant Analysis Risk (SPAR Model), Version 8.15.

The SRA also reviewed and discussed the licensee's bounding risk assessment documented in PRA Memo 11

, Revisions 0 and 1, "Risk Assessment of Intake Fire Suppression System Plugging."

The finding was determined to be of very low safety significance (Green) because the risk increase using bounding assumptions was below 1E

-6. The licensee flushed the system, restored functionality, and wrote AR 01303860 to document the multiple rescheduling.

The licensee identified a finding of very low safety significance (Green) and associated NCV of License Condition 2.C.4 for the failure to implement and maintain in effect all provisions of their approved fire protection program.

This includes adhering to the 10 CFR 50, Appendix B Quality Assurance Program requirements for the design, procurement, installation, testing and administrative controls for the fire protection program. Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, 15 Enclosure Procedures, and Drawings," requires, in part, that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions procedures, or drawings." Contrary to the above, on April 30, 2009, the license failed to follow procedure FP-OP-OL-01 "Operability/Functionality Determination

," when assessing identified blockage in the intake structure fire protection sprinkler piping. Specifically, the assessor failed to justify assumptions, perform an extent of condition

, and obtain additional condition bounding information to ensure an accurate assessment of the condition. The performance deficiency was determined to be more than minor because it was associated with the Mitigating Systems cornerstone attribute of Protection Against External Factors (Fire) and affected the cornerstone objective of ensuring the availability, reliability, a nd capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Using IMC 0609, Appendix F, Fire Protection SDP, and the Monticello SPAR model, the inspectors determined that this finding had very low safety significance. The licensee entered this issue into their corrective action program as AR 01304353, "Inaccurate functionality assessment for CAP 1180222," in order to perform further evaluation of the deficiency.

The licensee identified a finding of very low safety significance (Green) and associated NCV of License condition 2.C.4 for the failure to implement and maintain in effect all provisions of their approved fire protection program. This includes adhering to the 10 CFR 50, Appendix B Quality Assurance Program requirements for the design, procurement, installation, testing and administrative controls for the fire protection program. Title 10 CFR Part 50, Appendix B, Criterion XI, "Test Control," requires, in part, that "test results shall be documented and evaluated to assure that test requirements have been satisfied.

" Contrary to this requirement, on April 30, 2009, the licensee failed to document and evaluate the results of a PMT that did not meet all of its acceptance criteria. Specifically, when a step in the PMT required flow through the inspector test valve was not accomplished, the PMT was not annotated as failure and the PMT work order was signed off as complete without further evaluation

. The performance deficiency was determined to be more than minor because it was associated with the Mitigating Systems cornerstone attribute of Protection Against External Factors (Fire) and affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage).

Using IMC 0609, Appendix F, Fire Protection SDP, and the Monticello SPAR model, the inspectors determined that this finding had very low safety significance. The licensee entered this issue into their corrective action program as AR 01304348, "Failed PMT results not captured in PMT WO," in order to perform further evaluation of the deficiency

. ATTACHMENTS:

1. Supplemental information 2. Special inspection charter 3. Event timeline

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTAC

T Licensee

T. O'Connor, Site Vice President
J. Grubb, Plant Manager
P. Anderson, Regulatory Assurance Director
G. Sherwood, Program Engineering

Manager

P. Kissinger, Regulatory Assurance Manager
P. Young, Program Engineering Supervisor
B. Dixon, Program Engineering Supervisor
C. Bloink, Licensing Engineer

Nuclear Regulatory Commission

A. Stone, Chief, Division of Reactor Safety, Engineering Branch 2 LIST OF ITEMS OPENED, CLOSED AND DISCUSS

ED Opened and Closed

05000263/2011010

-01 FIN Failure to Follow Fire Water Aging Management Program Implementing Procedure

Attachment 1

LIST OF DOCUMENTS REVIEWED The following is a partial list of documents reviewed during the inspection. Inclusion on this list does not imply that the NRC inspector reviewed the documents in their entirety, but rather that selected sections or portions of the documents were evaluated as part of the overall inspection effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

CALCULATIONS

Number Description or Title

Date/Rev 81N301 Hydraulic Calculation for Intake Structure

10/06/83 MN11-995-160-100 Intake Structure Pre

-Action Sprinkler System Hydraulic Analysis 0 CORRECTIVE ACTION DOCUMENTS GENERATED DURING THE INSPECTIO

N Number Description or Title

Date 1302981 Gloves Were Not Used To Perform Inspection

09/08/11 1303597 Check Valve Has No Equipment ID

09/14/11 1303654 Block-Completed Service Water Inspect Form Lacks Detail

09/14/11 1303780 Lack Of EDG Sprinkler Flushing Documentation

09/14/11 1303860 Intake Sprinkler Flush WO Rescheduled Multiple Times

09/15/11 1304047 License Renewal Testing Performance

09/16/11 1304800 EC-18745 Had A Transcription Error

09/21/11 1308068 Intake Sprinkler RCE Didn't Specifically Address Age Mgmt

10/13/11 1308146 Need Guidance For Using SW Inspection Form For Fire Systems 10/13/11 1308180 CAP Screen

Team Failed to Record SCAQ Determination For A RCE 10/13/11 1308266 Fire Water OE Was Not Factored Into AMP 10/14/11 1308276 Wording of Action i n RCE is Not Specific

10/14/11 CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTIO

N Number Description or Title

Date 696791 Converted Issue No.:4002086 Title: 4" Gate Valve FP

-82-1 Is PR 02/25/04 1061683 Spurious actuation of Intake Structure deluge system

11/14/06 1066042 Intake Deluge activated during RHRSW run

2/07/06 1072672 Received unexpected fire system actuation in Intake

01/18/07 1092089 Spurious Intake HAD signal but deluge failed to actuate

05/10/07 1092335 Intake Sprinkler System spurious trip, Fire Pps Auto Start

05/13/07 1100115 Low 'A' RHR Room ESW flow

07/02/07 1105540 Actuation of Fire System During Battery Replacement of C

-371 08/06/07

Attachment 1

CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTIO

N Number Description or Title

Date 1105808 FP-152-2 EDG Room Deluge Trip Shortly After Reset

08/07/07 1106280 FME: EDG Deluge Seat Missing Rubber

08/10/07 1106463 Found sprinkler piping plugged during flush of EDG deluge

08/11/07 1180222 Intake Structure Sprinkler Blockage

04/30/09 1301107 Known Equip. issue adversely affects test completion

08/26/11 1301631 FP-171-10 failed PMT

08/31/11 1302334 Sprinkler Piping In Intake Plugged With Clay Like Debris

09/02/11 1302778 On 9/9/11, Intake Fire Suppress 14 day Impairment Exceeded

09/07/11 1303209 Response to fire impairment could be more aggressive

09/10/11 1303212 Opportunities were missed to resolve fire system blockage

09/10/11 1303860 Intake sprinkler flush WO rescheduled multiple times

09/15/11 1304047 License Renewal Testing Performance

09/16/11 1304348 Failed PMT Results Not Captured in PMT WO

09/19/11 1304353 Inaccurate Functionality Assessment for CAP 01180222

09/19/11 1304563 Drain path for IS Sprinkler piping not used

09/20/11 1305091 Security Preaction Fire Systems

- EOC 09/23/11 1305183 Intake fire sprinkler configuration discrepancy

09/23/11 1306728 Off-Gas Compressor Drain Line PM

10/03/11 1307159 EOC for removing items from TS and changes to screening

10/06/11 DRAWINGS Number Description or Title

Revision Fig 1 Fire Zone

23-A Intake Structure Pump Room

F01696 Color Coded Intake Fire Protection Piping

09/16/11 NH-36048 Fire Protection System Interior Locations

NH-36516 Fire Protection System Yard Areas

NH-36666 P&ID Screen Wash, Fire & Chlorination System Intake Structure 85 MISCELLANEOUS

Number Description or Title

Date/Rev NX-16995 Intake Structure Pre

-Action Sprinkler System (Vendor)

PRA-MEMO-11-014 Risk Assessment of Intake Fire Suppression System Plugging 1 PROCEDURES

Number Description or Title

Revision 0324 Fire Protection System

- Sprinkler System Tests

4 AWI-04.05.06 Post-Maintenance Testing

A.3-15-A Fire Zone 15A

- No. 12 DG Room: Strategy A.3

-15-A 7

Attachment 1

PROCEDURES

Number Description or Title

Revision A.3-23-A Fire Zone 23

-A Intake Structure Pump Room Strategy A.3

-23-A 11 PBD/AMP-007 Aging Management Program Basis Document; Open

-Cycle Cooling Water System Program

PBD/AMP-014 Aging Management Program Basis Document; Fire Water System 3 FP-OP-OL-01 Operability/ Functionality Determination

FG-PA-RCE-01 Root Cause Evaluation Manual

FP-PA-OE-01 Operating Experience Program

FP-PA-SW-1 SW/MIC Program

FP-PE-PHS-01 Program Health Process

FP-WM-PLA-01 Work Order Planning Process

Form 3590 Service Water System Inspection

Ops Man B.08.05-05 Operations Manual Section: Fire Protection, System

operation 52 ROOT CAUSE EVALUATIO

N Number Description or Title

Date/Rev QF-0433 RCE: Intake Structure Fire Sprinkler Piping Blockage

WORK DOCUMENTS

AND COMPLETED SURVEILLANCES Number Description or Title

Date/Rev WRA 83-02978 Intake Structure Pump Room Hydrostatic Test

2/02/83 WRA 92-5457 Replace Fire Protection Piping between valves FP 6&7

07/28/92 WO 00330915 FIR, Intake Deluge Failed to Actuate

05/11/07 WO 00308070

Replace Heat Detector For Intake Structure Deluge System

05/14/07 WO 00341476

Flush DG Deluge System Thru Valve Near FZ

-4375 and FP

-159 08/11/07 WO 00342675

FP-171-2 Intake Structure Sprinkler Valve Maintenance

08/21/07 WO 00384321

Intake Sprinkler Test Valve Plugged [need task 2]

08/27/07 PMCR 01109543 Increase Frequency of Deluge Solenoid Valve PMID 9461

08/30/07 WO 00312490

V-UH-52 - Replace Fan Motor

10/16/07 WO 00366402

23-01 Fire Prot System Sprinkler Functional Test

07/22/09 WO 00381724

-0 Service Water Component Inspection

11/13/09 WO 00381724

-2 Remove/reinstall pipe interferences in the intake tunnel and intake building to facilitate RHR "A Loop" removal

4/28/09 PCR 01236104 0324 Rev 40 License Renewal

06/04/10 WO 00438526

WO 384321 FP

-171-10 Failed PMT

09/11/11 WR 00071626

Sprinkler Piping Upstream Of FP

-171-10 Is Plugged

09/12/11 WO 00439540

Inspect Sprinkler Branch Lines in 12 EDG Room

09/21/11

Attachment 1

WORK DOCUMENTS

AND COMPLETED SURVEILLANCES Number Description or Title

Date/Rev PMCR 1305208

FP-171-2 Flush Intake Structure Fire Sprinkler Piping

10/04/11 0273 Fire Station Hose Station Valve Operability and Flow Blockage Test 09/06/11 0319 Fire Protection System

- Yard Hydrant Barrel Inspection

09/06/11

Attachment 1

LIST OF ACRONYMS USED

ADAMS Agencywide Document Access Management System

AMP Aging Management Program

CFR Code of Federal Regulations

EDG Emergency Diesel Generator

FPP Fire Protection Program

IMC Inspection Manual Chapter

IP Inspection Procedure

LRA License Renewal Application

NCV N on-Cited Violation

NFPA National Fire Protection Association

NRC U.S. Nuclear Regulatory Commission

OCCW Open Cycle Cooling Water

OE Operating Experience

PARS Publicly Available Records System

PMCR Preventative Maintenance Change Request

PMT Post Maintenance Testing

PRA Probabilistic Risk Analysis

RCE Root Cause Evaluation

RHRSW Residual Heat Removal Service Water

SDP Significance Determination Process

SIT Special Inspection Team

SPAR Standard Plant Analysis Risk

SRA Senior Risk Analyst

TS Technical Specification USAR Updated Safety Analysis Report

WO Work Order

Attachment 2

UNITED STATES

NUCLEAR REGULATORY COMMISSION

LISLE, IL 60532

-4352 September 12, 2011

MEMORANDUM TO:

Caroline Tilton , Senior Reactor Inspector

Engineering Branch 2, DRS

FROM: Steven

A. Reynolds, Director /RA/ Division of Reactor Safety SUBJECT: SPECIAL INSPECTION CHARTER

MONTICELLO NUCLEAR GENERATING PLANT

SEPTEMBER 2, 20 11 , UNANALYZED CONDITION OF THE INTAKE STRUCTURE FIRE SUPPRESSION SYSTEM

At 8:15 p.m., EDT on September 2, 2011, the licensee at Monticello made a 50.72 event notification (EN 47237) after a portion of the fire suppression sprinkler system located in the intake structure was unable to pass flow during surveillance testing. The

licensee entered a 14

-day fire protection system impairment action, instituted a continuous compensatory fire watch, and stationed backup suppression. Subsequently, the licensee found substantial fouling of the sprinkler suppression piping such that it was incapable of passing flow.

The sprinkler system located in the intake structure is relied upon, in part, to satisfy an exemption for the station to 10CFR50, Appendix R, Section III.G.2.B concerning the separation of safety-related components in the intake structure. The sprinkler

system provides fire suppression for the safety

-related service water supply

to both divisions of the residual heat removal, emergency diesel generator, emergency core cooling room coolers, and emergency filtration systems. The significant amount of foulin g caused the fire suppression system to be unable to perform its design function. Specifically, the system was incapable of preventing the loss of more than one train of safety

-related equipment in the event of a fire, which is part of t

he fire protection

design basis

. A bounding conditional core damage probability calculation for this condition was in the range of about 3.3E

-6 to 8.5E-6, placing the risk in the "special inspection" area. There is large uncertainty whether there are

risk significant credible fire scenarios which could lead to the risk significance associated with the above values. A field walkdown by a fire protection inspector would be necessary to determine whether any risk significant credible fire scenarios exist.

In addition, typical Technical Specification or administrative surveillance requirements for the fire protection systems do not require verification of adequate water flow through the sprinkler portions of fire protection piping. As such, significant fouling could be undetected using typical industry surveillance practices; therefore, this issue could have generic implications.

The CONTACT:

A. M. Stone, DRS

(630) 829-9729

Attachment 2

C. Tilton -2- licensee recently revised the surveillance to include a flow test as a result of a license renewal commitment.

Accordingly, based on the deterministic criteria in Management

Directive 8.3 and as provided in Regional Procedure 8.31, "Special Inspections at Licensed Facilities

," you are to lead a Special Inspection that will commence on September 12, 2011.

You will be supported by Dariusz Szwarc, Reactor Inspector and Patricia Voss, Monticello Resident Inspector.

This special inspection is intended to

evaluate the facts, circumstances, and licensee actions surrounding the September 2, 2011, incident described above. The specific Charter for the Team is enclosed.

Enclosure: As Stated

cc w/encl: