ML13354B870

From kanterella
Revision as of 18:28, 21 June 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
2013, Dresden Initial License Exam, as Administered System JPMs
ML13354B870
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/25/2013
From: Walton R
NRC/RGN-III/DRS/OLB
To:
Walton R
Shared Package
ML11355A018 List:
References
Download: ML13354B870 (70)


Text

Exelon Nuclear Job Performance Measure

SBLC - INJECTION WITH PUMP AND RWCU FAILURE S JPM Number:

S-N-a Revision Number: 0 2 Date: 0 8/1 3 EXAM MATERIAL

Developed By:

Instructor Date Approved By:

Facility Representative Date Job Performance Measure (JPM)

S-N-a Page 2 of 8 Revision Record (Summary)

Revision 0 2 Revised for 201 3 NRC exam.

Job Performance Measure (JPM)

S-N-a Page 3 of 8 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to IC 12.

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Insert following Malfunctions and/or Remotes:

IMF CIRWCUAP (2

-1201-1 valve failure to close

- and allows manual closure).

IMF CIRWCUBP (2

-1201-2 valve failure to close

- and allows manual closure).

IMF SCRLFVAD 0.0 (Inserts BOTH SBLC Pump relief valve setpoint drift to 0.0 so

  1. whichever pump is started first will not develop flow

) IMF SCRLFVBD 0.0 (Inserts BOTH SBLC Pump relief valve setpoint drift to 0.0 so

  1. whichever pump is started first will not develop flow

) IOR SCD3013 OFF (Overrides SBLC SYS1&2 and SYS2&1 positions OFF

) 3. Setup the following Triggers:

TRGSET 1 "SCD301_DRW(1)" (Trigger 1 Activates when SBLC control switch is placed to SYS1 position

) TRG 1 "DMF SCRLFVBD" (Deletes 2B SBLC relief valve setpoint drift malfunction

) TRGSET 2 "SCD301_DRW(2)" (Trigger 2 Activates when SBLC control switch is placed to SYS2 position

) TRG 2 "DMF SCRLFVAD" (Deletes 2A SBLC relief valve setpoint drift malfunction

) DOCUMENT PREPARATION DOP 1100-02 hardcard

.

Job Performance Measure (JPM)

S-N-a Page 4 of 8 INITIAL CONDITIONS

1. You are the Unit 2 NSO.
2. A transient has occurred, resulting in an ATWS

. 3. The Unit Supervisor has authorized the use of Hard Cards

. INITIATING CUE

1. The Unit Supervisor has ordered you to inject SBLC, for an ATWS, per the Hard Card. 2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-a Page 5 of 8 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Examinee should locate the hard card, then provide the included copy

. 1. Place the SBLC INJECTION CONTROL keylock switch to the SYS 1 OR SYS 2 position. Turns the SBLC INJECTION CONTROL keylock switch to either the intermediate right OR intermediate left position.

_____ _____ _____

2. Verifies applicable SQUIB pilot light NOT lit. SQUIB "A" or "B" light off.

_____ _____ _____

NOTE: The selected pump starts but does not develop flow (relief valve failure in the JPM setup).

3. Verifies applicable PUMP pilot light lit.

PUMP light on.

_____ _____ _____

BEGIN ALTERNATE PATH

4. Verifies FLOW pilot light lit.

FLOW light off (SBLC is NOT injecting

). _____ _____ _____

5. SBLC SQUIB VLV CKT FAILURE annunciator alarms (902-5 H-6). Annunciator 902

-5 H-6 illuminated.

_____ _____ _____

  • 6. Places SBLC INJECTION CONTROL keylock switch to opposite position taken to in step 1. Turns the SBLC INJECTION CONTROL keylock switch to the opposite direction turned in step 1. _____ _____ _____
7. Verifies opposite PUMP pilot light lit.

Opposite PUMP light on.

_____ _____ _____

NOTE: Flow light will illuminate when SBLC INJECTION CONTROL keylock switch is re

-positioned.

Job Performance Measure (JPM)

S-N-a Page 6 of 8 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment 8. Verifies RWCU valve 2-1201-1 closed. Examinee recognizes that valve 2-1201-1 valve did NOT close. _____ _____ _____

  • 9. Closes RWCU valve 2-1201-1. Takes manual action for a failed automatic action and closes 2-1201-1 valve, by placing c/s in the CLOSED position. _____ _____ _____
10. Verifies RWCU valve 2-1201-1A closed.

GREEN light illuminated.

_____ _____ _____

11. Verifies RWCU valve

2-1201-2 closed. Examinee recognizes that valve 2-1201-2 valve did NOT close. _____ _____ _____

  • 12. Closes RWCU valve

2-1201-2. Takes manual action for a

failed automatic action and closes 2-1201-2 valve, by placing c/s in the CLOSED position. _____ _____ _____

13. Verifies RWCU valve 2-1201-3 closed. GREEN light illuminated.

_____ _____ _____

14. Verifies RWCU valve 2-1201-7 closed. RED light illuminated.

_____ _____ _____

15. Informs Unit Supervisor task is complete.

Reports SBLC is injecting but the first pump did not inject and valves 2-1201-1 and 2-1201-2 failed to close automatically.

_____ _____ _____

CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-a Page 7 of 8 Operator's Name:

Job Title: RO SRO JPM Title: SBLC - INJECTION WITH PUMP AND RWCU FAILUR ES Revision Number: 0 2

JPM Number: S

-N-a Task Number and Title: 211L002, Injection of Standby Liquid Control System

K/A Number and Importance: 211000

.A4.08 4.2 / 4.2

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Y es No Time Critical:

Yes No Estimated Time to Complete:

9 minutes Actual Time Used:

minutes

References:

DOP 1100-02, rev 1 8 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily? Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print):

Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-a Page 8 of 8 INITIAL CONDITIONS

1. You are the Unit 2 NSO.
2. A transient has occurred, resulting in an ATWS.
3. The Unit Supervisor has authorized the use of Hard Cards.

INITIATING CUE

1. The Unit Supervisor has ordered you to inject SBLC, for an ATWS, per the Hard Card.
2. Inform the Unit Supervisor when the task is complete.

Exelon Nuclear Job Performance Measure

CORE SPRAY

- PERFORM PUMP TEST WITH PUMP TRIP JPM Number: S

-N-b Revision Number: 0 6 Date: 08/1 3 EXAM MATERIAL

Developed By:

Instructor Date Approved By:

Facility Representative Date Job Performance Measure (JPM)

S-N-b Page 2 of 10 Revision Record (Summary)

Revision 0 5 Bank JPM. Revision 0 6 Revised for ILT 1 2-1 (201 3-301) NRC Exam.

Job Performance Measure (JPM)

S-N-b Page 3 of 10 SIMULATOR SETUP INSTRUCTIONS

1. Core Spray pump operability surveillance can be performed from any IC with Core Spray in the normal standby lineup NOT E: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. Start the LPCI/CS room cooler fans.
3. Enter the following Expert commands to set up an automatic trigger to trip the Core Spray pump after the test valve is opened:

NOTE:The trigger assignment can be changed to any other available trigger to accommodate running this JPM concurrently with other JPMs.

trgset 1 "cssbkppb .and. cslop4b" (Trigger 1 Activates when 2B Core Spray pump is running AND when MO 1402

-4B OPEN light turns ON) ior csdtpppb (1 10) trip (After 10 sec, inserts a 2B Core Spray pump trip) ior csdclppb (1 10) off (After 10 sec, inserts a 2B Core Spray pump trip) trgset 2 "(et_array(1) .and. (.not. cssbkppb))"l2 (Trigger 2 Activates when Trigger 1 is active AND when 2B Core Spray pump is NOT running) trg 2 "dor csdtpppb"l2 (Deletes 2B Core Spray pump trip)

DOCUMENT PREPARATION

1. Markup a copy of DOS 1400-05 as complete up through Step I.
7. (Ready to start 2B Core Spray Pump per step I.

8).

Job Performance Measure (JPM)

S-N-b Page 4 of 10 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The Unit 2 Core Spray 'B' Pump operability surveillance is required due to maintenance.
3. The operability surveillance for the 2A Core Spray pump is NOT needed.
4. The system is filled and vented.
5. The required valve operability surveillance has been completed.
6. Vibration data is NOT required.
7. The Unit 2 EO is standing by in the corner room.
8. The LPCI/Core Spray Room Coolers are running.

INITIATING CUE

1. The Unit Supervisor directs you to perform DOS 1400

-05 step I.8 for the 2B Core Spray pump. 2. All applicable Prerequisites have been met.

3. Inform the Unit Supervisor upon completion of step I.8.

Job Performance Measure (JPM)

S-N-b Page 5 of 10 Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-b Page 6 of 10 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide Examinee a copy of DOS 1400-05. 1. Verify the following valve line up: MO 2-1402-4B Closed MO 2-1402-38B Open 2-1402-6B Open MO 2-1402-25B Closed MO 2-1402-3B Open 2-1402-40B-SV Closed Verifies the following:

Green light illuminated

. Green light illuminated

. Green light illuminated

. Green light illuminated

. Green light illuminated

. Directs EO to Verify 2

-1402-40B-SV Closed

_____ _____ _____

CUE: 2-1402-40B-SV, INST SV is closed.

NOTE: The next three (3) actions may be requested to be performed at the same time.

2. Verify 2B CORE SPRAY MOTOR has adequate lubrication

. Contacts EO to verify 2B CORE SPRAY MOTOR has adequate lubrication per step I.8.b.(1).

_____ _____ _____

CUE: 2B Core Spray motor oil level is normal (within +0 to -1/8 inch band).

3. Verify 2B LPCI/CS Room Cooler is operating properly.

Contacts EO to verify proper room cooler operation per step I.8.c

. _____ _____ _____

CUE: 2B LPCI/CS room cooler is operating normally.

Job Performance Measure (JPM)

S-N-b Page 7 of 10 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment 4. Direct EO to open 2-140 2-40B-SV and report pressure.

Directs 2-1402-40B-SV Open per step I.8.d

_____ _____ _____

CUE: When asked, report: "2

-1402-40B-SV Inst SV is Open

". 5. Record suction pressure provided by EO. Pressure of 7 psig recorded on Data Sheet 1 per step I.8.e

. _____ _____ _____

CUE: When asked, report: "suction pressure is 7 psig on PI 2-1402-40B". 6. Step I.8.f calculate 2

-1402-8B initial closed DP.

DP Calculated:

2-1450-1B ________ psig Minus 2-1402-40B ___7____psig Records 2-1450-1B pressure as 75 psig (+ 5 psig) _____ _____ _____

CUE: If examinee requests the above calculation to be verified, sign the "verified by" line

. If the student informs the SRO that the Core Spray System should be declared inoperable, acknowledge the report.

NOTE: Candidate will N/A step I.8.g.

Red light illuminated and annunciators H

-13 and A-5 alarm. _____ _____ _____

NOTE: 2B Core Spray Pump overcurrent trip malfunction is automatically inserted 10 seconds after the 2-1402-4B valve has dual indication.

Job Performance Measure (JPM)

S-N-b Page 8 of 10 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment

  • 8. Step I.8.j open FLOW TEST VLV MO 2-1402-4B. Rotates and holds MO 2

-1402-4B Control switch CW to Open.

_____ _____ ____

_ BEGIN ALTERNATE PATH

9. Acknowledge and report alarm for 2B CS pump trip.

Acknowledges annunciator H-5 and makes report.

_____ _____ _____

CUE: Acknowledge report.

  • 10. Immediately Close 2-1402-4B. Green light illuminated.

Red light illuminated. _____ _____ _____

CUE: If examinee enters DOA 6500

-10, respond that the assist NSO will execute that procedure.

CUE: If examinee terminates, or requests permission to terminate the surveillance OR If examinee references the DAN for pump trip and has at least considered the actions to take, then provide the cue: Terminate the surveillance. Leave the system in the current lineup. Someone else will be assigned to verify the system is restored to normal.

11. Informs Unit Supervisor task is complete.

Examinee notifies the Unit Supervisor.

_____ _____ _____

CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-b Page 9 of 10 Operator's Name:

Job Title: RO SRO JPM Title: CORE SPRAY

- PERFORM PUMP TEST WITH PUMP TRIP Revision Number: 0 6

JPM Number: S-N-b Task Number and Title: 209L004, Perform a CS pump operability test and determine if the results meet the acceptance criteria as stated in DOS 140 0-05 K/A Number and Importance: 209001.A4.01 3.8 / 3.6

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

22 minutes Actual Time Used: minutes

References:

DOS 1400-05, rev 47 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print): Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-b Page 10 of 10 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The Unit 2 Core Spray 'B' Pump operability surveillance is required due to maintenance.
3. The operability surveillance for the 2A Core Spray pump is NOT needed.
4. The system is filled and vented.
5. The required valve operability surveillance has been completed.
6. Vibration data is NOT required.
7. The Unit 2 EO is standing by in the corner room.
8. The LPCI/Core Spray Room Coolers are running.

INITIATING CUE

1. The Unit Supervisor directs you to perform DOS 1400

-05 step I.8 for the 2B Core Spray pump.

2. All applicable Prerequisites have been met. 3. Notify the Unit Supervisor upon completion of step I.8.

Exelon Nuclear Job Performance Measure

MAIN STEAM

- UNISOLATE ONE LINE USING ALTERNATE METHOD JPM Number:

S-N-c Revision Number: 0 1 Date: 02/12 EXAM MATERIAL

Developed By:

Instructor Date Approved By:

Facility Representative Date Job Performance Measure (JPM)

S-N-c Page 2 of 8 Revision Record (Summary)

Revision 00 Bank JPM. Revision 01 Revised for ILT 11

-1 (2012-301) NRC Exam

.

Job Performance Measure (JPM)

S-N-c Page 3 of 8 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to IC 16 (<50% power).

NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.

2. Power needs to be low enough so that isolating one main steam line will NOT cause a Group 1 high flow isolation.
3. Close 'C' Main Steam Line Isolation Valves:

AO-2-203-1 C AO-2-203-2 C 4. Verify Main Steam Line drain valves closed:

MO 2-220-1, 2, 3 & 4 MO 2-220-90A, B, C & D

5. Place O.O.S. cards on Main Steam Line drain valves: 2-220-1 MSL DRN VLV 2-220-2 MSL DRN VLV
6. Insert following Malfunctions and/or Remotes:

None. 7. Setup the following Triggers:

None. DOCUMENT PREPARATION

1. Clean copy of DOP 0250-02.

Job Performance Measure (JPM)

S-N-c Page 4 of 8 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Following maintenance work on the AO 2

-203-2 C MSIV, the "

C" Main Steam Line is ready to be unisolated.

INITIATING CUE

1. The Unit Supervisor has directed you to unisolate the "

C" Main Steam Line using the ALTERNATE method in accordance with DOP 0250

-02, step G.

6. 2. The Main Steam system engineer has provided concurrence to unisolate the 2C Main Steam Line using the alternate method.
3. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-c Page 5 of 8 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide the Examinee with the supplied copy of DOP 0250-02.
  • 1. Open MO 2-220-3 MSL DRN VLV. RED light illuminated.

_____ _____ ____

_

  • 2. Open MO 2-220-90C MSL DRN VLV. RED light illuminated.

_____ _____ _____

3. Wait a minimum of 5 minutes.

5 minutes elapsed OR verbal cue received.

_____ _____ _____

CUE: Inform examinee that 5 minutes has elapsed

.

  • 4. Open AO 2-203-2C MSIV. GREEN light illuminated.

_____ _____ _____

5. Wait a minimum of 30 minutes. 30 minutes elapsed OR verbal cue received.

_____ _____ _____

CUE: Inform examinee that 30 minutes has elapsed

.

  • 6. Open AO 2-203-1C MSIV. GREEN light illuminated.

_____ _____ _____

7. Close M O 2-220-90C MSL DRN VLV. GREEN light illuminated.

_____ _____ _____

8. Close MO 2

-220-3 MSL DR N VLV. GREEN light illuminated.

_____ _____ _____ 9. Informs Unit Supervisor task is complete.

Examinee notifies the Unit Supervisor.

_____ _____ _____

Job Performance Measure (JPM)

S-N-c Page 6 of 8 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-c Page 7 of 8 Operator's Name:

Job Title: RO SRO JPM Title: MAIN STEAM

- UNISOLATE ONE LINE USING ALTERNATE METHOD Revision Number: 0 1

JPM Number: S-N-c Task Number and Title: 239L004 Unisolating, One Main Steam Line

K/A Number and Importance:

239001.A4.01 4.2 / 4.0

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

1 4 minutes Actual Time Used:

minutes

References:

DOP 025 0-02, rev 12 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print): Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-c Page 8 of 8 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Following maintenance work on the AO 2

-203-2C MSIV, the "C" Main Steam Line is ready to be unisolated.

INITIATING CUE

1. The Unit Supervisor has directed you to unisolate the "C" Main Steam Line using the ALTERNATE method in accordance with DOP 0250

-02, step G.6

. 2. The Main Steam system engineer has provided concurrence to unisolate the 2C Main Steam Line using the alternate method

. 3. Inform the Unit Supervisor when the task is complete.

Exelon Nuclear Job Performance Measure

ISO COND - STARTU P, WITH FAILURE OF THE M

/U SYSTEM JPM Number:

S-N-d Revision Number: 0 3 Date: 0 8/1 3 EXAM MATERIAL Developed By:

Instructor Date Approved By:

Facility Representative Dat e Job Performance Measure (JPM)

S-N-d Page 2 of 10 Revision Record (Summary)

Revision 0 2 Bank JPM. Revision 0 3 Revised for ILT 1 2-1 (201 3-301) NRC Exam

.

Job Performance Measure (JPM)

S-N-d Page 3 of 10 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any IC. NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. Verify the Isolation Condenser is in its normal standby lineup.
3. Ensure 2/3A Clean Demin Pump is operating.
4. Ensure 2/3B Clean Demin Pump is NOT operating.
5. Place 2/3B ISOL CNDR M U PP control switch in PTL.
6. Place a CO tag on the 2/3B ISOL CNDR M U PP control switch.
7. Enter the following Simulator Expert commands which trips the 2/3 A Diesel Driven Iso Makeup Pump a few seconds after starting:

trgset 1 "wmsdp(1)" {

Trigger 1 Activates when 2A IC M

-U PP is started}

imf wmpmpaf (1 2) {

After 2 sec, inserts a trip of 2A IC M

-U PP} 8. Verify Reactor Pressure is < 10 50 psig. 9. Acknowledge / Reset alarms.

DOCUMENT PREPARATION

1. Clean copy of DOP 1300-03.

Job Performance Measure (JPM)

S-N-d Page 4 of 10 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The U2 Isolation Condenser (IC) has been verified in Standby per DOP 1300

-01. 3. A special engineering test requires the manual initiation of the U2 IC. 4. An NLO is in the field to monitor operation of the IC Makeup Pump

. 5. 2/3B ISOL CNDR M

/U PP is OOS for pump replacement.

6. RPV parameters and the time of IC initiation in Unit 2 Reactor Log Book will be recorded by another NSO.
7. Another NSO will make ALL notifications outside of the Main Control Room.

INITIATING CUE

1. The Unit Supervisor has directed you to startup the U2 Isolation Condenser to full flow per DOP 1300-0 3 Step G.4. 2. RPV pressure band is 920 to 1000 psig.
3. Hard Cards are NOT authorized.
4. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the Job Performance Measure (JPM)

S-N-d Page 5 of 10 local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-d Page 6 of 10 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide the examinee with the supplied copy of DOP 1300

-03.

  • 1. Place AO 2

-1301-17 AO 2-1301-20, VENT VLV, control switch in CLOSE and verify closed.

Both RED light s illuminated.

_____ _____ _____

2. Rotate RX INLET ISOL VLV HAND/RESET to HAND.

Places switch to HAND position and releases.

_____ _____ _____

3. Verify annunciator 902

-3 B-4, ISOL CONDR VLVS OFF NORMAL, alarms.

Annunciator 902

-3 B-4, ISOL CONDR VLVS OFF NORMAL illuminated.

_____ _____ _____

  • 4. Open AND throttle MO 2-1301-3, RX INLET ISOL, as necessary.

RED light illuminated.

_____ _____ _____

5. Monitor IC shell level using ISOL CONDR LVL, LI 2-1340-2, on Panel 902

-3. Pointer in normal GREEN band. _____ _____ _____

CUE: If contacted as Makeup Demin Control Room, report the Dilution Pumps are NOT operating.

6. Open MO 2-4399-74, CLEAN DEMIN VLV.

RED light illuminated.

_____ _____ _____

7. Start 2/3A ISOL CNDR M

-U PP. RED Light illuminated

. _____

_____ _____

NOTE: 2/3A ISOL CNDR M U PP will trip a few seconds after starting, due to a malfunction inserted in setup.

Job Performance Measure (JPM)

S-N-d Page 7 of 10 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment BEGIN ALTERNATE PATH

  • 8. Directs the NLO to locally close 2-4399-756, 2/3 ISOL CDSR CLEAN DEMIN MAKEUP SYS DISCH HDR TO U2 ISOL CDSR ISOL VLV. Directs NLO to close the valve per step G.11.a

. _____ _____ _____

CUE: 2-4399-756, ISOL CDSR CLEAN DEMIN M

/U SYS DISCH HDR TO U2 ISOL CDSR ISOL VLV is closed.

NOTE: Examinee may close 2

-4399-74, CLEAN DEMIN VLV, prior to starting the CLEAN DEMIN Water pump. MO 2(3)-4399-74, CLEAN DEMIN VLV, is opened prior to starting 2/3-43122A/B, 2/3A(B) ISOL CNDR M-U PP, to minimize water hammer.

This is not a concern with the clean demin water pumps.

  • 9. Starts 2/3 B CLEAN DEMIN water Pump. BLUE light illuminated.

_____ _____ _____

  • 10. Directs the NLO to locally unlock and open the 2-4399-72, U2 ISOL CDSR CLEAN DEMIN WTR SUPPLY. Directs NLO to unlock and open the valve per step G.11.c. _____ _____ __

___ CUE: 2-4399-72, U2 ISOL CDSR CLEAN DEMIN WTR SUPPLY valve is unlocked and open. NOTE: The IC level requires a long time for level to increase.

  • 11. Cycle the MO 2-4399-74, CLEAN DEMIN VALVE, as needed to maintain LI 2-1340-2, ISOL CONDR LVL, in green band. Maintains level in green band. _____ _____ _____

CUE: Inform examinee that another NSO will now assume duties for the IC.

Job Performance Measure (JPM)

S-N-d Page 8 of 10 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment 12. Informs the Unit Supervisor that the Isolation Condenser Makeup P um p (s) did NOT start as expected and that he/she is currently maintaining IC level with the Clean Demin system and that the task is complete Examinee notifies the Unit Supervisor.

_____ _____ _____

CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-d Page 9 of 10 Operator's Name:

Job Title: RO SRO JPM Title: ISO COND - Startup, With Failure Of The M/U System Revision Number: 0 3

JPM Number: S-N-d Task Number and Title: DRE207LN008, Given a set of conditions, analyze the conditions and determine the corrective actions required to return the Isolation Condenser to a stable condition.

.

K/A Number and Importance: 207000.A4.0 1 3.7 / 3.8

Suggested Testing Environment:

Simulator Actual Testing Environment: Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

1 5 minutes Actual Time Used:

minutes

References:

DOP 1300-0 3, rev 3 4 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactoril y? Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory

Comments: Evaluator's Name (Print): Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-d Page 10 of 10 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The U2 Isolation Condenser (IC) has been verified in Standby per DOP 1300-01. 3. A special engineering test requires the manual initiation of the U2 IC. 4. An NLO is in the field to monitor operation of the IC Makeup Pump.
5. 2/3B ISOL CNDR M

/U PP is OOS for pump replacement.

6. RPV parameters and the time of IC initiation in Unit 2 Reactor Log Book will be recorded by another NSO.
7. Another NSO will make ALL notifications outside of the Main Control Room.

INITIATING CUE

1. The Unit Supervisor has directed you to startup the U2 Isolation Condenser to full flow per DOP 1300

-0 3 Step G.4. 2. RPV pressure band is 920 to 1000 psig.

3. Hard Cards are NOT authorized.
4. Inform the Unit Supervisor when the task is complete.

Exelon Nuclear Job Performance Measure

LPCI - START TORUS COOLING WITH INITIATION SIGNAL PRESENT (LPCI NOT INJECTING INTO THE VESSEL)

JPM Number: S-N-e Revision Number: 0 0 Date: 0 8/13 EXAM MATERIAL Developed By:

Instructor Date Approved By: Facility Representative Date Job Performance Measure (JPM)

S-N-e Page 2 of 9 Revision Record (Summary)

Revision 00 Modified for ILT 1 2-1 (201 3-301) NRC Exam

.

Job Performance Measure (JPM)

S-N-e Page 3 of 9 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any IC with an ECCS initiation signal present, Reactor pressure > 500 psi and with the A LPCI loop selected for injection. NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. Place HPCI 2-2301-4 & 14 C/S in PTL
3. Place an info card on the 2

-1501-20B stating the valve is OOS.

4. Allow the 5 min interlock on the 2

-1501-21A valve to elapse prior to snapping to an IC.

5. Insert following Malfunctions and/or Remotes:

Small Drywell leak (to cause the ECCS initiation) o imf i21 0.01 1:00 0.2l10 2-1501-20B OOS o ior LPLvlvcl14 falsel4 o irf LPCI20bBC closel4 Ensure 2B Loop selected for injection.

o ior rrmbbias 0.05

6. Setup the following Triggers:

None. DOCUMENT PREPARATION Clean copy of DOP 1500-02, Attachment "D" Hard Card

.

Job Performance Measure (JPM)

S-N-e Page 4 of 9 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The 2-1501-20B TORUS CLG/TEST valve is OOS for breaker repairs.
3. A transient and Reactor scram occurred resulting in the following conditions:

Drywell pressure is 2.5 psig and slowly risin

g. Reactor pressure is 9 40 psig and slowly lowering.

INITIATING CUE

1. The Unit Supervisor has directed you to initiate MAXIMUM Torus cooling per the Hardcard. 2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-e Page 5 of 9 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide the Examinee with t he supplied copy of DOP 1500-02, Attachment "D" Hard Card
  • 1. Place 316A/B AND 318A/B keylock switches in MANUAL (MANUAL OVERRD)

Places the 316 A/B keylock switch to MANUAL AND the 318 A/B to MANUAL OVERRD

_____ _____ _____

  • 2. Start one CCSW Pump in each loop AND verify 3 A/B valves open. (IF only one CCSW loop available, THEN start second CCSW Pump in same loop.)

Starts one CCSW Pump in each loop (Red ON light lit)

AND 2-1501-3A/B are open (dual indication)

_____ _____ _

____ 3. Start at least one LPCI pump in each loop. (Start additional LPCI pumps as required.)

Verifies both LPCI pumps are running in both loops. (Red ON lights lit)

_____ _____ _____

NOTE: All four LPCI pumps will be running due to a n EC CS initiation signal being locked in.

NOTE: Steps 4 and 5 may be performed after step 10 per the DOP 1500

-02 hardcard.

4. Adjust CCSW flow controller to approximately 3500 gpm for one pump; > 5000 gpm two pumps. [Maintain LPCI Pumpsid (two LPCI Pumps/loop)]

ADJUSTS CCSW flow to approximately 3500 gpm per pump. _____ _____ _____

  • 5. Momentarily place 11A/B valve control switches to close. (IF 11A/B remain open OR re-opened due to LPCI logic, THEN close valves as soon as possible.)

Places BOTH 2-1501-11 A and B C/S to CLOSE (Red CLOSED lights lit.

) _____ _____ _____

Job Performance Measure (JPM)

S-N-e Page 6 of 9 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment

  • 6. Open 21A/B AND 20A/B valves in desired loop.

Place s 2-1501-20A and 21A C/S to OPEN (MO 2-1501-21A Green OPEN light AND 2-1501-20A Red OPEN light lit.

) _____ _____ _____

NOTE: 2-1501-21A will be closed due to B LPCI loop being selected for injection.

  • Throttle open 38A/B valves until > 5000 gpm per LPCI pump is established (maintain LPCI pump discharge pressure > 125 psig).

Places the 2

-1501-38A C/S to OPEN. Achieves approximately 20,000 gpm flow on FI 2

-1561A (maintain LPCI pump discharge pressure > 125 psig) _____ _____ _____

NOTE: Maximum flow through the LPCI cross

-tie will be 8. IF TR 86(32) LTC in MANUAL, THEN PRIOR to starting 3rd OR 4th CCSW PP, verify voltage on applicable ECCS bus > 4000 volts, preferred target 4160V.

Verifies TR 86(32) LTC is in AUTO _____ _____ _____

  • 9. Start additional CCSW Pumps if desired Starts second CCSW pump in each loop (Red ON lights lit)

_____ _____ _____

10. Adjust CCSW flow controller to > 5000 gpm for twoCCSW Pumps [Maintain LPCI/CCSW (two LPCI Pumps/loop)]. ADJUSTS CCSW flow to approximately > 5000 gpm

. [Maintains LPCI/CCSW dP (two LPCI Pumps/loop)]

on both loops.

_____ _____ _____

11. Informs Unit Supervisor task is complete.

Examinee notifies the Unit Supervisor.

_____ _____ _____

Job Performance Measure (JPM)

S-N-e Page of 9 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-e Page 8 of 9 Operator's Name:

Job Title: RO SRO JPM Title: LPCI - START TORUS COOLING WITH INITIATION SIGNAL PRESENT (LPCI NOT INJECTING INTO THE VESSEL)

Revision Number: 00

JPM Number: S-N-e Task Number and Title: 203L003 , Initiate Torus Cooling with an Injection Signal Present.

K/A Number and Importance: 219000.A4.01 3.8 / 3.7

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

2 0 minutes Actual Time Used:

minutes

References:

DOP 1500-02, rev 65 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print): Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-e Page 9 of 9 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. The 2-1501-20B TORUS CLG/TEST valve is OOS for breaker repairs. 3. A transient and Reactor scram occurred resulting in the following conditions:

Drywell pressure is 2.5 psig and slowly rising.

Reactor pressure is 9 40 psig and slowly lowering.

INITIATING CUE

1. The Unit Supervisor has directed you to initiate MAXIMUM Torus cooling per the Hardcard.
2. Inform the Unit Supervisor when the task is complete.

Exelon Nuclear Job Performance Measure

EDG - PERFORM SURVEILLANCE TESTING JPM Number:

S-N-f Revision Number: 0 0 Date: 0 8/1 3 EXAM MATERIAL

Developed By:

Instructor Date Approved By:

Facility Representative Date Job Performance Measure (JPM)

S-N-f Page 2 of 8 Revision Record (Summary)

Revision 0 0 Revised for ILT 1 2-1 (201 3-301) NRC Exam

.

Job Performance Measure (JPM)

S-N-f Page 3 of 8 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any IC 12. NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. U2 Diesel Generator should be started but not loaded to Bus 2 4-1, per DOS 6600

-01 up to and including step I.12.

3. Insert following Malfunctions and/or Remotes:

IRF T02 = TRUE (Set Diesel Generator 2 droop to 55)

. IRF T20 = acknowledge (Acknowledge the local EDG alarm)

4. Acknowledge all applicable alarms (locally and on the 902

-8 panel). 5. Adjust 2 EDG frequency to approx. 59.5 Hz

6. Setup the following remote functions set to triggers, for when directed by examinee
IRF T02 = FALSE (When directed by examinee to set droop to 5).

IRF T20 = ACKNOWLEDGE (A few seconds after the droop has been set to 55 acknowledges U2 D/G Local Panel Trouble Alarms).

DOCUMENT PREPARATION

1. Marked up copy of DOS 6600-01, up to and including step I.
12.

Job Performance Measure (JPM)

S-N-f Page 4 of 8 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. DOS 6600-01 is in progress on the Unit 2 Diesel Generator, which is currently NOT paralleled or loaded to Bus 24-1. 3. No maintenance has been performed on the diesel

. 4. A full load reject test IS NOT required. 5. An EO has been briefed and is in the field with the appropriate portions of DOS 6600

-01. INITIATING CUE

1. The Unit Supervisor has directed you to review DOS 6600-01 and then synchronize and load the Unit 2 Diesel Generator, starting at step I.1
3. 2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-f Page 5 of 8 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide the Examinee with the supplied copy of DOS 6600-01. 1. Adjust D/G speed to 60 hz.

2 DG GOVERNOR C/S to INCR until Frequency meter reads 60 HZ.

_____ _____ _____

2. Adjust D/G volt to 4160 volts.

2 DG VOLTAGE REG C/S to RAISE until Volts meter reads 4160 (just clockwise of the first small division after 4000).

_____ _____ _____

NOTE: Each small division on his meter = 125 volts.

  • 3. Insert key AND turn the Synchroscope ON for the appropriate D/G 4 kV output breaker. Inserts key and turn ON the synchroscope for the Unit 2 D/G to Bus 24

-1 circuit breaker.

_____ _____ _____

  • 4. Adjust the voltage AND the governor controls until the D/G output is synchronized with the 4 kV system.

Adjusts 2 DG voltage and governor controls until Synchroscope is rotating in the fast (clockwise) direction at approximately 30 second pace.

_____ _____ ____

_

  • 5. WHEN the D/G is synchronized to the bus, THEN close the D/G output breaker to the 4 kV bus.

2 D/G Output breaker to CLOSED. Red closed light illuminated.

_____ _____ _____

  • 6. Using the GOVERNOR control switch, raise the load on the D/G to 2340 to 2600 kW over a period of approximately 30 to 90 seconds. Over a period of approx. 30 to 90 seconds Governor C/S to Raise until KW meter reads 2340 to 2600.

_____ _____ _____

Job Performance Measure (JPM)

S-N-f Page 6 of 8 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: <30 sec. or >90 sec. is NOT cause for a failure. 7. Turn Synchroscope off AND remove key.

2 DG Synchroscope to OFF. Key removed.

_____ _____ _____

8. Using the VOLTAGE REG control switch, adjust D/G excitation to

-300 to +300 KVARS (real load may have to be re-adjusted to maintai n the kW band listed in the previous step).

VOLTAGE REG C/S to Lower or Raise until KILOVAR meter is between -300 and +300.

_____ _____ _____

9. Verify D/G load is 2340 to 2600 kW. Record load AND time. Records the amount of load applied and the time the load was applied to the D/G. _____ _____ _____

CUE: Inform the examinee that another NSO will complete the surveillance on the Diesel Generator.

10. Informs Unit Supervisor that the D/G is synchronized and loaded and the task is complete. Examinee notifies the Unit Supervisor.

_____ _____ _____

CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-f Page 7 of 8 Operator's Name:

Job Title: RO SRO JPM Title: EDG - PERFORM SURVEILLANCE TESTING Revision Number: 0 0

JPM Number: S-C-f Task Number and Title: 264L009 Perform DG Surveillance Testing

K/A Number and Importance: 264000.A4.05 3.6 / 3.7

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

15 minutes Actual Time Used:

minutes

References:

DOS 6600-01, rev 123 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print): Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-f Page 8 of 8 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. DOS 6600-01 is in progress on the Unit 2 Diesel Generator, which is currently NOT paralleled or loaded to Bus 24-1. 3. No maintenance has been performed on the diesel.
4. A full load reject test IS NOT required. 5. An EO has been briefed and is in the field with the appropriate portions of DOS 6600-01. INITIATING CUE
1. The Unit Supervisor has directed you to review DOS 66 00-01 and then synchronize and load the Unit 2 Diesel Generator, starting at step I.1
3. 2. Inform the Unit Supervisor when the task is complete.

Exelon Nuclear Job Performance Measure

RBM - CLEAR RBM MALFUNCTIO N JPM Number: S-N-g Revision Number: 0 0 Date: 0 8/13 EXAM MATERIAL

Developed By:

Instructor Date Approved By:

Facility Representative Date Job Performance Measure (JPM)

S-N-g Page 2 of 8 Revision Record (Summary) Revision 00 New JPM for ILT 12

-1 (2013-301) NRC Exam.

.

Job Performance Measure (JPM)

S-N-g Page 3 of 8 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any IC with. NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. 3. Insert following Malfunctions and/or Remotes:

None. 4. Setup the following Triggers:

None. DOCUMENT PREPARATION Clean copy of DOA 0700-03.

Job Performance Measure (JPM)

S-N-g Page 4 of 8 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO. 2. Control rod moves were in progress when annunciator 902

-5 A-7, RBM HI/INOP was received. 3. Control rod withdrawal attempts were stopped.

4. DAN 902(3)

-5 A-7 RBM HI/INOP was ineffective in clearing the condition.

INITIATING CUE

1. The Unit Supervisor has directed you to clear the condition per DOA 0700

-03, ROD OUT BLOCKS. 2. Inform the Unit Supervisor when the task is complete.

Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps.

Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-g Page 5 of 8 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide the Examinee with the supplied copy of DOA 0700-03 1. Observe the selected rod position is correct.

Checks RWM and full core display for rod position.

_____ _____ _____

2. Depress the appropriate RBM PUSH TO SET

-UP Push Buttons. Depress the RBM PUSH TO SET-UP Push Button for RBM 7. _____ _____ _____

3. Verify only one Control Rod i s selected for movement, and that it is in the proper sequence (the NO ROD SELECTED Light on Panel 902(3)-37 should be extinguished).

Verifies only one rod is selected on the rod select matrix and the NO ROD SELECTED light for RBM 7 at panel 902

-37 is extinguished. _____ _____ _____

4. Check that there are NO unusually high LPRM indications, and that there are the proper number of assigned LPRMs for each of the RBM Channels.

Verifies that there are no high LPRM indications and RBM 7 has the proper number of LPRMs assigned. _____ _____ _____

CUE: When the examinee begins to use the Plant Process computer to obtain printouts, inform the examinee "Another NSO has printed the Control Rod Printout and a LPRM Printout, the QNE has reviewed the printouts and has no concerns."

5. Obtain a Control Rod Printout and a LPRM Printout from the process computer (Reference DOP 9950-03 AND DOP 9950-07) to verify proper Control Rod Position and LPRM flux profile.

Uses a Plant Process Computer terminal to print Control Rod and LPRM printouts.

_____ _____ _____

Job Performance Measure (JPM)

S-N-g Page 6 of 8 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment

  • 6. Place the RBM 7 Mode Selector Switch to the ZERO 2 position and then move it to the STANDBY Position.

Places the RBM 7 Mode Selector Switch to the ZERO 2 positi on AND then to STANDBY.

_____ _____ _____

NOTE: This will cause the card to perform a nulling sequence, the RBM 7 INOP light will go on and the NO BALANCE Light for RBM 7 on Panel 902

-37 will go out.

  • 7. Place the RBM Mode Selector Switch to the OPERATE Position.

Places the RBM 7 Mode Selector Switch to OPERATE _____ _____ _____

NOTE: The RBM 7 INOP light on Panel 902

-37 will go out.

NOTE: At this point the JPM is complete, the examinee may return to the 902

-5 panel and reset annunciators.

8. Informs Unit Supervisor task is complete.

Examinee notifies the Unit Supervisor.

_____ _____ _____

CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-g Page 7 of 8 Operator's Name:

Job Title:

RO SRO JPM Title: RBM - Clear RBM Malfunction Revision Number: 00

JPM Number: S-N-g Task Number and Title: 201L016 , Respond to a rod out block.

K/A Number and Importance: 215001.A2.05 3.2 / 3.3

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control Room In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

15 minutes Actual Time Used:

minutes

References:

DOA 0700-03, rev 12 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print): Evaluator's Signature:

Date:

Job Performance Measure (JPM)

S-N-g Page 8 of 8 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Control rod moves were in progress when annunciator 902

-5 A-7, RBM HI/INOP was received.

3. Control rod withdrawal attempts were stopped.
4. DAN 902(3)

-5 A-7 RBM HI/INOP was ineffective in clearing the condition.

INITIATING CUE

1. The Unit Supervisor has directed you to clear the condition per DOA 0700

-03, ROD OUT BLOCKS.

2. Inform the Unit Supervisor when the task is complete.

Exelon Nuclear Job Performance Measure

SBGT - POST MAINTENANCE TESTING , WITH AUTO INITIATION JPM Number:

S-N-h Revision Number: 0 9 Date: 08/13 EXAM MATERIAL Developed By:

Instructor Date Approved By:

Facility Representative Date Job Performance Measure (JPM)

S-N-h Page 2 of 9 Revision Record (Summary)

Revision 0 8 Bank JPM. Revision 0 9 Revised for ILT 1 2-1 (201 3-301) NRC Exam

.

Job Performance Measure (JPM)

S-N-h Page 3 of 9 SIMULATOR SETUP INSTRUCTIONS

1. Reset the simulator to any low power IC with Reactor Building ventilation operating in a NORMAL lineup. NOTE: It is acceptable to use a similar IC to the IC listed above, provided the IC actually used is verified to be compatible with this and other JPMs that are scheduled to be run concurrently.
2. Ensure the 2/3A SBGT train is in STBY and the 2/3B SBGT train is in PRI. 3. Place control switches for Unit 2 and 3 DW and Torus Purge fans in PTL on 923-5 panel. 4. Insert following Malfunctions and/or Remotes:

Trg 1 "vgdstrta" (Causes Trigger 1 to activate when 2/3 SBGT control switch is place to START)

Imf radrbdah (1

70) (fails 'A' channel reactor building vent monitor high, to cause a Group II isolation 70 sec. after 2/3A SBGT switch is placed to START).
5. Setup the following Triggers:

None. DOCUMENT PREPARATION

1. Marked up copy of DOS 7500-02 , up to and including step E.
7.

Job Performance Measure (JPM)

S-N-h Page 4 of 9 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO. 2. Maintenance has been completed on 2/3 A SBGT train and the train is ready for post maintenance testing

. 3. The prerequisites of DOS 7500

-02 have been completed

. 4. IST testing is NOT required

5. Valve timing is NOT required.
6. No painting OR propane equipment operation has happened in the last 24 hours1 days <br />0.143 weeks <br />0.0329 months <br />

. 7. The Initial Cumulative Run Time has been recorded.

INITIATING CUE

1. The Unit 2 Supervisor has directed you to perform DOS 7500

-02 for the 2/3A SBGT train for post maintenance testing.

2. Notify the Unit 2 Supervisor when the task is complete

. Fill in the JPM Start Time when the student acknowledges the Initiating Cue.

Information For Evaluator's Use:

UNSAT requires written comments on respective step.

  • Denotes critical steps. Denotes critical elements of a critical step.

Number any comments in the "Comment Number" column on the following pages. Then annotate that comment in the "Comments" section at the bottom of the page. The comment section should be used to document the reason that a step is marked as unsatisfactory and to document unsatisfactory performance relating to management expectations.

Some operations that are performed from outside of the control room may require multiple steps.

These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.

The timeclock starts when the candidate acknowledges the initiating cue.

Job Performance Measure (JPM)

S-N-h Page 5 of 9 JPM Start Time

_________ PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: Provide the examinee with the provided copy of DOS 7500-02. 1. Ensure the following:

2/3 A and B AIR HEATERs are OFF.

2/3 A and B Fans are OFF. Correctly verifies:

GREEN lights illuminated

. GREEN lights illuminated

. _____ _____ _____

2. Verifies the following annunciators are NOT in alarm: 923-5 A-6, STBY GAS TRT SYS A TROUBLE 923-5 B-6, STBY GAS TRT SYS B TROUBLE Correctly verifies
NOT illuminate
d. NOT illuminated.

_____ _____ _____

  • 3. Verify "B" SBGT SELECT SWITCH in B STBY position.

Places 2/3 B SBGT SELECT switch in B STBY. _____ _____ _____

  • 4. Place 2/3 "A" SBGT SELECT SWITCH to START A position. Places the 2/3 "A" SBGT SELECT SWITCH to START A. _____ ____ _____

NOTE: The Initial Run Time data has already been recorded. (in the initial cues).

5. Record start time for SBGT SYSTEM TRAIN A INITIAL RUN DATA on Checklist 1

. Records the Start Time for SBGT Train "A" on Checklist 1

. _____ _____ _____

NOTE: 70 sec. after the 2/3A SBGT control switch is placed to START, a malfunction is automatically inserted to cause a Reactor Building Hi

-Hi Rad condition (auto start signal for SBGT). Depending on speed of candidate, the following step may or may NOT be completed prior to the malfunction being inserted.

6. Verifies the 2/3A SBGT train initiated properly.

Verifies the 2/3A SBGT train is initiated properly.

_____ _____ _____

Job Performance Measure (JPM)

S-N-h Page 6 of 9 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment NOTE: When Reactor Building Hi

-Hi rad signal is received, the examinee should recognize the need to perform the required Limitation and Action steps (which may be performed in any order)

. CUE: When Reactor Building Isolates (alarm 902

-3 F-14), provide the following cue: "Attention for an update, Reactor Building Vent Channel 'A' Rad Hi

-Hi alarm received" BEGIN ALTERNATE PATH

  • 7. Place the SELECT SWITCH for the non

-running train to PRI. Places the SELECT SWITCH for "B" SBGT train to PRI.

_____ ____ _____

  • 8. Place the control switch for the train under test to OFF.

Places the control switch

for "A" SBGT train to OFF. _____ _____ _____

9. Verify train in PRI has sufficient flow and the heater is operating.

Nominally ~4000 scfm

. _____ ____ _____

10. Place the Train previously under test to STBY. Places the control switch for "A" SBGT train to STBY. _____ _____ _____
11. Verifies a Reactor Building Isolation has occurred on Panel 923-4, verifying the following:

Trip of both units Reactor Building Vent Fans (Panel 923-5) Trip of both units' Reactor Building Exhaust Fans (Panel 923-5) Trip of both units Drywell and Torus Purge Fans (Panel 923-5) Closure of both units Reactor Building Ventilation Isolation Dampers (Panel 923-4) Verifies: YELLOW AUTO TRIP lights illuminated.

YELLOW AUTO TRIP lights illuminated. (No light change since purge fans are in PTL)

. RED lights illuminated.

_____ ____ _____

Job Performance Measure (JPM)

S-N-h Page 7 of 9 PERFORMANCE CHECKLIST STANDARDS SAT UNSAT Comment 12. Informs Unit Supervisor task is complete.

Examinee notifies the Unit Supervisor.

_____ _____ _____

CUE: Acknowledge report of task completion.

END JPM Stop Time

_________

Job Performance Measure (JPM)

S-N-h Page 8 of 9 Operator's Name:

Job Title: RO SRO JPM Title: SBGT - POST MAINTENANCE TESTING , WITH AUTO INITIATION Revision Number: 0 9

JPM N umber: S-N-h Task Number and Title: 261L002, Start the SBGT system.

K/A Number and Importance: 261000.A2.13 3.4 / 3.7

Suggested Testing Environment:

Simulator Actual Testing Environment:

Simulator Control R oom In-Plant Testing Method:

Simulate Alternate Path

Yes No Perform SRO Only: Yes No Time Critical:

Yes No Estimated Time to Complete:

15 minutes Actual Time Used:

minutes

References:

DOS 7500-02, rev 4 8 EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

Yes No The operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:

Satisfactory Unsatisfactory Comments: Evaluator's Name (Print): Evaluator's Signature: Date:

Job Performance Measure (JPM)

S-N-h Page 9 of 9 INITIAL CONDITIONS

1. You are the Unit 2 Aux NSO.
2. Maintenance has been completed on 2/3 A SBGT train and the train is ready for post maintenance testing

. 3. The prerequisites of DOS 7500

-02 have been completed.

4. IST testing is NOT required
5. Valve timing is NOT required.
6. No painting OR propane equipment operation has happened in the last 24 hours1 days <br />0.143 weeks <br />0.0329 months <br />. 7. The Initial Cumulative Run Time has been recorded.

INITIATING CUE

1. The Unit 2 Supervisor has directed you to perform DOS 7500

-02 for the 2/3A SBGT train for post maintenance testing.

2. Notify the Unit 2 Supervisor when the task is complete

.