MONTHYEARIR 05000341/20240032024-11-0606 November 2024 Integrated Inspection Report 05000341/2024003 IR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000016/20240012024-11-0101 November 2024 Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2024001 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 2024-09-09
[Table view] |
Text
LICENSEE:
FACILITY:
SUBJECT:
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O.C. 20555-0001 March 20, 2019 DTE Electric Company Fermi 2
SUMMARY
OF FEBRUARY 19, 2019, PUBLIC MEETING WITH DTE ELECTRIC COMPANY REGARDING UPCOMING LICENSE AMENDMENT REQUEST TO AMEND THE LICENSE BASIS TO ACCEPT THE ADDITIONAL DEBRIS SOURCES (EPID L-2019-LRM-0007)
On February 19, 2019, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of DTE Electric Company {DTE, or the licensee).
The purpose of the meeting was to discuss Fermi 2's upcoming license amendment request (LAR) which would request to amend the license to accept the debris sources beyond the current design basis. The meeting notice can be found in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML 19038A053.
The attendance list for the meeting is enclosed.
The licensee's presentation slides are available at ADAMS Accession No. ML 19045A269.
NRC/DTE Discussion The NRC staff and DTE discussed items that would be important to include in the LAR. The discussion between the NRC and DTE included the following:
- The NRC staff described the need to address the principles of risk-informed decision making (e.g., defense-in-depth, safety margin, performance monitoring) in the LAR, to quantify and address uncertainty (e.g., use of loss of coolant accident frequencies from NUREG-1829), and discuss assumptions regarding the risk evaluation.
- The NRC staff stated that the analysis for the LAR that Fermi 2 is performing should include sensitivity studies to help assess uncertainties.
The staff suggested that the licensee review the docketed information regarding the use of risk in assessing the effects of debris on long-term cooling submitted to the NRC by other power plants.
- The NRC staff stated that it will be validating the modeling performed for debris generation and transport to the emergency core cooling system strainers.
- The NRC staff stated that even if a break is isolated quickly, the damage to the insulation within the zone of influence probably had occurred prior to the isolation.
This should be addressed in the analysis.
- DTE clarified that the sensitivity studies for coatings and labeling will be done to define new licensing basis limits for these debris types. The staff stated that the 1/8 inch threshold assumption mentioned for the coatings sensitivity study would need to be justified.
- DTE provided clarifications regarding the content of their presentation.
These clarifications were beneficial to the NRC staff in understanding the proposed path forward.
- DTE stated that it expects to submit the LAR in fall of 2019 Two members of the public participated in the meeting by teleconference.
One member of the public referenced a recent NRC inspection finding of debris in the torus. The staff responded that NRC will be following up with the licensee to ensure that the recommended corrective actions are taken. Another member of the public was concerned that an operator may take actions that could makes things worse. The staff explained that the failure of operators to take beneficial actions is modeled and that staff's risk-informed decision-making includes consideration of defense-in-depth as well as safety margins thereby not relying solely on such operator actions. No regulatory decisions or commitments were made during the meeting. Please direct any inquiries to me at 301-415-8004, or Sujata.Goetz@nrc.gov.
Docket No. 50-341
Enclosure:
List of Attendees cc: Listserv /) 1/ +/-5-. .. .~ / '. i a_/ (fa{/~ll_
.. Sujat~ oetz, ~ct
- ger Plant icensing Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation 4 LIST OF ATTENDEES FEBRUARY 19, 2019 PUBLIC TELECONFERENCE MEETING WITH DTE ELECTRIC COMPANY NAME ORGANIZATION Sue Goetz NRC/NRR/DORL/LPL3 Josh Whitman NRC/NRR/DSS/SNPB Reed Anzalone NRC/NRR/DSS/SRXB Josh Wilson NRC/NRR/DSS/SRXB Yuri Orechwa NRC/NRR/DSS/SNPB Mehdi Reisi Fard NRC/NRR/DRA/APLB Shilp Vasarada NRC/NRR/DRA/APLB Steven Jones NRC/NRR/DSS/SCPB Steve Smith NRC/NRR/DSS/STSB Scott Maglio DTE Electric Company Jason Haas DTE Electric Company Phillip Summers DTE Electric Company Christopher Vukonich DTE Electric Company Kendra Hullum-Lawson DTE Electric Company Rondi Sloan DTE Electric Company Robert Choromokos DTE Electric Company Bruce Leittier DTE Electric Company Kent Sutton DTE Electric Company
SUBJECT:
SUMMARY
OF FEBRUARY 19, 2019, PUBLIC MEETING WITH DTE ELECTRIC COMPANY REGARDING UPCOMING LICENSE AMENDMENT REQUEST TO AMEND THE LICENSE BASIS TO ACCEPT THE ADDITIONAL DEBRIS SOURCES (EPID L-2019-LRM-0007)
DATED MARCH 20, 2019 DISTRIBUTION:
PUBLIC RidsACRS MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl3 Resource RidsNrrDssSrxb Resource RidsNrrDssSnpb Resource RidsNrrLASRohrer Resource RidsNrrPMFermi Resource RidsRgn3MailCenter Resource TWertz, NRR BHeida,NRR ADAMS Accession Nos.: Package: ML 19058A246 Meeting Notice: ML 19038A053 Slides: ML 19045A269 Meeting Summary: ML 19058A246 OFFICE NRR/DORL/LPL3/PM NAME SGoetz DATE 2/26/19 OFFICE NRR/DSS/DRA/BC NAME MReisi Fard DATE 2/26/19 NRR/DORL/LPL3/LA SRohrer 2/27/19 SGoetz SJones, RAnzalone JWilson JWhitman CTilton SVasavada MReisi Fard JWilson YOrechwa SSmith NRR/DSS/SNPB/BC Rlukes 2/25/19 NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM DWrona SGoetz 3/20/19 3/20/19 OFFICIAL RECORD COPY NRR/DSS/STSB/BC VCusumano 2/26/19