MONTHYEARML24289A0062024-10-21021 October 2024 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2024003 ML24289A2372024-10-15015 October 2024 Transmittal of Revision 1 Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles ML24262A2272024-09-18018 September 2024 Transmittal of Additional Errata Pages for WCAP-18830-P (Proprietary) and WCAP-18830-NP (Non-Proprietary), Turkey Point Fuel Storage Criticality Analysis for 24 Month Cycles ML24228A2952024-08-15015 August 2024 Westinghouse Electric Company, LLC - NRC Semi-Annual Discharge Report (Jan - June 2024) ML24176A2762024-06-24024 June 2024 Westinghouse Electric Company LLC, Submittal of Slides for the June 27, 2024, Partially Closed Meeting with NRC Staff on the Designation of Buildings as Items Relied on for Safety ML24173A2992024-06-24024 June 2024 Westinghouse Columbia Fuel Fabrication Facility – Inspection Schedule for Calendar Year 2025 ML24138A1152024-05-21021 May 2024 Cover Letter - the U.S. Nuclear Regulatory Commission Approval Letter for Westinghouse Emergency Plan Change Request for Columbia Fuel Fabrication Facility ML24134A2742024-05-13013 May 2024 Submittal of Slide Packages for the May 16, 2024 Pre-Application Meeting with NRC on the Proposed License Amendment Request Re Low Enriched Uranium Plus Expansion at Columbia Fuel Fabrication Facility ML24128A2662024-05-13013 May 2024 Notification of New Licensing Project Manager for Westinghouses SNM-1151 for the Columbia Fuel Fabrication Facility ML24130A2492024-05-0909 May 2024 Submittal of Information in Support of Surry Power Station Unit 1 Thermal Shield Flexure Replacement Campaign ML24110A0502024-04-22022 April 2024 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2024001 ML24109A0002024-04-19019 April 2024 Public Meeting Summary - Licensee Performance Review for Westinghouse Columbia Fuel Fabrication Facility, Docket Number 70-1151 ML24110A1442024-04-19019 April 2024 Response to Request for Additional Information - Westinghouse Request for Prior Approval of Revision 24 of the Columbia Fuel Fabrication Facility (CFFF) Site Emergency Plan ML24080A5072024-03-20020 March 2024 Westinghouse, Request for Prior Approval of Revision 24 of the Columbia Fuel Fabrication Facility (CFFF) Site Emergency Plan ML24074A2962024-03-19019 March 2024 Cover Letter for WEC Correction to Amendment 3 ML24064A2542024-03-0707 March 2024 Westinghouse Electric Company, Licensee Performance Review of Licensed Activities - Nuclear Regulatory Commission Inspection Report No 70-1151/2024-005 ML24025A1292024-02-23023 February 2024 Westinghouse Electric Company, LLC, - Amendment 2, Request for Exemption from 24-Hour Reporting Requirement of Title 10 of the Code of Federal Regulations Paragraph 70.50(B)(1) ML24023A6952024-01-26026 January 2024 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 07001151/2023004 ML24026A1512024-01-25025 January 2024 Westinghouse Electric Company, LLC, Notice of Intent to Fabricate Low Enriched Uranium (Leu+) ML24017A2252024-01-22022 January 2024 Westinghouse Electric Company, LLC, Conveyance of Revised Standby Trust Agreement to Support the Decommissioning Funding Plan (Enterprise Project Identifier L-2023-DFA-0009) ML23349A2722023-12-14014 December 2023 Westinghouse, Submittal of Monthly Progress Reports Under Consent Agreement 19-02-HW with the South Carolina Department of Health and Environmental Control ML23338A3372023-12-0404 December 2023 Submittal of Amendment 4 to Standby Trust Agreement (STA) for License Nu. SNM-1107, Replacement of Trust Fund with Additional Surety Bonds, and Certification of Financial Assurance for SNM-1107 ML23311A0032023-11-0606 November 2023 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 70-1151/2023-402 (Cover Letter) ML23296A0362023-10-24024 October 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023003 ML23240A5082023-08-28028 August 2023 Westinghouse Electric Company LLC - NRC Semi-Annual Discharge Report (January- June 2023) ML23230B2022023-08-18018 August 2023 Westinghouse, Supplemental Information for Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23216A0712023-08-0404 August 2023 Westinghouse Columbia Fuel Fabrication Facility Physical Security Core Inspection Report 07001151/202340 ML23202A1472023-07-24024 July 2023 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2023002 ML23150A2362023-07-0303 July 2023 Letter to Westinghouse Regarding Effluent Testing Issue ML23184A1512023-06-29029 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report Revision ML23171B1502023-06-20020 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report ML23160A2612023-06-0909 June 2023 Westinghouse, Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23139A1942023-06-0505 June 2023 Westinghouse Electric Company LLC - Approval of Environmental Sampling and Monitoring Program ML23138A3762023-05-18018 May 2023 Westinghouse Submittal of Columbia Fuel Fabrication Facility Site Emergency Plan, Revision 23 ML23096A2812023-05-15015 May 2023 Letter - Transfer of Control Approval 2023 ML23094A1582023-05-0505 May 2023 Westinghouse Electric Company, LLC - Revision to Temporarily Store Hematite Ash Above License Limits and Removal of Uranium Flywheel ML23115A2382023-04-26026 April 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023001 ML23114A3592023-04-24024 April 2023 Westinghouse Submittal of Environmental Sampling and Monitoring Program for NRC Review and Approval ML23114A3612023-03-23023 March 2023 Enclosures 2 & 3 - SCDHEC Approval Letter of Westinghouse Ri Report, Dated March 23, 2023 and Environmental Sampling and Monitoring Program Section of SNM-1107 License Application ML23055A3022023-03-0808 March 2023 Letter - Westinghouse License Transfer Interim Threshold Determination ML23058A4482023-02-27027 February 2023 Request for Threshold Determination for Interim Transaction Included in December 20, 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals ML23058A2722023-02-27027 February 2023 Westinghouse, NRC Semiannual Discharge Report July - December 2022 ML23053A0712023-02-17017 February 2023 Westinghouse Electric Company LLC, Supplement to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23053A0752023-02-17017 February 2023 Westinghouse Electric Co. - Supplement 2 to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23047A4562023-02-16016 February 2023 Westinghouse, Response to Request for Additional Information - Request for Temporary License Amendment for Storage of Hematite Ash ML23024A2312023-01-30030 January 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151//2022004 ML23030B8552023-01-30030 January 2023 Westinghouse 10CFR70.72 Facility Change Report ML23013A2122023-01-27027 January 2023 Acceptance Letter for Westinghouse License Transfer - Cac/Epid L-2022-LLM-0004 ML23026A3642023-01-26026 January 2023 Westinghouse, January 2023 Updated Integrated Safety Analysis Summary ML22354A0732023-01-19019 January 2023 Response to Westinghouse Revised Funding Instrument in Support of the Decommissioning Funding Plan 2024-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 5, 2023 Jeff Ferguson, Environmental, Health and Safety Manager Westinghouse Electric Company LLC Columbia Fuel Site 5801 Bluff Road Hopkins, SC 29061-9121
SUBJECT:
WESTINGHOUSE ELECTRIC COMPANY LLC - APPROVAL OF ENVIRONMENTAL SAMPLING AND MONITORING PROGRAM
Dear Jeff Ferguson:
The U.S. Nuclear Regulatory Commission (NRC) reviewed the submission from Westinghouse Electric Company LLC (Westinghouse or WEC) requesting review and approval of the revised environmental sampling and monitoring program. The application was transmitted by letter dated April 24, 2023 (Agencywide Documents Access and Management System [ADAMS]
Accession Number ML23114A358). Westinghouse submitted its request pursuant to License Condition (LC) S-17 in the renewed license issued September 12, 2022 (ML22157A348).
The applicable LCs from SNM-1107(renewed 2022) are:
License Condition S-17: WEC shall submit its environmental sampling and monitoring program (Section 10.1.4 of the LRA) to the NRC for review and approval upon South Carolina Department of Health and Environmental Controls approval of the Remedial Investigation Report, or within five years of the license renewal (whichever comes first).
License Condition S-18: Within 90 days of submittal of the CA [Consent Agreement] final written report to SCDHEC, WEC shall submit its environmental sampling and monitoring program described in Section 10.1.4 of the LRA to the NRC for review and approval.
On March 23, 2023, the South Carolina Department of Health and Environmental Control (SC-DHEC) approved the Final Remedial Investigation Report (RI) for the Columbia Fuel Fabrication Facility (CFFF). Westinghouse provided a copy of the RI for the CFFF Site and the SC-DHEC approval letter in the request as supporting information. LC S-17 required the submission of the CFFF environmental sampling and monitoring program (Section 10.1.4 and associated tables and figures of the SNM-1107 License Application) once the RI was approved by SC-DHEC. No changes were made to the program as a result of the SC-DHEC review.
The NRC staff reviewed the April 24, 2023, submission and determined that the licensees revised monitoring and sampling program is acceptable and conforms to LC-17 because the program can properly delineate the plume boundaries of the contaminants of potential concerns.
Per LC S-18, the NRC staff will have another opportunity to review and approve the environmental sampling and monitoring program after Westinghouse submits the final written report under the Consent Agreement currently in place with SC-DHEC.
J. Ferguson 2 The NRC staff has completed its review of the April 24, 2023, request. This action closes activities under Enterprise Project Identifier L-2023-LLL-0010.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 2, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
If you have any questions regarding this matter, please contact Jenny Tobin at 301-415-2328, or via email at Jennifer.Tobin@nrc.gov.
Sincerely, Signed by Lav, Samantha on 06/05/23 Samantha C. Lav, Chief Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-1151 License No. SNM-1107 cc: westinghouse_ff@listmgr.nrc.gov Kim Kuhn, SC-DHEC kuhnkm@dhec.sc.gov