MONTHYEARML24249A1922024-08-21021 August 2024 News Release-II-24-023: NRC Schedules Pre-decisional Enforcement Conference with BWXT ML24052A0512023-08-24024 August 2023 News Release-II-23-024: NRC Proposes $87,500 Fine to BWXT ML24047A2712023-06-15015 June 2023 News Release-II-23-020: NRC Schedules Predecisional Enforcement Conference with BWXT ML22270A0822022-09-14014 September 2022 News Release-II-22-024: NRC Schedules Pre-Decisional Enforcement Conference with BWXT Press Release-II-19-010, NRC Names Senior Resident Inspector at BWXT Nuclear Fuel Facility in Lynchburg2019-04-0202 April 2019 Press Release-II-19-010: NRC Names Senior Resident Inspector at BWXT Nuclear Fuel Facility in Lynchburg Press Release-II-17-021, NRC Schedules Webinar to Discuss Safety Performance of Bwx Technologies Nuclear Fuel Facility2017-04-11011 April 2017 Press Release-II-17-021: NRC Schedules Webinar to Discuss Safety Performance of Bwx Technologies Nuclear Fuel Facility Press Release-II-17-007, NRC Names Senior Resident Inspector at BWXT Fuel Facility in Lynchburg2017-03-0808 March 2017 Press Release-II-17-007: NRC Names Senior Resident Inspector at BWXT Fuel Facility in Lynchburg Press Release-II-16-007, NRC Names New Senior Resident Inspector for BWXT Nuclear Fuel Facility in Lynchburg2016-03-14014 March 2016 Press Release-II-16-007: NRC Names New Senior Resident Inspector for BWXT Nuclear Fuel Facility in Lynchburg Press Release-II-10-002, NRC Proposes $32,500 Civil Penalty for Babcock & Wilcox in Lynchburg2010-01-12012 January 2010 Press Release-II-10-002: NRC Proposes $32,500 Civil Penalty for Babcock & Wilcox in Lynchburg Press Release-II-09-061, NRC Schedules Enforcement Conference with Babcock and Wilcox Nuclear Operations Group2009-10-29029 October 2009 Press Release-II-09-061: NRC Schedules Enforcement Conference with Babcock and Wilcox Nuclear Operations Group Press Release-II-09-053, NRC to Present Results of Licensee Performance Review at B&W Nuclear Operations Group in Lynchburg2009-09-21021 September 2009 Press Release-II-09-053: NRC to Present Results of Licensee Performance Review at B&W Nuclear Operations Group in Lynchburg Press Release-II-08-041, NRC Names New Senior Resident Inspector at BWXT Fuel Plant in Lynchburg2008-07-25025 July 2008 Press Release-II-08-041: NRC Names New Senior Resident Inspector at BWXT Fuel Plant in Lynchburg Press Release-II-08-002, NRC Proposes $32,500 Fine Against BWXT in Lynchburg, VA2008-01-24024 January 2008 Press Release-II-08-002: NRC Proposes $32,500 Fine Against BWXT in Lynchburg, VA 2024-08-21
[Table view] |
Text
No: II-23-020 June 15, 2023
Contact:
Dave Gasperson , 404-997-4417 NRC Schedules Predecisional Enforcement Conference with BWXT
The Nuclear Regulatory Commission staff will hold a predecisional enforcement conference with officials fromBWXT Nuclear Operations Group Inc. on June 21 to discuss two preliminary violations of regulatory requirements that occurred at the Lynchburg, Virginia, fuel fabrication facility in January 2023.
The conferencestarts at 10 a.m. Eastern time in Suite 800 at the NRCs Region II Office, Marquis One Tower, 245 Peachtree Center Avenue, NE, in Atlanta. The NRC staff will be available to answer questions from the public after the formal portion of the meeting.
Members of the public can also listen to the meeting by dialing 301-576-2978 and entering the conference number 753930684#.
The preliminary violations of NRC requirements were discovered after a January 19 event when a storage tank at BWXT's Uranium Recovery Facility overflowed, spilling uranium solution onto the floor and into a ventilation system. Two safety controls designed to prevent this failed, increasing the risk of an accidental criticality.
BWXT took immediate corrective actions in the affected area. The event did not endanger the plant workers, the public, or the environment.
A subsequent inspection revealed an apparent breakdown of safety controls designed to prevent an accidental criticality at BWXT's facility. The NRC's inspection findings related to that event are described in a May 5 inspection report .
During the conference, BWXT will have the opportunity to provide its perspective or additional information about the apparent violations. The NRC will review the information provided during the meeting and finalize its enforcement decision in a publicly available document.