ML19211A955

From kanterella
Revision as of 12:08, 19 October 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Initial Approach to Power Tests (B-Series),Interim Startup Rept 13 for 790823-1122
ML19211A955
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 11/22/1979
From:
PUBLIC SERVICE CO. OF COLORADO
To:
Shared Package
ML19211A954 List:
References
NUDOCS 7912210376
Download: ML19211A955 (2)


Text

.

.

.

THE FORT ST. VRAIN INITIAL APPROACH TO POWER TESTS (B-SERIES)

.

INTERIM REPORT 13 Report for Period Ending November 22, 1979 1637 123 7912210 3 76

, .

.

Inr.erim Report 8 covering the 90 day period ending August 22, 1978, re-ported the completion of all tests up to 70% of plant load. Since the Nuclear Regulatory Commission did not release the plant for operation at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending Novecher 22, 1979.

The Fort S t. Vrain Nuclear Generating Station was accepted for commercial operation at 70% power by Public Service Company of Colorado on July 1,1979.

Future interim reports will report the results of any startup tests at power levels above 70%.

.

.

.

-.

'GE FORT ST. VPE N INITIAL APPROACH TO POWER TESTS (B-SERIES)

.

INTERIM REPORT 13 Report for Period Ending November 22, 1979

,

s 9

1637 125

, .

A Interim Report 8 covering the 90 day period ending August 22, 1978, re-ported the completion of all tests up to 70% of plant load. Since the Nuclear Regulatory Commission did not release the plant for operation at power levels in excess of 70%, no further Initial Approach to Power Tests were performed during the 90 days ending November 22, 1979.

The Fort St. Vrain Nuclear Generating Station was accepted for commercial operation at 70% power by Public Service Company of Colorado on July 1,1979.

Future interim reports will report the results of any startup tests at power levels above 70%.

.

%