IR 05000259/2021011
ML21236A028 | |
Person / Time | |
---|---|
Site: | Browns Ferry |
Issue date: | 08/24/2021 |
From: | Shawn Smith Reactor Projects Region 2 Branch 6 |
To: | Jim Barstow Tennessee Valley Authority |
References | |
IR 2021011 | |
Download: ML21236A028 (13) | |
Text
August 24, 2021
SUBJECT:
BROWNS FERRY NUCLEAR PLANT - TEMPORARY INSTRUCTION 2515/TI-193 INSPECTION REPORT 05000259/2021011, 05000260/2021011, AND 05000296/2021011
Dear Mr. Barstow:
On August 6, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Browns Ferry Nuclear Plant. On August 13, 2021, the NRC inspectors discussed the results of this inspection with Mr. M. Rasmussen and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding did not involve a violation of NRC requirements.
If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Browns Ferry Nuclear Plant.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Steven P. Smith, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos. 05000259, 05000260, and 05000296 License Nos. DPR-33, DPR-52, and DPR-68
Enclosure:
As stated
Inspection Report
Docket Numbers: 05000259, 05000260 and 05000296 License Numbers: DPR-33, DPR-52 and DPR-68 Report Numbers: 05000259/2021011, 05000260/2021011 and 05000296/2021011 Enterprise Identifier: I-2021-011-0031 Licensee: TVA Facility: Browns Ferry Nuclear Plant Location: Athens, Alabama Inspection Dates: August 02, 2021 to August 06, 2021 Inspectors: B. Bishop, Senior Project Engineer S. Ninh, Senior Project Engineer Approved By: Steven P. Smith, Chief Reactor Projects Branch 6 Division of Reactor Projects Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Temporary Instruction 2515/TI-193 Inspection at Browns Ferry Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Hardened Containment Vent System Preventative Maintenance not Performed Within Periodicity Cornerstone Significance Cross-Cutting Report Aspect Section Barrier Integrity Green [H.5] - Work 2515/193 FIN Management 05000259,05000260,05000296/202101 1-01 Open/Closed The inspectors identified a finding of very low safety significance (Green) for the failure to perform the required surveillances within periodicity for the hardened containment vent system (HCVS). Specifically, HCVS valves are required to be stroked once per operating cycle per TVA final integrated plan, CNL-19-004, Table 3-3, Testing and Inspection Requirements. At the time of the inspection, the HCVS valves for each unit had been in service for greater than one cycle on each unit; however, these surveillances had never been performed.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL 2515/193 - Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions (1 Sample)
Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the reliable hardened containment wetwell vent as described in the plant specific submittals and the associated NRC safety evaluation (ADAMS Accession No. ML19329E319), and determined that the licensee was in compliance with NRC Order EA-13-109 Phase 1, Reliable, Severe Accident Capable Wetwell Venting System (ADAMS Accession No. ML13143A321).
The inspectors evaluated licensee implementation of the appropriate elements of the reliable hardened containment wetwell vent as described in the plant specific submittals and the associated NRC safety evaluation (ADAMS Accession No.
ML19329E319). Specifically, the inspectors evaluated licensee implementation of the Hardened Containment Vent System (HCVS) functional requirements, design features, maintenance and testing, quality standards, and programmatic requirements as described in Appendix A of TI 2515/193 Revision 1.
The inspectors verified that the licensee satisfactorily:
- Developed and implemented adequate maintenance and testing of HCVS equipment to ensure their availability and capability;
- Developed and issued procedures to safely operate the HCVS using normal power supplies, during Extended Loss of All AC Power (ELAP), and a postulated severe accident scenario, and integrated the procedures into existing plant procedures; and
- Trained their staff to assure personnel can proficiently operate the HCVS.
Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the reliable wetwell venting strategy as described in the plant specific submittals and the associated safety evaluation (ADAMS Accession No. ML19329E319) and determined that the licensee was in compliance with NRC Order EA-13-109 Phase 2, Reliable, Severe Accident Capable Drywell (or alternative strategy) Venting System (ADAMS Accession No.
The inspectors evaluated licensee implementation of the appropriate elements of the reliable wetwell venting strategy as described in the plant specific submittal(s) and the associated NRC safety evaluation (ADAMS Accession No. ML19329E319).
Specifically, the inspectors evaluated licensee implementation of Severe Accident Water Addition / Severe Accident Water Management (SAWA/SAWM) functional requirements, installed instrumentation, maintenance and testing, and programmatic requirements as described in Appendix B of TI 2515/193 Revision 1.
The inspectors verified that the licensee satisfactorily developed a strategy making it unlikely that venting from the containment drywell would be necessary. As part of that strategy, the licensee:
- Implemented the Severe Accident Water Addition (SAWA)/Severe Accident Water Management (SAWM) systems as defined and fulfilled functional requirements for installed and portable equipment.
- Installed and/or identified the previously-installed instrumentation necessary to implement SAWM;
- Developed and implemented adequate maintenance and testing of SAWA/SAWM equipment to ensure availability and capability;
- Developed and issued procedures to safely operate the SAWA/SAWM during an ELAP and during postulated severe accident scenario, and integrated their procedures into their existing plant procedures such that entry into and exiting from the procedures are clear when using existing plant procedures; and
- Trained their staff to assure personnel can proficiently operate the HCVS during ELAP and accident scenarios.
INSPECTION RESULTS
Hardened Containment Vent System Preventative Maintenance not Performed Within Periodicity Cornerstone Significance Cross-Cutting Report Aspect Section Barrier Integrity Green [H.5] - Work 2515/193 FIN Management 05000259,05000260,05000296/20210 11-01 Open/Closed The inspectors identified a finding of very low safety significance (Green) for the failure to perform the required surveillances within periodicity for the hardened containment vent system (HCVS). Specifically, HCVS valves are required to be stroked once per operating cycle per TVA final integrated plan, CNL-19-004, Table 3-3, Testing and Inspection Requirements. At the time of the inspection, the HCVS valves for each unit had been in service for greater than one cycle on each unit; however, these surveillances had never been performed.
Description:
Order EA-13-109, Attachment 2, Section 1.2.13 requires that the HCVS include features and provisions for the operation, testing, inspection, and maintenance adequate to ensure that reliable function and capability are maintained. Relevant guidance is found in NEI 13-02 Sections 5.4 and 6.2; and HCVS-FAQs-05 and -06. TVAs Final Integrated Plan, CNL-19-004, Table 3-3, (Testing and Inspection Requirements) defines the surveillance requirements for the HCVS system.
Browns Ferry Hardened Containment Vent System PMs 137277,137278, 137279, 137280, 138726, 149220, 149222, 149223 were not completed within periodicity. Under the testing requirements of DCNs 71389, 71390, and 71391, cycling of the HCVS valves and the interfacing system boundary valves not used to maintain containment integrity during operations must be cycled once every operating period. After 2 successful performances the test frequency may then be reduced to a maximum of once every other operating cycle. The compliance dates which signal the start of the frequency clock are Unit 1, Nov 2018 ( 1R12),
Unit 3, March 2018 (3R18) and Unit 2, April 2019 (2R20). These frequency due dates have been surpassed by one operating period for each unit. (CR1712139). At the time of the inspection, the HCVS valves for each unit had been in service for greater than one cycle on each unit, however, these surveillances had never been performed.
There were missed opportunities to identify and correct this issue based on related deficiencies identified by TVA. See bulleted examples below.
- A TVA Self-Assessment for NRC Order EA 13-109 conducted in 2019 noted that PMs required to be performed in accordance with NEI 13-02 had not been created for all HCVS and SAWA components. (CR 1548744).
- Inspectors noted that Browns Ferry had identified in 2018 that PMs for HCVS batteries were not in periodicity (CR 1396691)
Corrective Action References: CR 1396691, CR 1548744, CR 1712139
Performance Assessment:
Performance Deficiency: Failure to comply with TVAs Final Integrated Plan, CNL-19-004, Table 3-3, Test and Inspection Requirements, was a performance deficiency. The self-imposed surveillance requirements for Browns Ferry Hardened Containment Vent System, PMs 137277,137278, 137279, 137280, 138726, 149220, 149222, 149223, were not completed within periodicity. Under the testing requirements of DCNs 71389, 71390, and 71391, cycling of the HCVS valves and the interfacing system boundary valves not used to maintain containment integrity during operations must be cycled once every operating period. The compliance dates which signal the start of the frequency clock are Unit 1, Nov 2018 ( 1R12), Unit 3, March 2018 (3R18) and Unit 2, April 2019 (2R20). These frequency due dates have been surpassed by one operating period for each unit. (CR1712139).
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the SSC and Barrier Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors consulted Exhibit 3, Barrier Integrity, screening questions, Section C, Reactor Containment. The finding screened as Green, or of very low safety significance.
Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities.
Enforcement:
Inspectors did not identify a violation of regulatory requirements associated with this finding.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On August 13, 2021, the inspectors presented the Final NRC inspection results to Mr. M.
Rasmussen and other members of the licensee staff.
- On August 6, 2021, the inspectors conducted an Onsite Exit Meeting to communicate preliminary inspection results to Mr. Rasmussen and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
2515/193 Corrective Action 1069208
Documents 1139619
21098
23245
27133
247751
268370
280296
289350
1338591
1396191
1396691
1397180
1399201
1399627
1417198
1417207
28829
1502376
1548744
1548751
1548757
1548759
1548763
1611594
1645279
Corrective Action BFN HCVS Inspection - NRC observation CILRT spool piece 08/04/2021
Documents 1712118
Resulting from 1711983 BFN HCVS Inspection - NRC observation- the lighting is very 08/04/2021
Inspection poor in the diesel generator buildings
1711987 BFN HCVS Inspection - NRC observation- there are large 08/04/2021
doors/panels stored under the stairs in the area of the HCVS
Inspection Type Designation Description or Title Revision or
Procedure Date
Nitrogen bottles that could possibly impact an operators ability
to operate the equipment.
137277,137278,137279,137280,138726,149220,149222,149223
not completed within periodicity
1712329 HCVS Flex Inspection item concerning throttling Dominator 08/05/2021
flowrate
1712439 During the NRC HCVS Inspection, the NRC Inspector noted the 08/04/2021
need for an enhancement to FSIs
Miscellaneous Tennessee Valley Authority, Browns Ferry Nuclear Plant, Unit 3, 05/31/2018
Completion of Required Action for NRC Order EA-13-109,
Reliable Hardened Containment Vents Capable of Operation
Under Severe Accident Conditions (CAC No. MF4542)
Tennessee Valley Authority, Browns Ferry Nuclear Plant, Unit 2, 6/01/2019
Completion of Required Action for NRC Order EA-13-109,
Reliable Hardened Containment Vents Capable of Operation
Under Severe Accident Conditions (CAC No. MF4541)
Tennessee Valley Authority, Browns Ferry Nuclear Plant, Unit 1, 01/22/2019
Completion of Required Action for NRC Order EA-13-109,
Reliable Hardened Containment Vents Capable of Operation
Under Severe Accident Conditions (CAC No. MF4540)
Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Safety 01/02/2020
Evaluation Regarding Implementation of Hardened Containment
Vents Capable of Operation Under Severe Accident Conditions
Related to Order EA-13-109 (CAC NO
- S. MF4540, MF4541,
AND MF4542; EPID NO. L-2014-JLD-0044)
Licensed operator Requalification TPD-LQR Training Program Revision 16
Description
TVA NPG Fleet Attachment A Browns Ferry Non-Licensed Revision 4
Operator Initial Training and Qualification Curricula List, TPD-
NLO/ATT A Training Program Description
TVA NPG Fleet Attachment A Browns Ferry ILT Training and Revision 15
Qualification Curricula List TPD-ILT/ATT A Training Program
Description,
Inspection Type Designation Description or Title Revision or
Procedure Date
0-TPP-ENG- Diverse and Flexible Coping Strategies (FLEX) Program Bases Revision 5
2(Bases) Document
Procedures BFN-ODM-4.20 Strategies for Successful Transient Mitigation Revision 8
0-AOI-57-1A Loss of Offsite Power (161 and 500 KV)/Station Blackout Revision 114
0-FSI-1 Flex Response Revision 4
0-TI-641, Time Time Critical Operator Actions Revision 0
Critical Operator
Actions, Revision
0000
1-AOI-64-1 Drywell Pressure and/or Temperature High, or Excessive Revision 3
Leakage Into Drywell
1-EOI Appendix- Emergency Venting Primary Containment Revision 4
2-AOI-64-1 Drywell Pressure and/or Temperature High, or Excessive Revision 27
Leakage into Drywell
2-EOI Appendix- Emergency Venting Primary Containment Revision 10
3-AOI-64-1 Drywell Pressure and/or Temperature High, or Excessive Revision 6
Leakage Into Drywell
3-EOI Appendix- Emergency Venting Primary Containment Revision 7
OPDP-8 Operability Determination Process and Limiting Conditions for Revision 27
Operation,
Work Orders 118805616
118805646
119057106
119062924
119573383
119610739
119617796
119673383
119920141
20122431
20251758
Inspection Type Designation Description or Title Revision or
Procedure Date
20446347
20486376
20537137
20622950
20746573
20746979
20747395
20904051
20921315
20972793
21035985
21035987
21036645
21144575
21159471
21292184
21346543
119617796
119920141
20446347
20486376
21035985
21035987
10