{{#Wiki_filter:From:                               Buckberg, Perry Sent:                               Monday, April 4, 2022 9:41 AM To:                                 Taylor, Andrew Charles Cc:                                 Rymer, Stuart Loveridge; Wrona, David
{{#Wiki_filter:From: Buckberg, Perry Sent: Monday, April 4, 2022 9:41 AM To: Taylor, Andrew Charles Cc: Rymer, Stuart Loveridge; Wrona, David


==Subject:==
==Subject:==
Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)
Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)
: Andy, By {{letter dated|date=March 15, 2022|text=letter dated March 15, 2022}}, Tennessee Valley Authority submitted a request for an alternative for Sequoyah Nuclear Plant, Units 1 and 2. The proposed alternative would allow operation for 1 cycle if certain pressure isolation valves undergo mechanical agitation as a means to achieve acceptable valve seat leakage. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
: Andy,
 
By {{letter dated|date=March 15, 2022|text=letter dated March 15, 2022}}, Tennessee Valley Authority submitted a request for an alternative for Sequoyah Nuclear Plant, Units 1 and 2. The proposed alternative would allow operation for 1 cycle if certain pressure isolation valves undergo mechanical agitation as a means to achieve acceptable valve seat leakage. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Pursuant to Sections 50.55a(z)(1) and 50.55a(z)(2) of Title 10 of the Code of Federal Regulations (10 CFR), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.
Pursuant to Sections 50.55a(z)(1) and 50.55a(z)(2) of Title 10 of the Code of Federal Regulations (10 CFR), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal and discussions during the pre-application meeting on February 16, 2022, the NRC staff has estimated that this licensing request will take approximately 174 hours to complete. The NRC staff expects to complete this review by October 15, 2022, as requested in the March 15, 2022, submittal. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
Based on the information provided in your submittal and discussions during the pre-application meeting on February 16, 2022, the NRC staff has estimated that this licensing request will take approximately 174 hours to complete. The NRC staff expects to complete this review by October 15, 2022, as requested in the March 15, 2022, submittal. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
: Thanks, Perry Buckberg Senior Project Manager / Agency 2.206 Petition Coordinator U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation
: Thanks, Perry Buckberg Senior Project Manager / Agency 2.206 Petition Coordinator U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation office: (301)415-1383 perry.buckberg@nrc.gov Mail Stop O-8B1a, Washington, DC, 20555-0001


office: (301)415-1383 perry.buckberg@nrc.gov Mail Stop O-8B1a, Washington, DC, 20555-0001
Hearing Identifier: NRR_DRMA Email Number: 1588


Hearing Identifier:    NRR_DRMA Email Number:          1588 Mail Envelope Properties     (PH0PR09MB76748553D7BD5E0A8771057A9AE59)
Mail Envelope Properties (PH0PR09MB76748553D7BD5E0A8771057A9AE59)


==Subject:==
==Subject:==
Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)
Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)
Sent Date:             4/4/2022 9:41:01 AM Received Date:         4/4/2022 9:41:00 AM From:                   Buckberg, Perry Created By:             Perry.Buckberg@nrc.gov Recipients:
Sent Date: 4/4/2022 9:41:01 AM Received Date: 4/4/2022 9:41:00 AM From: Buckberg, Perry
 
Created By: Perry.Buckberg@nrc.gov
 
Recipients:
"Rymer, Stuart Loveridge" <slrymer@tva.gov>
"Rymer, Stuart Loveridge" <slrymer@tva.gov>
Tracking Status: None "Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None "Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None "Taylor, Andrew Charles" <actaylor@tva.gov>
Tracking Status: None "Taylor, Andrew Charles" <actaylor@tva.gov>
Tracking Status: None Post Office:           PH0PR09MB7674.namprd09.prod.outlook.com Files                           Size                   Date & Time MESSAGE                         3059                   4/4/2022 9:41:00 AM Options Priority:                       Normal Return Notification:           No Reply Requested:               No Sensitivity:                   Normal Expiration Date:}}
Tracking Status: None
 
Post Office: PH0PR09MB7674.namprd09.prod.outlook.com
 
Files Size Date & Time MESSAGE 3059 4/4/2022 9:41:00 AM
 
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:}}

Revision as of 12:25, 18 November 2024

NRR E-mail Capture - Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)
ML22095A018
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 04/04/2022
From: Perry Buckberg
NRC/NRR/DORL/LPL2-2
To: Taylor A
Tennessee Valley Authority
Buckberg P
References
L-2022-LLR-0034
Download: ML22095A018 (3)


Text

From: Buckberg, Perry Sent: Monday, April 4, 2022 9:41 AM To: Taylor, Andrew Charles Cc: Rymer, Stuart Loveridge; Wrona, David

Subject:

Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)

Andy,

By letter dated March 15, 2022, Tennessee Valley Authority submitted a request for an alternative for Sequoyah Nuclear Plant, Units 1 and 2. The proposed alternative would allow operation for 1 cycle if certain pressure isolation valves undergo mechanical agitation as a means to achieve acceptable valve seat leakage. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.

The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Pursuant to Sections 50.55a(z)(1) and 50.55a(z)(2) of Title 10 of the Code of Federal Regulations (10 CFR), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal and discussions during the pre-application meeting on February 16, 2022, the NRC staff has estimated that this licensing request will take approximately 174 hours0.00201 days <br />0.0483 hours <br />2.876984e-4 weeks <br />6.6207e-5 months <br /> to complete. The NRC staff expects to complete this review by October 15, 2022, as requested in the March 15, 2022, submittal. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

Thanks, Perry Buckberg Senior Project Manager / Agency 2.206 Petition Coordinator U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation office: (301)415-1383 perry.buckberg@nrc.gov Mail Stop O-8B1a, Washington, DC, 20555-0001

Hearing Identifier: NRR_DRMA Email Number: 1588

Mail Envelope Properties (PH0PR09MB76748553D7BD5E0A8771057A9AE59)

Subject:

Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034)

Sent Date: 4/4/2022 9:41:01 AM Received Date: 4/4/2022 9:41:00 AM From: Buckberg, Perry

Created By: Perry.Buckberg@nrc.gov

Recipients:

"Rymer, Stuart Loveridge" <slrymer@tva.gov>

Tracking Status: None "Wrona, David" <David.Wrona@nrc.gov>

Tracking Status: None "Taylor, Andrew Charles" <actaylor@tva.gov>

Tracking Status: None

Post Office: PH0PR09MB7674.namprd09.prod.outlook.com

Files Size Date & Time MESSAGE 3059 4/4/2022 9:41:00 AM

Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: