Line 5: |
Line 5: |
| | author name = Flynn J | | | author name = Flynn J |
| | author affiliation = Palisades Park Country Club, Inc | | | author affiliation = Palisades Park Country Club, Inc |
| | addressee name = Burns S G | | | addressee name = Burns S |
| | addressee affiliation = NRC/Chairman | | | addressee affiliation = NRC/Chairman |
| | docket = 05000255 | | | docket = 05000255 |
Revision as of 18:24, 20 June 2019
|
---|
Category:E-Mail
MONTHYEARML24248A0902024-08-28028 August 2024 Steam Generator Inspection Call ML24192A0012024-07-0606 July 2024 (E-Mail) Palisades Nuclear Plant - Plant - Draft Request for Additional Information: Palisades Operating TS License Amendment Request - June 6, 2024 ML24187A1332024-07-0505 July 2024 LTR-24-0069 Emailed Response Regarding Palisades Restart Project ML24192A1472024-06-28028 June 2024 Email - Palisades Nuclear Plant - Draft Request for Additional Information: Palisades Administrative TS License Amendment Request - June 28, 2024 ML24192A1672024-06-28028 June 2024 Restart - NRC Request for Additional Information - EP ORO Coordination - June 28, 2024 ML24135A3542024-05-20020 May 2024 NRC Response to Jody Flynn of Michigan Regarding Statements Made About Holtec in the April 25, 2024 Peekskill Herald Article: Holtec Playing Fast and Loose with Taxpayers Money by Tina Volz-Bongar (Docket 50-255) ML24141A0862024-05-16016 May 2024 Notification of NRC Activities Regarding Palisades Restart ML24170A8812024-05-15015 May 2024 NRR E-mail Capture - Post Acceptance/Abeyance Process for the 10 CFR 2.206 Petition on Palisades Misuse of Decommissioning Trust Fund ML24032A2442024-02-0101 February 2024 OEDO-24-00011 - 10 CFR 2.206 Petition Holtec Misuse Decommissioning Fund- Email to Petitioner ML24005A1262024-01-0505 January 2024 Permanently Defueled Emergency Plan Implementation Notification ML23055A1532023-02-24024 February 2023 Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22343A1902022-12-0909 December 2022 Acceptance Review: Palisades Proposed Exemption from 10 CFR 140.11 (a)(4) Primary and Secondary Liability Insurance ML22343A2282022-12-0909 December 2022 Acceptance Review: Palisades Proposed Exemption from 10 CFR 50.54(w)(1) - Onsite Property Damage Insurance ML22284A0502022-10-0707 October 2022 Acceptance Review: License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML22227A0092022-08-12012 August 2022 Acceptance Review: License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme (L-2022-LLA-0099) ML22227A0082022-08-12012 August 2022 Acceptance Review: Exemption Request from 10CFR50.47(b), 10 CFR 50.47(c)(2), and 10 CFR Part 50, Appendix E, Section IV ML22179A0752022-06-28028 June 2022 E-mail from Entergy Dated June 28, 2022, Notification of Palisades and Big Rock Point License Transfer (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) ML22159A2672022-06-0202 June 2022 Answers to Your Questions on Palisades ML22159A2652022-05-0303 May 2022 Questions Asked at Palisades Plant Performance Public Meeting April 26, 2022 ML21328A0062021-11-18018 November 2021 NRR E-mail Capture - (External_Sender) State of Michigan Response - Palisades Nuclear Plant and Big Rock Point Plant - Application for Order Consenting to Transfers of Licenses and Conforming License Amendments ML22208A1052021-11-16016 November 2021 NRR E-mail Capture - (External_Sender) State of Michigan Response - Palisades - Preparation for Issuance of Final Environmental Assessment and Finding of No Significant Impact Holtec Exemption Request to Use Dtf ML21309A5152021-11-0505 November 2021 NRR E-mail Capture - Palisades Nuclear Plant - Preparation for Issuance of Final Environmental Assessment and Finding of No Significant Impact Holtec Exemption Request to Use Dtf ML21309A2982021-11-0505 November 2021 NRR E-mail Capture - Palisades Nuclear Plant and Big Rock Point Plant - Application for Order Consenting to Transfers of Licenses and Conforming License Amendments ML21209A9802021-07-28028 July 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Requested Licensing Action, Rescission of Interim Compensatory Measure from Order EA-02-026 ML21189A2462021-07-0606 July 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Requested Licensing Action, Proposed Partial Exemption from Record Retention Requirements ML21189A0432021-07-0606 July 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Requested Licensing Action, Permanently Defueled Technical Specifications ML21054A1822021-02-23023 February 2021 NRR E-mail Capture - Regarding Public Comment on Palisades Request for Relief RR 5-8 ML21028A4092021-01-27027 January 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of Holtec Exemption Request from 10CFR50.82(a)(8)(i)(A) and 10CFR50.75(h)(1)(iv) ML21028A0552021-01-27027 January 2021 NRR E-mail Capture - Palisades Nuclear Plant - Acceptance of License Transfer Application ML21007A3752021-01-0707 January 2021 NRR E-mail Capture - Regarding Public Comment on Palisades Nuclear Plant License Transfer (Sierra Club Nuclear Free Michigan) ML21054A1812021-01-0606 January 2021 NRR E-mail Capture - (External_Sender) Regarding Public Comment on Palisades Request for Relief RR 5-8 ML20275A3432020-10-0101 October 2020 Verbal Authorization for Proposed Alternative (RR 5-8) Reactor Vessel Closure Head Penetration Repairs ML20272A0112020-09-26026 September 2020 Request for Additional Information - Palisades Relief Request RR 5-8 (Proposed Alternative) for Reactor Pressure Vessel Head Penetration Repairs ML20262G9622020-09-17017 September 2020 Acknowledgement to Mr. Muhich e-mail, Dated September 15, 2020 (e-mail) ML20241A1802020-08-27027 August 2020 NRR E-mail Capture - Palisades Nuclear Plant- Upcoming Steam Generator Tube Inservice Inspection ML20162A4522020-04-0808 April 2020 Lake Mich Level Correspondence with Ipotter ML19344C7162019-08-25025 August 2019 Response from NEIMA Local Community Advisory Board Questionnaire 08-25-2019 C Ferry ML19344C8072019-08-16016 August 2019 Scanned Response 09-29-2019 I Potter ML19226A2932019-08-14014 August 2019 NRR E-mail Capture - Request for Additional Information Re License Amendment Request to Adopt TSTF-425, Revision 3 for the Palisades Nuclear Plant ML19226A2922019-08-0505 August 2019 NRR E-mail Capture - Draft Request for Additional Information for Palisades License Amendment Request to Adopt TSTF-425 ML19122A4852019-04-29029 April 2019 NRR E-mail Capture - Request for Additional Information for Palisades License Amendment Request to Revise License Conditions Related to NFPA 805 Modifications ML19095A6572019-04-0505 April 2019 NRR E-mail Capture - Acceptance for Review of Application to Revise the Palisades Nuclear Plant License Renewed Facility Operation License Regarding Full Compliance Implementation Date for the Fire Protection Program ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML19059A0292019-02-27027 February 2019 NRR E-mail Capture - Acceptance Review Results for License Amendment Request to Adopt TSTF-529, Revision 4, Clarify Use and Application Rules, for Entergy Fleet ML19009A5392019-01-0909 January 2019 NRR E-mail Capture - Request for Additional Information for Palisades License Amendment Request to Revise Emergency Diesel Generator Degraded Voltage Surveillance Requirement 3.3.5.2a ML19009A5382018-12-12012 December 2018 NRR E-mail Capture - Draft Request for Additional Information for Palisades License Amendment Request to Revise Emergency Diesel Generator Degraded Voltage Surveillance Requirement 3.3.5.2a ML18337A1382018-11-30030 November 2018 NRR E-mail Capture - Request for Additional Information Related to Palisades Relief Request Number RR 5-7 ML18337A1352018-11-30030 November 2018 NRR E-mail Capture - Acceptance for Review of Application to Revise the Palisades Nuclear Plant License Renewed Facility Operation License Regarding Changes to the Fire Protection Plan ML18337A1402018-11-29029 November 2018 NRR E-mail Capture - Draft Request for Additional Information Related to Palisades Relief Request 5-7 ML18184A2402018-07-0303 July 2018 NRR E-mail Capture - Acceptance for Review of Application to Revise Technical Specification Surveillance Requirement 3.3.5.2a for the Diesel Generator Undervoltage Start 2024-08-28
[Table view] |
Text
CHAIRMAN Resource From: Sent: To: Jody Flynn <jodygflynn@gmail.com>
Thursday, September 10, 2015 8:34 AM CHAIRMAN Resource
Subject:
[External_Sender]
Entergy Palisades Nuclear Power Plant Coupons Follow Up Flag: Flag Status: Follow up Flagged From: Palisades Park Country Club, Inc. 79336 Ravine Way Covert, Michigan 49043 To: Mr Stephen G. Bums, Chairman U.S. Nuclear Regulatory Commission Washington, D>C> 20555-0001
Subject:
Entergy Nuclear Power Plant-Covert, Michigan Pressurized Reactor Vessel -Embrittlement We are writing you again in hopes you will make Entergy pull the coupons and read the state of embrittlement of the Palisades Nuclear Power Plant. We are concerned homeowners that border that plant in Covert, Michigan.
The name of the plant comes from our community, Palisades Park. We have been in existence since 1905 and currently consist of about two hundred homes. As a member of the regulating body, we are asking you to look into a very timely and critical situation concerning embrittlement testing of the Palisades Nuclear 1 Power Plants reactor pressure vessel. Palisades' pressure vessel is acknowledged as the most embrittled in the United States and one of the oldest in the world. Anthony Vitale, Site Vice President at Entergy Palisades Nuclear Plant, and seven other employees of Entergy came to our members meeting in early August of this year and made a direct statement that pulling the coupons would not give Entergy more accurate information than using mathematical "interpolations".
If this were true, why would Entergy be so adamantly avoiding pulling the coupons? If the concern of Entergy were to assure the vessels embrittlement state is safe, why would they not do both? We do not believe that Entergy wants to find out the level of embrittlement of this critical vessel. We are hoping the NRC will mandate the physical testing of these coupons as the Atomic Safety Board mandated in June of this year. Please help us feel safe by making them read the data from the pulled coupons. You know they have not read that data since 2003. Entergy' s' Palisades Nuclear Power Plant is on the shores of Lake Michigan, one of the largest body of freshwater in North America. It is the source of drinking water for millions of Americans.
Safety margins that have been built into the regulation of nuclear power plants should not be weakened, especially in the case of pressure vessels at aging facilities.
Palisades has exceeded its original design life of forty years. Scrutiny of the Palisades pressure vessel should be strengthened, not diminished, as Entergy proposes.
We rely on you to help protect us from potential harm. When it comes to safety, the precautionary principal should apply. Continuing to use a potentially embrittled pressure vessel that raises threats of harm to human health and/or the environment should not be allowed. They should be made to test the coupons, which were put there specifically to gather embrittlement data. Thank you for protecting us* and using the precautionary principal to make sure we will all be safe and our environment will as well. Palisades Park Country Club, Inc. 2