| title = River Bend Station: Request for Additional Information Concerning New Technical Specification for Control Building Air Conditioning (L-2017-LLA-0291)
| title = Station: Request for Additional Information Concerning New Technical Specification for Control Building Air Conditioning (L-2017-LLA-0291)
| author name = Regner L M
| author name = Regner L M
| author affiliation = NRC/NRR/DORL/LPLIV
| author affiliation = NRC/NRR/DORL/LPLIV

Revision as of 15:10, 5 April 2019

Station: Request for Additional Information Concerning New Technical Specification for Control Building Air Conditioning (L-2017-LLA-0291)
ML18060A153
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/01/2018
From: Regner L M
Plant Licensing Branch IV
To: Coates A R, Schenk T A
Entergy Nuclear Operations
References
L-2017-LLA-0291
Download: ML18060A153 (2)


Text

1 NRR-DMPSPEm Resource From: Regner, Lisa Sent: Thursday, March 01, 2018 10:01 AM To: Coates, Alyson; SCHENK, TIM Cc: Regner, Lisa

Subject:

Final Request for Additional Information - River Bend CBAC Request (L-2017-LLA-0291)Final Request for Additional Information (EPID L-2017-LLA-0291)

On February 16, 2018, the U.S. NRC staff sent River Bend Station (RBS, the licensee) a draft Request for Additional Information (RAI). The RAI questions relate to a license amendment request (LAR) that proposes to increase the allowed outage time and add a new technical specification (TS) for the Control building air conditioning system for RBS.

On February 27, 2018, the NRC staff held a clarification call with RBS; following the call, the licensee stated that it understood all of the questions and would respond within 30 days of the date of this email. If RBS does not respond by this date, the requested completion date for the LAR may not be met by the NRC.

The NRC staff also informed the licensee that a publicly av ailable version of this final RAI would be placed in the NRC's Agencywide Documents Access and Management System (ADAMS).

By letter dated September 8, 2017 (ADAMS Accession No. ML17255A463, the Entergy requested an amendment to the Operating License related to a new TS for the control building air conditioning system for RBS. The amendment proposes to add TS 3.7.7 "Control Building Air Conditioning (AC) System," and associated limiting condition for operation and surveillance requirements to allow completion of minor

maintenance activities and reduce the need for plant s hutdowns. The NRC staff requires additional information to complete its review of this request as detailed in the attached document.

Lisa M. Regner Senior Project Manager Branch 4, Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission

Hearing Identifier: NRR_DMPS Email Number: 220 Mail Envelope Properties (SN6PR09MB27201C8E93CBAC59A7121796E5C60)

Subject:

Final Request for Additional Information - River Bend CBAC Request (L-2017-LLA-0291) Sent Date: 3/1/2018 10:00:31 AM Received Date: 3/1/2018 10:00:36 AM From: Regner, Lisa Created By: Lisa.Regner@nrc.gov Recipients: "Regner, Lisa" <Lisa.Regner@nrc.gov> Tracking Status: None "Coates, Alyson" <alacey@entergy.com> Tracking Status: None "SCHENK, TIM" <tschenk@entergy.com>

Tracking Status: None Post Office: SN6PR09MB2720.namprd09.prod.outlook.com

Files Size Date & Time MESSAGE 1816 3/1/2018 10:00:36 AM

Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: