Line 2: |
Line 2: |
| | number = ML20147E363 | | | number = ML20147E363 |
| | issue date = 12/13/1978 | | | issue date = 12/13/1978 |
| | title = Review of Combustion Engr Topical Rept#CENPD-169-P COLSS- Assessment of the Accuracy of PWR Oper Limits as Determined by the Core Oper Limit Supervisory Sys. Finds Rept Is Acceptable Reference for Methodology | | | title = Review of Combustion Engr Topical Rept CENPD-169-P COLSS- Assessment of the Accuracy of PWR Oper Limits as Determined by the Core Oper Limit Supervisory Sys. Finds Rept Is Acceptable Reference for Methodology |
| | author name = | | | author name = |
| | author affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR) | | | author affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR) |
Review of Combustion Engr Topical Rept CENPD-169-P COLSS- Assessment of the Accuracy of PWR Oper Limits as Determined by the Core Oper Limit Supervisory Sys. Finds Rept Is Acceptable Reference for MethodologyML20147E363 |
Person / Time |
---|
Issue date: |
12/13/1978 |
---|
From: |
Office of Nuclear Reactor Regulation |
---|
To: |
|
---|
Shared Package |
---|
ML20147E348 |
List: |
---|
References |
---|
NUDOCS 7812210051 |
Download: ML20147E363 (4) |
|
|
---|
Category:TEXT-SAFETY REPORT
MONTHYEARML20216G0111999-09-30030 September 1999 Year 2000 Readiness in U.S. Nuclear Power Plants ML20206N2191999-04-30030 April 1999 Operator Licensing Examination Standards for Power Reactors ML20205A5291999-03-31031 March 1999 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,October-December 1998.(White Book) ML20211K2851999-03-31031 March 1999 Standard Review Plan on Power Reactor Licensee Financial Qualifications and Decommissioning Funding Assurance ML20205A5991999-03-31031 March 1999 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,July-September 1998.(White Book) ML17313A7791999-02-0505 February 1999 Safety Evaluation Accepting Licensee Rev to Emergency Plan That Would Result in Two Less Radiation Protection Positions Immediatelu Available During Emergencies ML20203D0541999-01-31031 January 1999 Fire Barrier Penetration Seals in Nuclear Power Plants ML20155A9281998-10-31031 October 1998 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,April-June 1998.(White Book) ML20154C2081998-09-30030 September 1998 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,January-March 1998.(White Book) ML15261A4681998-09-0404 September 1998 Safety Evaluation Supporting Amends 232,232 & 231 to Licenses DPR-38,DPR-47 & DPR-55,respectively ML20203A1521998-07-31031 July 1998 Assessment of the Use of Potassium Iodide (Ki) as a Public Protective Action During Severe Reactor Accidents.Draft Report for Comment ML20153D3371998-07-31031 July 1998 Assessment of the Use of Potassium Iodide (Ki) as a Public Protective Action During Severe Reactor Accidents.Draft Report for Comment ML20236S9771998-06-30030 June 1998 Knowledge and Abilities Catalog for Nuclear Power Plant Operators.Pressurized Water Reactors ML20236S9681998-06-30030 June 1998 Evaluation of AP600 Containment THERMAL-HYDRAULIC Performance ML20236S9591998-06-30030 June 1998 Knowledge and Abilities Catalog for Nuclear Power Plant Operators.Boiling Water Reactors ML20217Q7971998-05-0404 May 1998 Safety Evaluation Supporting Amends 227 & 201 to Licenses DPR-53 & DPR-69,respectively ML20247E3951998-04-30030 April 1998 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,October-December 1997.(White Book) ML20217F3801998-03-31031 March 1998 Risk Assessment of Severe ACCIDENT-INDUCED Steam Generator Tube Rupture ML20202J3051997-11-30030 November 1997 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,July-September 1997.(White Book) ML20197B0431997-11-30030 November 1997 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,April-June 1997.(White Book) ML20211L2931997-09-30030 September 1997 Aging Management of Nuclear Power Plant Containments for License Renewal ML20210K7801997-08-31031 August 1997 Topical Report Review Status ML20149G9431997-07-31031 July 1997 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,January-March 1997.(White Book) ML20140J4301997-05-31031 May 1997 Safety Evaluation Report Related to the Department of Energy'S Proposal for the Irradiation of Lead Test Assemblies Containing TRITIUM-PRODUCING Burnable Absorber Rods in Commercial LIGHT-WATER Reactors ML20210R2131997-05-31031 May 1997 Final Safety Evaluation Report Related to the Certification of the System 80+ Design.Docket No. 52-002.(Asea Brown Boveri-Combustion Engineering) ML20140F0801997-05-31031 May 1997 Final Safety Evaluation Report Related to the Certification of the Advanced Boiling Water Reactor Design.Supplement No. 1.Docket No. 52-001.(General Electric Nuclear Energy) ML20141J9391997-04-30030 April 1997 Safety Evaluation Report Related to the Renewal of the Operating License for the Research Reactor at North Carolina State University ML20141C2411997-04-30030 April 1997 Circumferential Cracking of Steam Generator Tubes ML20141A5791997-04-30030 April 1997 Proposed Regulatory Guidance Related to Implementation of 10 CFR 50.59 (Changes, Tests, or Experiments).Draft Report for Comment ML20137A2191997-03-31031 March 1997 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,October-December 1996.(White Book) ML20135D5711997-01-31031 January 1997 Operator Licensing Examination Standards for Power Reactors ML20134L3631997-01-31031 January 1997 Standard Review Plan on Power Reactor Licensee Financial Qualifications and Decommissioning Funding Assurance.Draft Report for Comment ML20134L3601997-01-31031 January 1997 Standard Review Plan on Antitrust.Draft Report for Comment ML20138J2461997-01-31031 January 1997 Licensee Contractor and Vendor Inspection Status Report. Quarterly Report,July-September 1996.(White Book) ML20133E9161996-12-31031 December 1996 License Renewal Demonstration Program: NRC Observations and Lessons Learned ML20149L8261996-10-31031 October 1996 Reactor Pressure Vessel Status Report ML20135A4981996-10-31031 October 1996 Historical Data Summary of the Systematic Assessment of Licensee Performance ML20128P4381996-10-0909 October 1996 Safety Evaluation Accepting Review of Cracked Weld Operability Calculations & Staff Response to NRC Task Interference Agreement ML20107F5611996-04-17017 April 1996 Safety Evaluation Providing Guidance on Submitting plant- Specific Info W/Respect to IST Program Alternatives Request ML14183A6951995-09-18018 September 1995 Safety Evaluation Approving Relocation of Technical Support Ctr ML20236L5971994-12-29029 December 1994 SER in Response to 940314 TIA 94-012 Requesting NRR Staff to Determine Specific Mod to Keowee Emergency Power Supply Logic Must Be Reviewed by Staff Prior to Implementation of Mod ML20128Q0761994-11-0404 November 1994 Coordinating Group Evaluation,Conclusions & Recommendations ML20149H0671994-11-0404 November 1994 Safety Evaluation Supporting Amend 27 to Amended License R-103 ML20149G4281994-09-28028 September 1994 NRC Perspectives on Accident Mgt, Presented at 940928 Severe Accident Mgt Implementation Workshop in Alexandria, VA ML20149F7581994-08-25025 August 1994 Topical Rept Evaluation of WCAP-13864,Rev 1, Rod Control Sys Evaluation Program ML20149F4151994-08-0404 August 1994 Safety Evaluation Concluding That Unit 1 Can Be Safely Operated During Next Operating Cycle (Cycle 14) ML20149E8831994-08-0202 August 1994 Safety Evaluation Accepting Interim Relief Request IRR-03 Re Drywell Isolation Check Valves in Equipment Drain Lines & Reactor Equipment Closed Cooling Water Sys ML20248C5731994-07-19019 July 1994 SER Step 1 Review of Individual Plant Exam of External Fire Events for Millstone Unit 3 ML20059J4591994-01-25025 January 1994 Safety Evaluation Supporting Request for Relief from ASME Code Re Inservice Testing Requirements to Measure Vibration Amplitude Displacement ML20059H4991994-01-24024 January 1994 Safety Evaluation Accepting Revised Responses to IEB-80-04 Re MSLB Reanalysis 1999-09-30
[Table view]Some use of "" in your query was not closed by a matching "". Category:TOPICAL REPORT EVALUATION
MONTHYEARML20149F7581994-08-25025 August 1994 Topical Rept Evaluation of WCAP-13864,Rev 1, Rod Control Sys Evaluation Program ML20059L1061994-01-12012 January 1994 Draft Topical Rept Evaluation of B&Wog Rept 47-1223141-00, Integrated Plant Assessment Sys/Structure Screening.... Applicant for License Renewal That Refs B&Wog Sys Screening Methodology Will Be Required to Develop Own Procedures ML20059D1911993-12-30030 December 1993 Topical Rept Evaluation of RXE-91-005, Methodology for Reactor Core Response to Steamline Break Events ML20058P2181993-12-10010 December 1993 SER Accepting Siemens Nuclear Power Corp Submittal of Topical Rept EMF-92-081, Statistical Setpoint/Transient Methodology for W Type Reactors ML20058H9851993-11-26026 November 1993 Topical Rept Evaluation of WCAP-10216-P, Relaxation of Constant Axial Offset Control. Rept Acceptable ML20059H8481993-11-0202 November 1993 SER Accepting Proposed Changes in Rev 3 to OPPD-NA-8302-P, OPPD Nuclear Analysis,Reload Core Analysis Methodology, Neutronics Design Methods & Verification ML20134B4761993-10-30030 October 1993 Topical Rept Evaluation of Rev 3 to NP-2511-CCM Re VIPRE-01 Mod 2 for PWR & BWR Applications ML20058M9851993-09-30030 September 1993 SE of Topical Rept, Transient Analysis Methodology for Wolf Creek Generating Station ML20056G4171993-08-18018 August 1993 Topical Rept Evaluation of Rev 4 to OPPD-NA-8303, Transient & Accident Methods & Verification. Proposed Changes in Rev 4 Acceptable Except for Use of Cents Computer Code for Transient Analyses ML20056E9661993-08-0606 August 1993 Sser Re Topical Rept HGN-112-NP, Generic Hydrogen Control Info for BWR/6 Mark III Containment Hydrogen Control ML20056E4681993-08-0505 August 1993 Supplemental Safety Evaluation for Topical Rept HGN-112-NP, Generic Hydrogen Control Info for BWR/6 Mark III Containments. Change Requests Consistent & Compatible W/ 10CF50.44 & Acceptable ML20056E3961993-08-0505 August 1993 Safety Evaluation of RXE-90-006-P, Power Distribution Control Analysis & Overtemperature N-16 & Overpower N-16 Trip Setpoint Methodology. Methodology Acceptable ML20056E3811993-08-0505 August 1993 Safety Evaluation of RXE-89-002, Vipre-01 Core Thermal- Hydraulic Analysis Methods for Comanche Peak Steam Electric Station Licensing Applications. Rept Is Acceptable for Ref in CPSES Core thermal-hydraulic Analyses ML20056E2571993-08-0505 August 1993 Corrected Safety Evaluation for Topical Rept RXE-91-001, Transient Analysis Methods for Commanche Peak Steam Electric Station Licensing Applications. Corrections Made to Second Sentense of Second Full Paragraph on Page Two ML20056D9921993-07-29029 July 1993 Topical Rept Evaluation of OPPD-NA-8301,Rev 5, Reload Core Analysis Methodology Overview. Proposed Changes in Rev 5 Acceptable ML20057A2661993-07-14014 July 1993 Topical Safety Evaluation of CEN-387-P, Pressurizer Surge Line Flow Stratification Evaluation. C-E Owners Group Analysis May Be Used as Basis for Licensees to Update plant- Specific Code Stress Rept for Compliance W/Bulletin 88-011 ML20056E1261993-06-29029 June 1993 Safety Evaluation of CENPD-382-P, Methodology for Core Designs Containing Erbium Burnable Absorbers. Rept Acceptable for Reload Licensing Applications of Both CE CE 14x14 & 16x16 PWR Lattice Type Core Designs ML20057B5431993-06-26026 June 1993 Errata for Sser Re Topical Rept HGN-112-NP, Generic Hydrogen Control Info for BWR/6 Mark III Containments, for Use in Issuance of Final Approved Version of Topical Rept ML20128B8101993-01-19019 January 1993 Safety Evaluation Accepting Methodology Described in Topical Rept RXE-91-002 Reactivity Anomaly Events Methodology for Reload Licensing Analyses for CPSES ML20126E0381992-12-0909 December 1992 Safety Evaluation Accepting Topical Rept NEDC-31753P W/Ter Recommendations W/Listed Exceptions ML20056D9351991-01-11011 January 1991 Topical Rept Evaluation Accepting Proposed Methodology for Fuel Channel Bowing Anaylses & for Referencing in Reload Licensing Applications W/Listed Conditions ML20235Q7121989-02-22022 February 1989 Safety Evaluation Re Review of WCAP-10271,Suppl 2 & WCAP-10271,Suppl 2,Rev 1 on Evaluation of Surveillance Frequencies & out-of-svc Times for ESFAS ML20206L9611988-11-23023 November 1988 Topical Rept Evaluation of PECO-FMS-0004, Methods for Performing BWR Sys Transient Analysis. Rept Approved,But Limited to Util Competence to Use Retran Computer Code for Facility ML20205M0091988-10-25025 October 1988 Safety Evaluation of Topical Rept YAEC-1300P, RELAP5YA: Computer Program for LWR Sys Thermal-Hydraulic Analysis. Program Acceptable as Licensing Method for Small Break LOCA Analysis Under Conditions Stipulated ML20204G8371988-10-18018 October 1988 Safety Evaluation Accepting Topical Rept 151, Haddem Neck Plant Non-LOCA Transient Analysis, Except for Issue of Feedwater Event ML20155G7991988-10-12012 October 1988 Topical Rept Evaluation of TR-045, BWR-2 Transient Analysis Using Retran Code. Methods Described in Rept Acceptable for Reload Analysis When Listed Conditions Satisfied ML20155G3201988-09-26026 September 1988 Safety Evaluation of TS NEDC-30936P, BWR Owners Group TSs Improvement Methodology. GE Analyses Demonstrated Acceptability of General Methodology for Considering TS Changes to ECCS Instrumentation Used in BWR Facilities ML20155B0501988-09-22022 September 1988 Topical Rept Evaluation of Suppl 1 to NEDC-30851P, Tech Spec Improvement Analysis for BWR Control Rod Block Instrumentation. Analyses Acceptable to Support Proposed Extensions to 3 Months ML20151K9921988-07-26026 July 1988 Topical Rept Evaluation of Nusco 140-1 Northeast Utils Thermal Hydraulic Model Qualification,Vol 1 (Retran). Rept May Be Generally Ref in Future Licensing Submittals.Further Justification by Util Required ML20150D7671988-03-21021 March 1988 Topical Rept Evaluation of Rev 0 to TR-033, Methods for Generation of Core Genetics Data for RETRAN-02. Uncertainties in Input Parameters & Impact on Retran Results Should Be Determined for Qualification of Model ML20150D9651988-03-21021 March 1988 Topical Rept Evaluation of Rev 0 to TR-040, Steady State & Quasi-Steady State Methods for Analyzing Accidents & Transients. Util Methods Acceptable for Performing Reload Assembly Mislocation Analysis W/Listed Exceptions ML20236D2621987-10-21021 October 1987 Topical Rept Evaluation of CEN-348(B)-P, Extended Statistical Combination of Uncertainties. Rept Acceptable ML20235D7041987-09-22022 September 1987 Safety Evaluation of Rev 0 to Topical Rept TR-021, Methods for Analysis of BWRs Steady State Physics. Rept,Methodology & Util Use of Methodology Acceptable ML20239A5461987-09-0909 September 1987 Safety Evaluation Supporting A-85-11, Retran Computer Code Reactor Sys Transient Analysis Model Qualification for Use in Performing plant-specific best-estimate Transient Analyses at Plant ML20215M3591987-05-0606 May 1987 Safety Evaluation Supporting Util Use of Suppl 1 to MSS-NA1-P, Qualification of Reactor Physics Methods for Application to PWRs of Middle South Utils Sys ML20212M7781987-02-17017 February 1987 Topical Rept Evaluation of WCAP-10325, Westinghouse LOCA Mass & Energy Release Model for Containment Design - Mar 1979 Version. Rept Acceptable for Ref in Licensing Actions ML20210N7331987-02-0404 February 1987 Safety Evaluation Supporting CEN-161(B)-P,Suppl 1-P, Improvements to Fuel Evaluation Model. Mods to Fission Gas Release & Fuel Thermal Expansion Models Acceptable ML20215B2331986-12-0404 December 1986 Corrected Page 1 to 861031 Topical Rept Evaluation of Rev 2 to STD-R-05-011, Mobile In-Container Dewatering & Solidification Sys (Mdss). Word Effective Inserted Before Words Pore Sizes in First Line of 4th Paragraph ML20214C5221986-11-14014 November 1986 Topical Rept Evaluation of Rev 0 to TR 020, Methods for Analysis of BWR Lattice Physics. Collision Probability Module Code Acceptable for BWR Fuel Lattice Calculations ML20213F6531986-11-10010 November 1986 Safety Evaluation of Rev 2 to Vol 3 of XN-NF-80-19(P), Exxon Nuclear Methodology for Bwrs,Thermex:Thermal Limits Methodology Summary Description. Rept Acceptable for Ref in Licensing Applications ML20207A8281986-11-0505 November 1986 Suppl 3 to Topical Rept Evaluation Re Submittal 2 to Rev 3 to CEN-152, C-E Emergency Procedure Guidelines. Rept Acceptable for Ref ML20215N6901986-11-0404 November 1986 Topical Rept Evaluation of BAW-10155, FOAM2 - Computer Program to Calculate Core Swell Level & Mass Flow Rate During Small-Break Loca. Rept Acceptable W/Listed Restrictions Re Ranges of Core Flow Rate & Pressure ML20215N3921986-10-31031 October 1986 Topical Rept Evaluation of STD-R-05-011, Mobile In-Container Dewatering & Solidification Sys (Mdss). Rept Acceptable for Ref in License Applications ML20211D6921986-10-16016 October 1986 Safety Evaluation of Nusco 140-2, Nusco Thermal Hydraulic Model Qualification,Vol II (Vipre). Rept Acceptable for Establishing Input Values & Selection of Correlation Options & Solution Techniques for Calculations ML20206S6511986-09-15015 September 1986 Topical Rept Evaluation of Addenda 3 to WCAP-8720, Improved Analytical Models Used in Westinghouse Fuel Rod Design Computations/Application for BWR Fuel Analysis. Rept Acceptable for Ref in Licensing Applications ML20212N2001986-07-23023 July 1986 Topical Rept Evaluation of Rev 1 to XN-NF-85-67 (P), Generic Mechanical Design for Exxon Nuclear Jet Pump BWR Reload Fuel. Rept Acceptable as Ref for Application to Jet Pump BWR Reload Cores,W/Listed Conditions ML20211A0091986-05-27027 May 1986 Nonproprietary Sser of WCAP-8822(P) & WCAP-8860(NP), Mass & Energy Releases Following Steam Line Rupture ML20203F8021986-04-17017 April 1986 Topical Rept Evaluation of WCAP-8745, Design Bases for Thermal Overpower Delta T & Thermal Overtemp Delta T Trip Functions. Rept Acceptable Ref in Licensing Documents for Plants Operating Under Constant Axial Offset Control ML20137Z7111986-03-0505 March 1986 Topical Rept Evaluation of Rev 1 to NEDO-20566-2, GE Analytical Model for LOCA Analysis in Accordance W/10CFR50, App K,Amend 2,One .... Rept Acceptable for LOCA Evaluations During single-loop Operation ML20141E9601985-12-27027 December 1985 Topical Rept Evaluation of NEDE-30878, Transportable Modular Aztech Plant. Rept Acceptable for Referencing in License Applications 1994-08-25
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
-
.. . OEC 131973 REVIEW 0F TOPICAL REPORT CENPD-169-P Report
Title:
Assessment of the Accuracy of PWR Operating Limits as Determined by the Core Operating Limit Supervisory System (COLSS)
Report Number: CENPD-169-P (Proprietary)
Report Date: July 1975 Originating Organization: Combustion Engineering, Inc.
l Reviewed by: Core Performance Branch, DSS Summary of Topical Report The primary objective of CENPD-169-P is to present the methodology fnr ascertaining the uncertainty in the core power distribution determined by the Core Operating Limit Supervisory System (COLSS) synthesis pro-cedure. In addition, the report serves as a reference for the basic concepts employed to transform the signals from five-level incore detectors into forty-node representations of the radially averaged core axial power shape (CAPS). Also included is a description of the construction of the hot pin and hot channel power distributions using precalculated planar Radial Peaking Factors (RPF) and the CAPS.
The subject report should only be used as a generic reference for the synthesis and uncertrinty methodology, since implementation of the methodology and the precise values of the uncertainty factors are plant specific.
Summary of Regulatory Evaluation The following sections are intended to clarify the essential points pertiment
, to the evaluation of the CENPD-169-P methodology.
"I812210 @
_2 OEC 131978 Applicability of the Report The COLSS methodology described in the report will generically encompass CE plants of the Arkansas Nuclear One-Unit 2 and future designs. However, the precise value of the appropriate uncertainty factors depend on basic-ally three design parameters: the number and burnup of the fuel assemblies the Control Element Assembly '(CEA) programming, and the number of operable -
incore detectors. Thus the Linear Power Density (LPD) uncertainty will depend on the plant design.
Core Power Distribution The core axial power shape (CAP) is calculated from the integral responses of 5 levels of incore detector segments. A simple 5 element Fourier fit to the power distribution is employed. Sets of integral detector signal equations are solved for the combining coefficients and the core axial power distribution is constructed for 40 axial nodes. For each reactor empicying a COLSS, these coefficients are calculated with a reactor simulator model and are experimentally verified during startup testing.
The detailed radial power distribution is not measured in COLSS. Radial peaking factors calculated with a reactor simulator model (the simulator l model is a three dimensional nodal core physics model for the calculation l
of the core power distribution) are employed to construct the hot pin and hot channel power distribution. The radial peaking factors are functions
' of CEA configuration and are stored in the COLSS computer. Tests will be
. , DEC 13 'D performed during the reactor start-up program to verify that the pre-calculated values of radial peaking factors are appropriate for the as-built reactor. Updating of COLSS power distribution constants will be based on the results of the measurement of core power distributions by the INCA (ref. 1) program.
Uncertainty Analysis _
The technique described for determining the uncertainty in the COLSS calculated Fg combines the CAPS synthesis error with the INCA (ref.1) verified planar RPF uncertainty. To determine the CAPS uncertainty, the Fg 's for more than 4000 core configurations, including steady-state, transients, and non-normal CEA configurations, calculated by the reactor simulator and the COLSS procedures were compared. In these computations, the COLSS procedures employed the planar RPFs obtained from the simulator for each core configuration.
Thus, the differences in Fg reflect only CAPS synthesis errors. The uncertainty in the RPF's attributable to the accuracy of the INCA (refs. I and 2) system used to verify the RPF's is combined with the CAPS uncertainty to yield the total uncertainty value.
The increase in the uncertainty in the COLSS synthesized Fg as a function of inoperable incore detectors was evaluated. The calculations show that the error is small, even with a large number of inoperable detectors. This is because the axial distribution is obtained from the average of all operable detectors at a given axial level and therefore even a large number of inoperable detectors does not greatly affect the average values.
Orc 1 a 570 Regulatory Position Based on our review of the areas described above, we conclude that the subject report is an acceptable reference for the general methodology of COLSS to determine core power distributions from incore detectors.
In addition, the procedure described for calculating the overall uncertainty in Fg including uncertainties in the COLSS synthesis pro- _
cedure is satisfactory. The values for uncertainties used in references 1 and 2 are intentionally excluded from this review, since review of those documents has not been completed.
REFERENCES
- 1. CENPD-145 INCA - Method cf Analyzing In-Core Detector Data, April 1975,
- 2. CENPD-153 Evaluation of Uncertainty in Fg Measured by Self-Powered Fixed In-Core Detector Systems, August 1974.