Line 3: Line 3:
| issue date = 08/19/2010
| issue date = 08/19/2010
| title = Operator Licensing Written Examination Approval 05000390-10-301
| title = Operator Licensing Written Examination Approval 05000390-10-301
| author name = Widmann M T
| author name = Widmann M
| author affiliation = NRC/RGN-II/DRS/OLB
| author affiliation = NRC/RGN-II/DRS/OLB
| addressee name = Thompson W
| addressee name = Thompson W
Line 14: Line 14:
| page count = 2
| page count = 2
}}
}}
See also: [[followed by::IR 05000390/2010301]]
See also: [[see also::IR 05000390/2010301]]


=Text=
=Text=

Revision as of 04:59, 11 July 2019

Operator Licensing Written Examination Approval 05000390-10-301
ML102310187
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 08/19/2010
From: Widmann M
NRC/RGN-II/DRS/OLB
To: Thompson W
Tennessee Valley Authority
References
ER-10-301
Download: ML102310187 (2)


See also: IR 05000390/2010301

Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257

August 19, 2010

Tennessee Valley Authority ATTN: Mr. William Thompson

Training Manager Watts Bar Nuclear Plant P. O. Box 2000 Spring City, TN 37381

SUBJECT: WATTS BAR NUCLEAR POWER PLANT - OPERATOR LICENSING WRITTEN EXAMINATION APPROVAL 05000390/2010301

Dear Mr. Thompson:

The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing written examination at Watts Bar Nuclear Power Plant.

The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to your office. The NRC staff will begin administering the operating tests to individuals, as applicable, during the weeks of August 23, 2010 and August 30, 2010. Note that any examination

waivers and application denials have been addressed in separate correspondence.

The NRC has approved the subject written examination and hereby authorizes you to administer the written examination in accordance with Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," on September 8, 2010.

This examination has undergone extensive review by my staff and representatives responsible for operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the

qualifications of licensed operators at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (404) 997-4550.

Please contact the Chief Examiner, Mr. Gerard Laska, at (404) 997-4626 if you have any questions or identify any errors or changes in license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant on the list of approved applicants.

Sincerely, /RA/

Malcolm T. Widmann, Chief Operations Branch Division of Reactor Safety

Docket No.: 50-390

License No.: NPF-90

Tennessee Valley Authority ATTN: Mr. William Thompson

Training Manager Watts Bar Nuclear Plant P. O. Box 2000 Spring City, TN 37381

SUBJECT: WATTS BAR NUCLEAR POWER PLANT - OPERATOR LICENSING WRITTEN EXAMINATION APPROVAL 05000390/2010301

Dear Mr. Thompson:

The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing written examination at Watts Bar Nuclear Power Plant.

The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to your office. The NRC staff will begin administering the operating tests to individuals, as applicable, during the weeks of August 23, 2010 and August 30, 2010. Note that any examination

waivers and application denials have been addressed in separate correspondence.

The NRC has approved the subject written examination and hereby authorizes you to administer the written examination in accordance with Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," on September 8, 2010.

This examination has undergone extensive review by my staff and representatives responsible for operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the

qualifications of licensed operators at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at (404) 997-4550.

Please contact the Chief Examiner, Mr. Gerard Laska, at (404) 997-4626 if you have any questions or

identify any errors or changes in license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant on the list of approved applicants.

Sincerely, /RA/

Malcolm T. Widmann, Chief Operations Branch Division of Reactor Safety

Docket No.: 50-390

License No.: NPF-90

X PUBLICLY AVAILABLE

G NON-PUBLICLY AVAILABLE

G SENSITIVE X NON-SENSITIVE ADAMS: Yes ACCESSION NUMBER: ML X SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS SIGNATURE GWL MTW NAME GLASKA MWIDMANN DATE 8/19/10 8/19/10 8/ /2010 8/ /2010 8/ /2010 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO