{{#Wiki_filter:From: | {{#Wiki_filter:From: Siva Lingam Sent: Thursday, July 20, 2023 4:09 PM To: Matthew.Cox@aps.com Cc: Jennifer Dixon-Herrity; Brian Wittick; Phillip Sahd; Vic Cusumano; Derek Scully; David Nold; Jo Ambrosini (She/Her); Ahsan Sallman; Matthew Hamm; Carl.Stephenson@aps.com | ||
==Subject:== | ==Subject:== | ||
Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - | Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - | ||
Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098) | Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098) | ||
By {{letter dated|date=June 29, 2023|text=letter dated June 29, 2023}} (Agencywide Documents Access and Management System Accession No. ML23180A222), Arizona Public Service Company submitted a license amendment request (LAR) for U.S Nuclear Regulatory Commission (NRC) approval for Palo Verde Nuclear Generating Station, Units 1, 2, and 3, by requesting the following changes: | By {{letter dated|date=June 29, 2023|text=letter dated June 29, 2023}} (Agencywide Documents Access and Management System Accession No. ML23180A222), Arizona Public Service Company submitted a license amendment request (LAR) for U.S Nuclear Regulatory Commission (NRC) approval for Palo Verde Nuclear Generating Station, Units 1, 2, and 3, by requesting the following changes: | ||
* Surveillance Requirement (SR) 3.5.1.2 for Technical Specification (TS) 3.5.1, Safety Injection Tanks (SITs) - Operating, | * Surveillance Requirement (SR) 3.5.1.2 for Technical Specification (TS) 3.5.1, Safety Injection Tanks (SITs) - Operating, | ||
Line 28: | Line 29: | ||
* Limiting Condition for Operation (LCO) for TS 3.5.2, and | * Limiting Condition for Operation (LCO) for TS 3.5.2, and | ||
* LCO for TS 3.6.5, Containment Air Temperature. | * LCO for TS 3.6.5, Containment Air Temperature. | ||
The purpose of this e-mail is to provide the results of the NRC staffs acceptance review for the LAR. The acceptance review was performed to determine if there is | |||
The purpose of this e-mail is to provide the results of the NRC staffs acceptance review for the LAR. The acceptance review was performed to determine if there is suffici ent technical information in scope and depth to allow the NRC staff to complete its detailed technical review. | |||
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | ||
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment. | The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment. | ||
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any | Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any f urther information needed to support the NRC staffs detailed technical review by separate correspondence. | ||
Based on the information provided in your submittal, the NRC staff has estimated that this LAR will take approximately 370 hours to complete. The | |||
Based on the information provided in your submittal, the NRC staff has estimated that this LAR will take approximately 370 hours to complete. The NR C staff expects to complete the review of this LAR by June 29, 2024, or earlier. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, or unanticipated addition of scope to the review. | |||
If you have any questions, please contact me at (301) 415-1564. | If you have any questions, please contact me at (301) 415-1564. | ||
Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Grand Gulf Nuclear Station Entergy Fleet Location: O-9E22; Mail Stop: O-9E03 Telephone: 301-415-1564 E-mail address: Siva.Lingam@nrc.gov | Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Grand Gulf Nuclear Station Entergy Fleet Location: O-9E22; Mail Stop: O-9E03 Telephone: 301-415-1564 E-mail address: Siva.Lingam@nrc.gov | ||
Hearing Identifier: | Hearing Identifier: NRR_DRMA Email Number: 2174 | ||
Mail Envelope Properties (SJ0PR09MB6109A1B62CACEFDC6A9BB029F63EA) | |||
==Subject:== | ==Subject:== | ||
Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - | Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - | ||
Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098) | Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098) | ||
Sent Date: | Sent Date: 7/20/2023 4:09:24 PM Received Date: 7/20/2023 4:09:00 PM From: Siva Lingam | ||
Created By: Siva.Lingam@nrc.gov | |||
Recipients: | |||
"Jennifer Dixon-Herrity" <Jennifer.Dixon-Herrity@nrc.gov> | "Jennifer Dixon-Herrity" <Jennifer.Dixon-Herrity@nrc.gov> | ||
Tracking Status: None "Brian Wittick" <Brian.Wittick@nrc.gov> | Tracking Status: None "Brian Wittick" <Brian.Wittick@nrc.gov> | ||
Line 54: | Line 65: | ||
Tracking Status: None "Carl.Stephenson@aps.com" <Carl.Stephenson@aps.com> | Tracking Status: None "Carl.Stephenson@aps.com" <Carl.Stephenson@aps.com> | ||
Tracking Status: None "Matthew.Cox@aps.com" <Matthew.Cox@aps.com> | Tracking Status: None "Matthew.Cox@aps.com" <Matthew.Cox@aps.com> | ||
Tracking Status: None Post Office: | Tracking Status: None | ||
Post Office: SJ0PR09MB6109.namprd09.prod.outlook.com | |||
Files Size Date & Time MESSAGE 3122 7/20/2023 4:09:00 PM | |||
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:}} |
Latest revision as of 18:26, 13 November 2024
ML23202A016 | |
Person / Time | |
---|---|
Site: | Palo Verde |
Issue date: | 07/20/2023 |
From: | Siva Lingam NRC/NRR/DORL/LPL4 |
To: | Cox M Arizona Public Service Co |
References | |
L-2023-LLA-0098 | |
Download: ML23202A016 (3) | |
Text
From: Siva Lingam Sent: Thursday, July 20, 2023 4:09 PM To: Matthew.Cox@aps.com Cc: Jennifer Dixon-Herrity; Brian Wittick; Phillip Sahd; Vic Cusumano; Derek Scully; David Nold; Jo Ambrosini (She/Her); Ahsan Sallman; Matthew Hamm; Carl.Stephenson@aps.com
Subject:
Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs -
Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098)
By letter dated June 29, 2023 (Agencywide Documents Access and Management System Accession No. ML23180A222), Arizona Public Service Company submitted a license amendment request (LAR) for U.S Nuclear Regulatory Commission (NRC) approval for Palo Verde Nuclear Generating Station, Units 1, 2, and 3, by requesting the following changes:
- Surveillance Requirement (SR) 3.5.1.2 for Technical Specification (TS) 3.5.1, Safety Injection Tanks (SITs) - Operating,
- SR 3.5.2.2 for TS 3.5.2, Safety Injection Tanks (SITs) - Shutdown,
- Limiting Condition for Operation (LCO) for TS 3.5.2, and
- LCO for TS 3.6.5, Containment Air Temperature.
The purpose of this e-mail is to provide the results of the NRC staffs acceptance review for the LAR. The acceptance review was performed to determine if there is suffici ent technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed LAR in terms of regulatory requirements and the protection of public health and safety and the environment.
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any f urther information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this LAR will take approximately 370 hours0.00428 days <br />0.103 hours <br />6.117725e-4 weeks <br />1.40785e-4 months <br /> to complete. The NR C staff expects to complete the review of this LAR by June 29, 2024, or earlier. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager. These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, or unanticipated addition of scope to the review.
If you have any questions, please contact me at (301) 415-1564.
Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Grand Gulf Nuclear Station Entergy Fleet Location: O-9E22; Mail Stop: O-9E03 Telephone: 301-415-1564 E-mail address: Siva.Lingam@nrc.gov
Hearing Identifier: NRR_DRMA Email Number: 2174
Mail Envelope Properties (SJ0PR09MB6109A1B62CACEFDC6A9BB029F63EA)
Subject:
Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs -
Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating (EPID L-2023-LLA-0098)
Sent Date: 7/20/2023 4:09:24 PM Received Date: 7/20/2023 4:09:00 PM From: Siva Lingam
Created By: Siva.Lingam@nrc.gov
Recipients:
"Jennifer Dixon-Herrity" <Jennifer.Dixon-Herrity@nrc.gov>
Tracking Status: None "Brian Wittick" <Brian.Wittick@nrc.gov>
Tracking Status: None "Phillip Sahd" <Phillip.Sahd@nrc.gov>
Tracking Status: None "Vic Cusumano" <Victor.Cusumano@nrc.gov>
Tracking Status: None "Derek Scully" <Derek.Scully@nrc.gov>
Tracking Status: None "David Nold" <David.Nold@nrc.gov>
Tracking Status: None "Jo Ambrosini (She/Her)" <Josephine.Ambrosini@nrc.gov>
Tracking Status: None "Ahsan Sallman" <Ahsan.Sallman@nrc.gov>
Tracking Status: None "Matthew Hamm" <Matthew.Hamm@nrc.gov>
Tracking Status: None "Carl.Stephenson@aps.com" <Carl.Stephenson@aps.com>
Tracking Status: None "Matthew.Cox@aps.com" <Matthew.Cox@aps.com>
Tracking Status: None
Post Office: SJ0PR09MB6109.namprd09.prod.outlook.com
Files Size Date & Time MESSAGE 3122 7/20/2023 4:09:00 PM
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: