ML110200355: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 | {{#Wiki_filter:UNITED STATES | ||
NUCLEAR REGULATORY COMMISSION | |||
REGION III | |||
Mr. Jack M. Davis Senior Vice President and | 2443 WARRENVILLE ROAD, SUITE 210 | ||
postulated events that could potentially cause loss of large areas of power reactor facilities due to explosions or fires. | LISLE, IL 60532-4352 | ||
inspection starting on March 23, 2011. The schedule for the on-site inspection activity is as follows: | January 20, 2011 | ||
protection programs, fire protection features, post-fire safe shutdown capabilities, and plant layout; and (3) to arrange administrative details, such as office space, availability of knowledgeable office personnel and to ensure unescorted site access privileges. | Mr. Jack M. Davis | ||
Senior Vice President and | |||
Chief Nuclear Officer | |||
Detroit Edison Company | |||
Fermi 2 - 210 NOC | |||
6400 North Dixie Highway | |||
Newport, MI 48166 | |||
SUBJECT: FERMI POWER PLANT, UNIT 2 - NOTIFICATION TO PERFORM A TRIENNIAL | |||
FIRE PROTECTION BASELINE INSPECTION; INSPECTION REPORT | |||
05000341/2011-009(DRS) | |||
Dear Mr. Davis | |||
On March 23, 2011, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial fire | |||
protection baseline inspection at your Fermi Power Plant, Unit 2. This inspection will be | |||
performed in accordance with Inspection Procedure (IP) 71111.05T, the NRCs baseline fire | |||
protection inspection procedure. | |||
Based on the latest revision to IP 71111.05T, dated September 30, 2010, changes were made | |||
to the IP which now requires the fire protection inspection to review your actions to mitigate | |||
postulated events that could potentially cause loss of large areas of power reactor facilities due | |||
to explosions or fires. This requirement was implemented by the issuance of the Interim | |||
Compensatory Measures Order EA-02-026, Section B.5.b and the subsequent requirements of | |||
10 CFR 50.54(hh)(2), which are collectively referred to as B.5.b requirements. During this | |||
inspection, the B.5.b requirements review will be performed during the first on-site week of the | |||
inspection starting on March 23, 2011. | |||
The schedule for the on-site inspection activity is as follows: | |||
y Information Gathering Visit: March 21 - 23, 2011 | |||
y B.5.b Requirements: March 23 - 25, 2011; and | |||
y Fire Protection Inspection: April 11 - 15, 2011 and April 25 - 29, 2011 | |||
The purpose of the information gathering visit is: (1) to obtain information and documentation | |||
needed to support the inspection; (2) to become familiar with the Fermi Power Plant fire | |||
protection programs, fire protection features, post-fire safe shutdown capabilities, and plant | |||
layout; and (3) to arrange administrative details, such as office space, availability of | |||
knowledgeable office personnel and to ensure unescorted site access privileges. | |||
J. Davis -2- | |||
Experience has shown that the baseline fire protection inspections are extremely resource | |||
intensive both for the NRC inspectors and the licensee staff. In order to minimize the inspection | |||
impact on the site and to ensure a productive inspection for both organizations, we have | |||
enclosed a request for documents needed for the inspection. These documents have been | |||
divided into four groups. The first group lists information necessary to aid the inspection team in | |||
choosing specific focus areas for the inspection. It is requested that this information be | |||
provided to the lead inspector via mail or electronically no later than March 7, 2011. The | |||
second group also lists information and areas for discussion necessary to aid the inspection | |||
team in choosing specific fire protection focus areas for the inspection and to ensure that the | |||
inspection team is adequately prepared for the inspection. It is requested this information be | |||
available during the information gathering visit (March 21, 2011). The third group of requested | |||
documents consists of those items that the team will review, or need access to, during the | |||
inspection. Please have this information available by the first day of the second on-site | |||
inspection week (April 11, 2011). The fourth group lists the information necessary to aid the | |||
inspection team in tracking issues identified as a result of the inspection. It is requested that | |||
this information be provided to the lead inspector as the information is generated during the | |||
inspection. It is important that all of these documents are up to date and complete in order | |||
to minimize the number of additional documents requested during the preparation and/or the | |||
on-site portions of the inspection. | |||
The lead inspector for this inspection is Mr. R. Langstaff. We understand that our regulatory | |||
contact for this inspection is Mr. R. Salmon of your organization. If there are any questions | |||
about the inspection or the material requested, please contact the lead inspector at (630) 829- | |||
9747 or via e-mail at Ronald.Langstaff@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject to | |||
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection | |||
requirements were approved by the Office of Management and Budget, Control Number | |||
3150-0011. | |||
The NRC may not conduct or sponsor, and a person is not required to respond to a request for | |||
information or an information collection requirement unless the requesting document displays a | |||
currently valid Office of Management and Budget control number. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and | |||
its enclosure will be available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of NRC's document | |||
J. Davis -3- | |||
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA by R. A. Langstaff for/ | |||
Robert C. Daley, Chief | |||
Engineering Branch 3 | |||
Division of Reactor Safety | |||
Docket Nos. 50-341 | |||
License Nos. NPF-43 | |||
Enclosure: Fire Protection Inspection Document Request | |||
cc w/encl: Distribution via ListServ | |||
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS | |||
Inspection Report: 05000341/2011-009(DRS) | |||
On-site Inspection Dates: March 21 - 23, 2011 (Information Gathering Visit) | |||
March 23 - 25, 2011 (B.5.b Requirements) | |||
April 11 - 15, 2011 (Fire Protection Inspection) | |||
April 25 - 29, 2011 (Fire Protection Inspection) | |||
Inspection Procedures: IP71111.05T, Fire Protection (Triennial) | |||
IP71152, "Identification and Resolution of Problems" | |||
Inspectors: R. A. Langstaff, Senior Reactor Inspector | |||
(630) 829-9747 | |||
Ronald.Langstaff@nrc.gov | |||
G. M. Hausman, Senior Reactor Inspector | |||
(630) 829-9743 | |||
SERs | George.Hausman@nrc.gov | ||
D. Szwarc, Reactor Inspector | |||
(630) 829-9803 | |||
Dariusz.Szwarc@nrc.gov | |||
Observer: N. A. Valos | |||
(630) 829-9761 | |||
Nicholas.Valos@nrc.gov | |||
J. S. Bowen | |||
(301) 415-3471 | |||
Jeremy.Bowen@nrc.gov | |||
I. Information Requested Prior To the Information Gathering Visit | |||
The following information is requested by March 7, 2011. If you have any questions | |||
regarding this request, please call the lead inspector as soon as possible. All information | |||
should be sent to R.A. Langstaff (e-mail address Ronald.Langstaff@nrc.gov). Electronic | |||
media is preferred. The preferred file format is a searchable pdf file on a compact | |||
disk (CD). The CD should be indexed and hyper-linked to facilitate ease of use, if possible. | |||
Please provide four copies of each CD submitted (one for each inspector). | |||
1. The most risk-significant fire areas as determined by probabilistic risk analyses, if | |||
available. Otherwise, the reactor plant's Individual Plant Examination for External | |||
Events (IPEEE) for fire and results of any post-IPEEE reviews for fire. | |||
1 Enclosure | |||
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS | |||
2. A copy of the current version of the fire protection program (FPP), fire hazards analysis | |||
(FHA), safe shutdown analysis (SSA), updated safety analysis report (USAR), Technical | |||
Specifications and license. | |||
3. A list of fire areas requiring alternative shutdown capability, (i.e., those areas for which | |||
10 CFR Part 50, Appendix R, Section III G requirements are satisfied under | |||
Section III.G.3), or where both safe shutdown trains can be affected. | |||
4. Plant operating procedures which would be used and describe shutdown for a | |||
postulated fire (for both areas requiring alternative shutdown and areas which do not | |||
require alternative shutdown). Only those procedures with actions specific to shutdown | |||
in the event of a fire need be included. | |||
II. Information Requested During the Information Gathering Visit (MARCH 21, 2011) | |||
The following information is requested to be provided to the inspection team during the | |||
on-site information gathering visit. Except for Item 8, it is requested that the following | |||
information be provided on three sets of CDs (searchable, if possible) with the B.5.b | |||
Mitigating Strategies information (Items 8.a through 8.h) provided on one separate CD. In | |||
addition, one set of hard copy drawings are requested for Items 4.a. through 4.e. | |||
1. One set of hard-copy documents for facility layout drawings, which identify plant fire area | |||
delineation; areas protected by automatic fire suppression and detection; and locations | |||
of fire protection equipment. | |||
2. Licensing Information: | |||
a. The facilitys license, including the fire protection license condition; | |||
b. All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs) | |||
applicable to fire protection (specifically including those SERs referenced by | |||
the plant fire protection license condition) and all licensing correspondence | |||
referenced by the SERs; | |||
c. All licensing correspondence associated with the comparison to Standard Review | |||
Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes; | |||
d. Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and associated | |||
licensing correspondence; | |||
e. For pre-1979 plants, all licensing correspondence associated with those | |||
sections of 10 CFR Part 50, Appendix R, that are not applicable to the plant under | |||
10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with | |||
those fire protection features proposed or implemented by the licensee that have | |||
been accepted by the NRC staff as satisfying the provisions of Appendix A to | |||
Branch Technical Position (BTP) APCSB 9.5-1 reflected in the NRC fire protection | |||
SERs issued before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire | |||
protection features, which were accepted by the NRC staff in comprehensive fire | |||
protection SERs issued before Appendix A to BTP APCSB 9.5-1 was published in | |||
August 1976 (10 CFR 50.48(b)(1)(ii)); and | |||
2 Enclosure | |||
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS | |||
f. For post-1979 plants, all licensing correspondence associated with the comparison | |||
to Standard Review Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing | |||
purposes. | |||
3. Fire Protection Program: | |||
a. A listing of changes made to the FPP since the last triennial fire protection | |||
inspection; | |||
b. For pre-1979 plants, a listing of the protection methodologies identified under | |||
10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for selected | |||
fire zones/areas (to be determined during information gathering visit). That is, | |||
please specify whether 3-hour rated fire barriers; (Section III.G.2.a), 20 foot | |||
separation along with detection and suppression; (Section III.G.2.b), 1-hour rated | |||
fire barriers with detection and suppression; (Section III.G.2.c), or alternative | |||
shutdown capability; (Section III.G.3) is used as a strategy for each selected fire | |||
zone/area; | |||
c. A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe-shutdown | |||
evaluations); | |||
d. A list of applicable codes and standards related to the design of plant fire | |||
protection features. The list should include National Fire Protection Association | |||
(NFPA) code versions committed to (i.e., the NFPA Codes of Record); and | |||
e. List of plant deviations from code commitments and associated evaluations. | |||
4. Facility Information: | |||
a. Piping and instrumentation (flow) diagrams showing the components used to | |||
achieve and maintain hot standby and cold shutdown for fires outside the control | |||
room, those components used for those areas requiring alternative shutdown | |||
capability, and systems relied upon for B.5.b mitigation strategies. These can be of | |||
the type that are used for training; | |||
b. One-line schematic drawings of the electrical distribution system for 4160 Volts | |||
alternating current (Vac) down to 480Vac; | |||
c. One-line schematic drawings of the electrical distribution system for 250 Volts | |||
direct current (Vdc) and 125Vdc systems as applicable; | |||
d. Logic diagrams showing the components used to achieve and maintain hot | |||
standby and cold shutdown; and | |||
e. Safe shutdown cable routing database (requested electronically such as on | |||
compact disc, if available. | |||
3 Enclosure | |||
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS | |||
5. Operations Response for Fire Protection: | |||
a. Pre-fire plans for selected fire zones/areas (to be determined during information | |||
gathering visit); and | |||
b. Plant operating procedures which specify the initial operations response to a fire | |||
alarm or annunciator; | |||
c. Procedure for calling out the fire brigade and requesting off-site assistance. | |||
6. Corrective Actions: | |||
a. Listing of open and closed fire protection condition reports (i.e., problem | |||
identification forms and their resolution reports) since the date of the last triennial | |||
fire protection inspection; and | |||
b. List of current fire impairments, including duration. | |||
7. General Information: | |||
a. A listing of abbreviations and/or designators for plant systems; | |||
b. Organization charts of site personnel down to the level of fire protection staff | |||
personnel; and | |||
c. A phone list for on-site licensee personnel. | |||
8. B.5.b Mitigating Strategies: | |||
a. A list of all modifications to regulatory commitments made to meet the | |||
requirements of Section B.5.b of the ICM Order, EA-02-026, dated | |||
February 25, 2002, the subsequently imposed license conditions, and | |||
10 CFR 50.54(hh)(2); | |||
b. Copies of procedures/guidelines that were revised or generated to implement the | |||
mitigation strategies. These could be extensive damage mitigation guidelines | |||
(EDMGs), severe accident management guidelines (SAMGs), emergency | |||
operating procedures (EOPs), abnormal operating procedures (AOPs), etc.; | |||
c. A matrix that shows the correlation between the mitigation strategies identified in | |||
Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that | |||
are used to implement each strategy; | |||
d. A listing of engineering evaluations/calculations that were used to verify | |||
engineering bases for the mitigation strategies; | |||
e. Copies of procedures used to inventory equipment (hoses, fittings, pumps, etc.) | |||
required to be used to implement the mitigation strategies; | |||
4 Enclosure | |||
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS | |||
f. A list of B.5.b mitigating strategies, if any, which have implementing details that | |||
differ from that documented in the submittals and the safety evaluation report; | |||
g. Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments) | |||
required to implement any mitigating strategies; and | |||
h. A list of changes made to B.5.b mitigating strategies and associated procedures | |||
since the previous NRC inspection of B.5.b mitigating strategies (October 2008). | |||
9. On-site Discussions: | |||
In addition, during the information gathering visit, it is requested that licensee staff be | |||
available for the following: | |||
a. Informal discussion on plant procedures operators would use in the event of fire or | |||
explosion (including B.5.b mitigation strategies) and under what conditions would | |||
the plant be shutdown using alternative shutdown methodology; | |||
b. Informal discussion on the plants safe shutdown cable routing database and the | |||
plant-wide cable routing database, as applicable; and | |||
c. A tour of alternative shutdown and risk-significant fire areas. | |||
III. Information Requested to be Available on First Day of the Second On-site Inspection | |||
Week (APRIL 11, 2011) | |||
The following information is requested to be provided on the first day of inspection. It is | |||
requested that this information be provided on three sets of CDs (searchable, if possible). | |||
1. Program Procedures: | |||
a. Procedures for: | |||
i. Administrative controls (such as allowed out of service times and | |||
compensatory measures) for fire protection systems and components | |||
ii. Control of transient combustibles | |||
iii. Control of hot work | |||
b. List of maintenance and surveillance testing procedures for alternative shutdown | |||
capability and fire barriers, detectors, pumps, and suppression systems; and | |||
c. List of maintenance procedures which routinely verify fuse breaker coordination | |||
in accordance with the post-fire safe shutdown coordination analysis. | |||
5 Enclosure | |||
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS | |||
2. Design and Equipment Information: | |||
a. Coordination calculations and/or justifications that verify fuse/breaker | |||
coordination for selected fire zones/areas (to be determined during | |||
information gathering visit) that are fed off of the same electrical buses as | |||
components in the protected safe shutdown train; | |||
b. Copies of significant fire protection and post-fire safe shutdown related design | |||
change package descriptions (including their associated 10 CFR 50.59 | |||
evaluations) and Generic Letter (GL) 86-10 (or adverse to safe shutdown) | |||
evaluations; | |||
c. Gaseous suppression system pre-operational testing, if applicable, for selected | |||
fire zones/areas (to be determined during information gathering visit); | |||
d. Hydraulic calculations and supporting test data which demonstrate operability for | |||
water suppression systems, if applicable, for selected fire zones/areas (to be | |||
determined during information gathering visit); | |||
e. Alternating current (ac) coordination calculations for 4160Vac down to 480Vac | |||
electrical systems; | |||
f. List of all fire protection or Appendix R calculations. | |||
3. Assessment and Corrective Actions: | |||
a. The three most recent fire protection Quality Assurance (QA) audits and/or fire | |||
protection self-assessments. | |||
4. Any updates to information previously provided. | |||
IV. Information Requested to Be Provided Throughout the Inspection | |||
1. Copies of any corrective action documents generated as a result of the inspection | |||
teams questions or queries during this inspection. | |||
2. Copies of the list of questions submitted by the inspection team members and the | |||
status/resolution of the information requested (provided daily during the inspection to | |||
each inspection team member). | |||
If you have questions regarding the information requested, please contact the lead inspector. | |||
6 Enclosure | |||
J. Davis -3- | |||
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room) | |||
Sincerely, | |||
/RA by R. A. Langstaff for/ | |||
Robert C. Daley, Chief | |||
Engineering Branch 3 | |||
Division of Reactor Safety | |||
Docket Nos. 50-341 | |||
License Nos. NPF-43 | |||
Enclosure: Fire Protection Inspection Document Request | |||
cc w/encl: Distribution via ListServ | |||
DISTRIBUTION: | |||
Daniel Merzke | |||
RidsNrrDorlLpl3-1 Resource | |||
RidsNrrPMFermi2 Resource | |||
RidsNrrDirsIrib Resource | |||
Cynthia Pederson | |||
Steven Orth | |||
Jared Heck | |||
Allan Barker | |||
Carole Ariano | |||
Linda Linn | |||
DRPIII | |||
DRSIII | |||
Patricia Buckley | |||
Tammy Tomczak | |||
ROPreports Resource | |||
DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\Ltr 012011 Fermi 2011009 Fire | |||
Protection RFI .docx | |||
9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive | |||
To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy | |||
OFFICE RIII RIII | |||
NAME RLangstaff:ls RLangstaff for RDaley | |||
DATE 01/20/11 01/20/11 | |||
OFFICIAL RECORD COPY | |||
}} | }} |
Latest revision as of 04:20, 13 November 2019
ML110200355 | |
Person / Time | |
---|---|
Site: | Fermi |
Issue date: | 01/20/2011 |
From: | Robert Daley Engineering Branch 3 |
To: | Jennifer Davis Detroit Edison |
References | |
Download: ML110200355 (10) | |
See also: IR 05000341/2011009
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE ROAD, SUITE 210
LISLE, IL 60532-4352
January 20, 2011
Mr. Jack M. Davis
Senior Vice President and
Chief Nuclear Officer
Detroit Edison Company
Fermi 2 - 210 NOC
6400 North Dixie Highway
Newport, MI 48166
SUBJECT: FERMI POWER PLANT, UNIT 2 - NOTIFICATION TO PERFORM A TRIENNIAL
FIRE PROTECTION BASELINE INSPECTION; INSPECTION REPORT
Dear Mr. Davis
On March 23, 2011, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial fire
protection baseline inspection at your Fermi Power Plant, Unit 2. This inspection will be
performed in accordance with Inspection Procedure (IP) 71111.05T, the NRCs baseline fire
protection inspection procedure.
Based on the latest revision to IP 71111.05T, dated September 30, 2010, changes were made
to the IP which now requires the fire protection inspection to review your actions to mitigate
postulated events that could potentially cause loss of large areas of power reactor facilities due
to explosions or fires. This requirement was implemented by the issuance of the Interim
Compensatory Measures Order EA-02-026, Section B.5.b and the subsequent requirements of
10 CFR 50.54(hh)(2), which are collectively referred to as B.5.b requirements. During this
inspection, the B.5.b requirements review will be performed during the first on-site week of the
inspection starting on March 23, 2011.
The schedule for the on-site inspection activity is as follows:
y Information Gathering Visit: March 21 - 23, 2011
y B.5.b Requirements: March 23 - 25, 2011; and
y Fire Protection Inspection: April 11 - 15, 2011 and April 25 - 29, 2011
The purpose of the information gathering visit is: (1) to obtain information and documentation
needed to support the inspection; (2) to become familiar with the Fermi Power Plant fire
protection programs, fire protection features, post-fire safe shutdown capabilities, and plant
layout; and (3) to arrange administrative details, such as office space, availability of
knowledgeable office personnel and to ensure unescorted site access privileges.
J. Davis -2-
Experience has shown that the baseline fire protection inspections are extremely resource
intensive both for the NRC inspectors and the licensee staff. In order to minimize the inspection
impact on the site and to ensure a productive inspection for both organizations, we have
enclosed a request for documents needed for the inspection. These documents have been
divided into four groups. The first group lists information necessary to aid the inspection team in
choosing specific focus areas for the inspection. It is requested that this information be
provided to the lead inspector via mail or electronically no later than March 7, 2011. The
second group also lists information and areas for discussion necessary to aid the inspection
team in choosing specific fire protection focus areas for the inspection and to ensure that the
inspection team is adequately prepared for the inspection. It is requested this information be
available during the information gathering visit (March 21, 2011). The third group of requested
documents consists of those items that the team will review, or need access to, during the
inspection. Please have this information available by the first day of the second on-site
inspection week (April 11, 2011). The fourth group lists the information necessary to aid the
inspection team in tracking issues identified as a result of the inspection. It is requested that
this information be provided to the lead inspector as the information is generated during the
inspection. It is important that all of these documents are up to date and complete in order
to minimize the number of additional documents requested during the preparation and/or the
on-site portions of the inspection.
The lead inspector for this inspection is Mr. R. Langstaff. We understand that our regulatory
contact for this inspection is Mr. R. Salmon of your organization. If there are any questions
about the inspection or the material requested, please contact the lead inspector at (630) 829-
9747 or via e-mail at Ronald.Langstaff@nrc.gov.
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, Control Number
3150-0011.
The NRC may not conduct or sponsor, and a person is not required to respond to a request for
information or an information collection requirement unless the requesting document displays a
currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document
J. Davis -3-
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by R. A. Langstaff for/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket Nos. 50-341
License Nos. NPF-43
Enclosure: Fire Protection Inspection Document Request
cc w/encl: Distribution via ListServ
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS
Inspection Report: 05000341/2011-009(DRS)
On-site Inspection Dates: March 21 - 23, 2011 (Information Gathering Visit)
March 23 - 25, 2011 (B.5.b Requirements)
April 11 - 15, 2011 (Fire Protection Inspection)
April 25 - 29, 2011 (Fire Protection Inspection)
Inspection Procedures: IP71111.05T, Fire Protection (Triennial)
IP71152, "Identification and Resolution of Problems"
Inspectors: R. A. Langstaff, Senior Reactor Inspector
(630) 829-9747
Ronald.Langstaff@nrc.gov
G. M. Hausman, Senior Reactor Inspector
(630) 829-9743
George.Hausman@nrc.gov
D. Szwarc, Reactor Inspector
(630) 829-9803
Dariusz.Szwarc@nrc.gov
Observer: N. A. Valos
(630) 829-9761
Nicholas.Valos@nrc.gov
J. S. Bowen
(301) 415-3471
Jeremy.Bowen@nrc.gov
I. Information Requested Prior To the Information Gathering Visit
The following information is requested by March 7, 2011. If you have any questions
regarding this request, please call the lead inspector as soon as possible. All information
should be sent to R.A. Langstaff (e-mail address Ronald.Langstaff@nrc.gov). Electronic
media is preferred. The preferred file format is a searchable pdf file on a compact
disk (CD). The CD should be indexed and hyper-linked to facilitate ease of use, if possible.
Please provide four copies of each CD submitted (one for each inspector).
1. The most risk-significant fire areas as determined by probabilistic risk analyses, if
available. Otherwise, the reactor plant's Individual Plant Examination for External
Events (IPEEE) for fire and results of any post-IPEEE reviews for fire.
1 Enclosure
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS
2. A copy of the current version of the fire protection program (FPP), fire hazards analysis
(FHA), safe shutdown analysis (SSA), updated safety analysis report (USAR), Technical
Specifications and license.
3. A list of fire areas requiring alternative shutdown capability, (i.e., those areas for which
10 CFR Part 50, Appendix R, Section III G requirements are satisfied under
Section III.G.3), or where both safe shutdown trains can be affected.
4. Plant operating procedures which would be used and describe shutdown for a
postulated fire (for both areas requiring alternative shutdown and areas which do not
require alternative shutdown). Only those procedures with actions specific to shutdown
in the event of a fire need be included.
II. Information Requested During the Information Gathering Visit (MARCH 21, 2011)
The following information is requested to be provided to the inspection team during the
on-site information gathering visit. Except for Item 8, it is requested that the following
information be provided on three sets of CDs (searchable, if possible) with the B.5.b
Mitigating Strategies information (Items 8.a through 8.h) provided on one separate CD. In
addition, one set of hard copy drawings are requested for Items 4.a. through 4.e.
1. One set of hard-copy documents for facility layout drawings, which identify plant fire area
delineation; areas protected by automatic fire suppression and detection; and locations
of fire protection equipment.
2. Licensing Information:
a. The facilitys license, including the fire protection license condition;
b. All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)
applicable to fire protection (specifically including those SERs referenced by
the plant fire protection license condition) and all licensing correspondence
referenced by the SERs;
c. All licensing correspondence associated with the comparison to Standard Review
Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes;
d. Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and associated
licensing correspondence;
e. For pre-1979 plants, all licensing correspondence associated with those
sections of 10 CFR Part 50, Appendix R, that are not applicable to the plant under
10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with
those fire protection features proposed or implemented by the licensee that have
been accepted by the NRC staff as satisfying the provisions of Appendix A to
Branch Technical Position (BTP) APCSB 9.5-1 reflected in the NRC fire protection
SERs issued before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire
protection features, which were accepted by the NRC staff in comprehensive fire
protection SERs issued before Appendix A to BTP APCSB 9.5-1 was published in
August 1976 (10 CFR 50.48(b)(1)(ii)); and
2 Enclosure
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS
f. For post-1979 plants, all licensing correspondence associated with the comparison
to Standard Review Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing
purposes.
3. Fire Protection Program:
a. A listing of changes made to the FPP since the last triennial fire protection
inspection;
b. For pre-1979 plants, a listing of the protection methodologies identified under
10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for selected
fire zones/areas (to be determined during information gathering visit). That is,
please specify whether 3-hour rated fire barriers; (Section III.G.2.a), 20 foot
separation along with detection and suppression; (Section III.G.2.b), 1-hour rated
fire barriers with detection and suppression; (Section III.G.2.c), or alternative
shutdown capability; (Section III.G.3) is used as a strategy for each selected fire
zone/area;
c. A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe-shutdown
evaluations);
d. A list of applicable codes and standards related to the design of plant fire
protection features. The list should include National Fire Protection Association
(NFPA) code versions committed to (i.e., the NFPA Codes of Record); and
e. List of plant deviations from code commitments and associated evaluations.
4. Facility Information:
a. Piping and instrumentation (flow) diagrams showing the components used to
achieve and maintain hot standby and cold shutdown for fires outside the control
room, those components used for those areas requiring alternative shutdown
capability, and systems relied upon for B.5.b mitigation strategies. These can be of
the type that are used for training;
b. One-line schematic drawings of the electrical distribution system for 4160 Volts
alternating current (Vac) down to 480Vac;
c. One-line schematic drawings of the electrical distribution system for 250 Volts
direct current (Vdc) and 125Vdc systems as applicable;
d. Logic diagrams showing the components used to achieve and maintain hot
standby and cold shutdown; and
e. Safe shutdown cable routing database (requested electronically such as on
compact disc, if available.
3 Enclosure
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS
5. Operations Response for Fire Protection:
a. Pre-fire plans for selected fire zones/areas (to be determined during information
gathering visit); and
b. Plant operating procedures which specify the initial operations response to a fire
alarm or annunciator;
c. Procedure for calling out the fire brigade and requesting off-site assistance.
6. Corrective Actions:
a. Listing of open and closed fire protection condition reports (i.e., problem
identification forms and their resolution reports) since the date of the last triennial
fire protection inspection; and
b. List of current fire impairments, including duration.
7. General Information:
a. A listing of abbreviations and/or designators for plant systems;
b. Organization charts of site personnel down to the level of fire protection staff
personnel; and
c. A phone list for on-site licensee personnel.
8. B.5.b Mitigating Strategies:
a. A list of all modifications to regulatory commitments made to meet the
requirements of Section B.5.b of the ICM Order, EA-02-026, dated
February 25, 2002, the subsequently imposed license conditions, and
10 CFR 50.54(hh)(2);
b. Copies of procedures/guidelines that were revised or generated to implement the
mitigation strategies. These could be extensive damage mitigation guidelines
(EDMGs), severe accident management guidelines (SAMGs), emergency
operating procedures (EOPs), abnormal operating procedures (AOPs), etc.;
c. A matrix that shows the correlation between the mitigation strategies identified in
Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that
are used to implement each strategy;
d. A listing of engineering evaluations/calculations that were used to verify
engineering bases for the mitigation strategies;
e. Copies of procedures used to inventory equipment (hoses, fittings, pumps, etc.)
required to be used to implement the mitigation strategies;
4 Enclosure
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS
f. A list of B.5.b mitigating strategies, if any, which have implementing details that
differ from that documented in the submittals and the safety evaluation report;
g. Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments)
required to implement any mitigating strategies; and
h. A list of changes made to B.5.b mitigating strategies and associated procedures
since the previous NRC inspection of B.5.b mitigating strategies (October 2008).
9. On-site Discussions:
In addition, during the information gathering visit, it is requested that licensee staff be
available for the following:
a. Informal discussion on plant procedures operators would use in the event of fire or
explosion (including B.5.b mitigation strategies) and under what conditions would
the plant be shutdown using alternative shutdown methodology;
b. Informal discussion on the plants safe shutdown cable routing database and the
plant-wide cable routing database, as applicable; and
c. A tour of alternative shutdown and risk-significant fire areas.
III. Information Requested to be Available on First Day of the Second On-site Inspection
Week (APRIL 11, 2011)
The following information is requested to be provided on the first day of inspection. It is
requested that this information be provided on three sets of CDs (searchable, if possible).
1. Program Procedures:
a. Procedures for:
i. Administrative controls (such as allowed out of service times and
compensatory measures) for fire protection systems and components
ii. Control of transient combustibles
iii. Control of hot work
b. List of maintenance and surveillance testing procedures for alternative shutdown
capability and fire barriers, detectors, pumps, and suppression systems; and
c. List of maintenance procedures which routinely verify fuse breaker coordination
in accordance with the post-fire safe shutdown coordination analysis.
5 Enclosure
FIRE PROTECTION INSPECTION DOCUMENT REQUESTS
2. Design and Equipment Information:
a. Coordination calculations and/or justifications that verify fuse/breaker
coordination for selected fire zones/areas (to be determined during
information gathering visit) that are fed off of the same electrical buses as
components in the protected safe shutdown train;
b. Copies of significant fire protection and post-fire safe shutdown related design
change package descriptions (including their associated 10 CFR 50.59
evaluations) and Generic Letter (GL) 86-10 (or adverse to safe shutdown)
evaluations;
c. Gaseous suppression system pre-operational testing, if applicable, for selected
fire zones/areas (to be determined during information gathering visit);
d. Hydraulic calculations and supporting test data which demonstrate operability for
water suppression systems, if applicable, for selected fire zones/areas (to be
determined during information gathering visit);
e. Alternating current (ac) coordination calculations for 4160Vac down to 480Vac
electrical systems;
f. List of all fire protection or Appendix R calculations.
3. Assessment and Corrective Actions:
a. The three most recent fire protection Quality Assurance (QA) audits and/or fire
protection self-assessments.
4. Any updates to information previously provided.
IV. Information Requested to Be Provided Throughout the Inspection
1. Copies of any corrective action documents generated as a result of the inspection
teams questions or queries during this inspection.
2. Copies of the list of questions submitted by the inspection team members and the
status/resolution of the information requested (provided daily during the inspection to
each inspection team member).
If you have questions regarding the information requested, please contact the lead inspector.
6 Enclosure
J. Davis -3-
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room)
Sincerely,
/RA by R. A. Langstaff for/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket Nos. 50-341
License Nos. NPF-43
Enclosure: Fire Protection Inspection Document Request
cc w/encl: Distribution via ListServ
DISTRIBUTION:
RidsNrrDorlLpl3-1 Resource
RidsNrrPMFermi2 Resource
RidsNrrDirsIrib Resource
Cynthia Pederson
DRPIII
DRSIII
Patricia Buckley
ROPreports Resource
DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\Ltr 012011 Fermi 2011009 Fire
Protection RFI .docx
9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive
To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy
OFFICE RIII RIII
NAME RLangstaff:ls RLangstaff for RDaley
DATE 01/20/11 01/20/11
OFFICIAL RECORD COPY