ML121310380: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
(5 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
| number = ML121310380 | | number = ML121310380 | ||
| issue date = 05/10/2012 | | issue date = 05/10/2012 | ||
| title = | | title = Acceptance Review Email, License Amendment Request to Revise Technical Specifications to Eliminate Use of the Term Core Alteration Consistent w/TSTF-471 and NUREG-1432, Revision 3 | ||
| author name = Singal B | | author name = Singal B | ||
| author affiliation = NRC/NRR/DORL/LPLIV | | author affiliation = NRC/NRR/DORL/LPLIV | ||
| addressee name = Stroud R | | addressee name = Stroud R | ||
| addressee affiliation = Arizona Public Service Co | | addressee affiliation = Arizona Public Service Co | ||
| docket = 05000528, 05000529, 05000530 | | docket = 05000528, 05000529, 05000530 | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: Singal, Balwant Sent: Thursday, May 10, 2012 7:42 AM To: russell.stroud@aps.com Cc: 'Thomas.N.Weber@aps.com' Subject: Acceptance of Application - License Amendment Request to Eliminate the Use of the Term CORE ALTERATIONS in the Technical Specifications (TACs ME8160, ME8161, and ME8162) | {{#Wiki_filter:From: Singal, Balwant Sent: Thursday, May 10, 2012 7:42 AM To: russell.stroud@aps.com Cc: 'Thomas.N.Weber@aps.com' | ||
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed alternative in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC | |||
==Subject:== | |||
Acceptance of Application - License Amendment Request to Eliminate the Use of the Term CORE ALTERATIONS in the Technical Specifications (TACs ME8160, ME8161, and ME8162) | |||
By letter dated March 8, 2012, Arizona Public Service Company (APS) submitted an amendment request for approval of the License Amendment Request to eliminate the use of term CORE ALTERATIONS throughout the Technical Specifications for Palo Verde Nuclear Generating Station, Units 1, 2, and 3. APS stated that the proposed amendment incorporates changes reflected in Technical Specification Task Force (TSTF) Traveler 471-A, Revision 1. | |||
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. | |||
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed alternative in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence. | |||
If you have any questions, please contact me. | |||
Balwant K. Singal Senior Project Manager (Comanche Peak, STP, and Palo Verde) | Balwant K. Singal Senior Project Manager (Comanche Peak, STP, and Palo Verde) | ||
Nuclear Regulatory Commission Division of Operating Reactor Licensing Balwant.Singal@nrc.gov Tel: (301) 415-3016 Fax: (301) 415-1222 | Nuclear Regulatory Commission Division of Operating Reactor Licensing Balwant.Singal@nrc.gov Tel: (301) 415-3016 Fax: (301) 415-1222}} | ||
}} |
Latest revision as of 15:27, 20 March 2020
ML121310380 | |
Person / Time | |
---|---|
Site: | Palo Verde |
Issue date: | 05/10/2012 |
From: | Balwant Singal Plant Licensing Branch IV |
To: | Stroud R Arizona Public Service Co |
Singal, Balwant, 415-3016, NRR/DORL/LPL4 | |
References | |
TAC ME8160, TAC ME8161, TAC ME8162 | |
Download: ML121310380 (1) | |
Text
From: Singal, Balwant Sent: Thursday, May 10, 2012 7:42 AM To: russell.stroud@aps.com Cc: 'Thomas.N.Weber@aps.com'
Subject:
Acceptance of Application - License Amendment Request to Eliminate the Use of the Term CORE ALTERATIONS in the Technical Specifications (TACs ME8160, ME8161, and ME8162)
By letter dated March 8, 2012, Arizona Public Service Company (APS) submitted an amendment request for approval of the License Amendment Request to eliminate the use of term CORE ALTERATIONS throughout the Technical Specifications for Palo Verde Nuclear Generating Station, Units 1, 2, and 3. APS stated that the proposed amendment incorporates changes reflected in Technical Specification Task Force (TSTF) Traveler 471-A, Revision 1.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed alternative in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
If you have any questions, please contact me.
Balwant K. Singal Senior Project Manager (Comanche Peak, STP, and Palo Verde)
Nuclear Regulatory Commission Division of Operating Reactor Licensing Balwant.Singal@nrc.gov Tel: (301) 415-3016 Fax: (301) 415-1222