IR 05000341/2011006: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 09/01/2011
| issue date = 09/01/2011
| title = Mid-Cycle Letter for Fermi Power Unit 2 - 05000341/2011-006
| title = Mid-Cycle Letter for Fermi Power Unit 2 - 05000341/2011-006
| author name = Giessner J B
| author name = Giessner J
| author affiliation = NRC/RGN-III/DRP/B4
| author affiliation = NRC/RGN-III/DRP/B4
| addressee name = Davis J M
| addressee name = Davis J
| addressee affiliation = Detroit Edison, Co
| addressee affiliation = Detroit Edison, Co
| docket = 05000341
| docket = 05000341
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:ember 1, 2011
[[Issue date::September 1, 2011]]


Mr. Jack Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
==SUBJECT:==
MID-CYCLE PERFORMANCE LETTER FOR FERMI POWER PLANT, UNIT 2; 05000341/2011-006


SUBJECT: MID-CYCLE PERFORMANCE LETTER FOR FERMI POWER PLANT, UNIT 2; 05000341/2011-006
==Dear Mr. Davis:==
On August 10, 2011, the NRC completed its mid-cycle performance review of the Fermi Power Plant, Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010, through June 30, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.
 
The NRC determined the performance at Fermi Power Plant, Unit 2, during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
 
The enclosed inspection plan lists the inspections scheduled through December 31, 2012.
 
Routine inspections performed by resident inspectors are not included in the inspection plan.


==Dear Mr. Davis:==
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on performing special and infrequently performed inspections: Inspection Procedure (IP) 60854.1, Preoperational Testing of Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants and IP 60855.1, Operation of an ISFSI at Operating Plants. In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs) at your facility. Results of these inspections can be found here:
On August 10, 2011, the NRC completed its mid-cycle performance review of the Fermi Power Plant, Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010, through June 30, 2011. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRC's assessment of your performance in the Security Cornerstone and its security-related inspection plan. The NRC determined the performance at Fermi Power Plant, Unit 2, during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through December 31, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan.
http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2),
and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident. The NRC is currently reviewing the Task Forces recommendations to determine what additional actions may be warranted.


The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on performing special and infrequently performed inspections: Inspection Procedure (IP) 60854.1, "Preoperational Testing of Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants" and IP 60855.1, "Operation of an ISFSI at Operating Plants." In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRC's processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, "Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event," and TI-184, "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)" at your facility. Results of these inspections can be found here: http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, "Mitigating Strategies," to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRC's Task Force made its recommendations to the Commission in its report, "Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident." The NRC is currently reviewing the Task Force's recommendations to determine what additional actions may be warranted. In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Please contact me at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.
Please contact me at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.


Sincerely,/RA/ John B.Giessner, Chief Branch 4 Division of Reactor Projects Docket No. 50-341 License No. NPF-43  
Sincerely,
 
/RA/
===Enclosure:===
John B.Giessner, Chief Branch 4 Division of Reactor Projects Docket No. 50-341 License No. NPF-43 Enclosure: Fermi 2 Inspection/Activity Plan cc w/encl: Distribution via ListServ
Fermi 2 Inspection/Activity Plan cc w/encl: Distribution via ListServ
}}
}}

Latest revision as of 16:20, 12 November 2019

Mid-Cycle Letter for Fermi Power Unit 2 - 05000341/2011-006
ML112440140
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 09/01/2011
From: Jack Giessner
Reactor Projects Region 3 Branch 4
To: Jennifer Davis
Detroit Edison, Co
References
IR-11-006
Download: ML112440140 (6)


Text

ember 1, 2011

SUBJECT:

MID-CYCLE PERFORMANCE LETTER FOR FERMI POWER PLANT, UNIT 2; 05000341/2011-006

Dear Mr. Davis:

On August 10, 2011, the NRC completed its mid-cycle performance review of the Fermi Power Plant, Unit 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010, through June 30, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined the performance at Fermi Power Plant, Unit 2, during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2012.

Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. We also plan on performing special and infrequently performed inspections: Inspection Procedure (IP) 60854.1, Preoperational Testing of Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants and IP 60855.1, Operation of an ISFSI at Operating Plants. In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs) at your facility. Results of these inspections can be found here:

http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2),

and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident. The NRC is currently reviewing the Task Forces recommendations to determine what additional actions may be warranted.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

John B.Giessner, Chief Branch 4 Division of Reactor Projects Docket No. 50-341 License No. NPF-43 Enclosure: Fermi 2 Inspection/Activity Plan cc w/encl: Distribution via ListServ