ML18267A195: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
| issue date = 09/18/2018
| issue date = 09/18/2018
| title = Decommissioning Funding Plans Interim Staff Guidance Presentation
| title = Decommissioning Funding Plans Interim Staff Guidance Presentation
| author name = Duvigneaud D D
| author name = Duvigneaud D
| author affiliation = NRC/NMSS/DFCSE/PORB
| author affiliation = NRC/NMSS/DFCSE/PORB
| addressee name =  
| addressee name =  
Line 9: Line 9:
| docket =  
| docket =  
| license number =  
| license number =  
| contact person = Duvigneaud D D
| contact person = Duvigneaud D
| document type = Decommissioning Funding Plan DKTs 30, 40, 50, 70, Slides and Viewgraphs
| document type = Decommissioning Funding Plan DKTs 30, 40, 50, 70, Slides and Viewgraphs
| page count = 7
| page count = 7
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:Update on Interim Staff Guidance Decommissioning Funding PlansMaterials Licensees Interim Staff GuidanceBackgroundNMSS has been working on a draft ISG (ML18163A087) covering:*Decommissioning Cost Estimate (DCE) reflecting current facility conditions
{{#Wiki_filter:Update on Interim Staff Guidance Decommissioning Funding Plans Materials Licensees
*Evaluating events since the last Decommissioning Funding Plan (DFP) approval
 
*Updates to financial instruments 2
Interim Staff Guidance
Interim Staff GuidanceDCE reflecting current facility conditionsPart 70 licensees covering inventory:
 
*Licensee owned  
===Background===
-contract in place where another party pays for packing, loading and shipping to an end destination
NMSS has been working on a draft ISG (ML18163A087) covering:
*Customer owned -customer retains legal title to the material and is contractually responsible for packing, loading and shipping to an end destination
* Decommissioning Cost Estimate (DCE) reflecting current facility conditions
*In-process inventory  
* Evaluating events since the last Decommissioning Funding Plan (DFP) approval
-justify a brief timeframe to process the material through into finished product, and then it will fall into licensee-owned or customer
* Updates to financial instruments 2
-owned inventoryThe draft ISG considers NEI's previous letter (ML16229A175) and NRC's response (ML16307A014)regarding DCE reflecting current facility conditions 3
 
Interim Staff GuidanceEvaluating events since last DFP approvalMake sure to include the 8 factors required by 30.35(e)(2), 40.36(d)(2) and CFR 70.25(e)(2):
Interim Staff Guidance DCE reflecting current facility conditions Part 70 licensees covering inventory:
*Spills of radioactive material impacting the subsurface
* Licensee owned - contract in place where another party pays for packing, loading and shipping to an end destination
*Waste inventory that exceeds previous estimate
* Customer owned - customer retains legal title to the material and is contractually responsible for packing, loading and shipping to an end destination
*Waste disposal costs that exceed previous cost estimated*Facility modifications
* In-process inventory - justify a brief timeframe to process the material through into finished product, and then it will fall into licensee-owned or customer-owned inventory The draft ISG considers NEIs previous letter (ML16229A175) and NRCs response (ML16307A014) regarding DCE reflecting current facility conditions 3
*Changes in possession limits*Remediation costs that exceed previous cost estimate
 
*Onsite disposal*Use of a settling pondTo reduce RAIs provide a narrative covering the 8 factors 4
Interim Staff Guidance Evaluating events since last DFP approval Make sure to include the 8 factors required by 30.35(e)(2), 40.36(d)(2) and CFR 70.25(e)(2):
Interim Staff GuidanceFinancial instruments
* Spills of radioactive material impacting the subsurface
*Send original hard copy financial instruments directly to site PM not NRC Document Control as DC does not maintain original hard
* Waste inventory that exceeds previous estimate
-copy documents*For approval, NRC staff needs to review all agreements including any side letters to the financial instruments
* Waste disposal costs that exceed previous cost estimated
*A template sight draft is being provided for staff use Banks typically require a sight draft to draw on the financial instrument
* Facility modifications
*Guidance on addressing CPA's opinion of off
* Changes in possession limits
-balance sheet transactions for guarantees
* Remediation costs that exceed previous cost estimate
*Supporting documents for Statements of Intent*Verifying trust operations are regulated and examined by a Federal or State agency 5
* Onsite disposal
Interim Staff GuidanceNotices *August 1stFederal Register Notice (FRN) published seeking comments on draft ISG requesting comments by September 17, 2018*NEI contacted NMSS and indicated they would be holding a meeting with industry and requested to extend the comment period until after this meeting; therefore, on August 21stan FRN was published extending the comment period to October 5, 2018 6
* Use of a settling pond To reduce RAIs provide a narrative covering the 8 factors 4
Interim Staff GuidanceNext steps*NMSS looks forward to receiving comments on the draft ISG  
 
*Working towards publishing final ISG at the end of January 2019 7}}
Interim Staff Guidance Financial instruments
* Send original hard copy financial instruments directly to site PM not NRC Document Control as DC does not maintain original hard-copy documents
* For approval, NRC staff needs to review all agreements including any side letters to the financial instruments
* A template sight draft is being provided for staff use Banks typically require a sight draft to draw on the financial instrument
* Guidance on addressing CPAs opinion of off-balance sheet transactions for guarantees
* Supporting documents for Statements of Intent
* Verifying trust operations are regulated and examined by a Federal or State agency                                                       5
 
Interim Staff Guidance Notices
* August 1st Federal Register Notice (FRN) published seeking comments on draft ISG requesting comments by September 17, 2018
* NEI contacted NMSS and indicated they would be holding a meeting with industry and requested to extend the comment period until after this meeting; therefore, on August 21st an FRN was published extending the comment period to October 5, 2018 6
 
Interim Staff Guidance Next steps
* NMSS looks forward to receiving comments on the draft ISG
* Working towards publishing final ISG at the end of January 2019 7}}

Latest revision as of 14:18, 20 October 2019

Decommissioning Funding Plans Interim Staff Guidance Presentation
ML18267A195
Person / Time
Issue date: 09/18/2018
From: Dylanne Duvigneaud
Programmatic Oversight and Regional Support Branch
To:
Duvigneaud D
References
Download: ML18267A195 (7)


Text

Update on Interim Staff Guidance Decommissioning Funding Plans Materials Licensees

Interim Staff Guidance

Background

NMSS has been working on a draft ISG (ML18163A087) covering:

  • Decommissioning Cost Estimate (DCE) reflecting current facility conditions
  • Updates to financial instruments 2

Interim Staff Guidance DCE reflecting current facility conditions Part 70 licensees covering inventory:

  • Licensee owned - contract in place where another party pays for packing, loading and shipping to an end destination
  • Customer owned - customer retains legal title to the material and is contractually responsible for packing, loading and shipping to an end destination
  • In-process inventory - justify a brief timeframe to process the material through into finished product, and then it will fall into licensee-owned or customer-owned inventory The draft ISG considers NEIs previous letter (ML16229A175) and NRCs response (ML16307A014) regarding DCE reflecting current facility conditions 3

Interim Staff Guidance Evaluating events since last DFP approval Make sure to include the 8 factors required by 30.35(e)(2), 40.36(d)(2) and CFR 70.25(e)(2):

  • Spills of radioactive material impacting the subsurface
  • Waste inventory that exceeds previous estimate
  • Waste disposal costs that exceed previous cost estimated
  • Facility modifications
  • Changes in possession limits
  • Remediation costs that exceed previous cost estimate
  • Onsite disposal
  • Use of a settling pond To reduce RAIs provide a narrative covering the 8 factors 4

Interim Staff Guidance Financial instruments

  • Send original hard copy financial instruments directly to site PM not NRC Document Control as DC does not maintain original hard-copy documents
  • For approval, NRC staff needs to review all agreements including any side letters to the financial instruments
  • A template sight draft is being provided for staff use Banks typically require a sight draft to draw on the financial instrument
  • Guidance on addressing CPAs opinion of off-balance sheet transactions for guarantees
  • Supporting documents for Statements of Intent
  • Verifying trust operations are regulated and examined by a Federal or State agency 5

Interim Staff Guidance Notices

  • August 1st Federal Register Notice (FRN) published seeking comments on draft ISG requesting comments by September 17, 2018
  • NEI contacted NMSS and indicated they would be holding a meeting with industry and requested to extend the comment period until after this meeting; therefore, on August 21st an FRN was published extending the comment period to October 5, 2018 6

Interim Staff Guidance Next steps

  • NMSS looks forward to receiving comments on the draft ISG
  • Working towards publishing final ISG at the end of January 2019 7