ML18267A195: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 09/18/2018 | | issue date = 09/18/2018 | ||
| title = Decommissioning Funding Plans Interim Staff Guidance Presentation | | title = Decommissioning Funding Plans Interim Staff Guidance Presentation | ||
| author name = Duvigneaud | | author name = Duvigneaud D | ||
| author affiliation = NRC/NMSS/DFCSE/PORB | | author affiliation = NRC/NMSS/DFCSE/PORB | ||
| addressee name = | | addressee name = | ||
Line 9: | Line 9: | ||
| docket = | | docket = | ||
| license number = | | license number = | ||
| contact person = Duvigneaud | | contact person = Duvigneaud D | ||
| document type = Decommissioning Funding Plan DKTs 30, 40, 50, 70, Slides and Viewgraphs | | document type = Decommissioning Funding Plan DKTs 30, 40, 50, 70, Slides and Viewgraphs | ||
| page count = 7 | | page count = 7 | ||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:Update on Interim Staff Guidance Decommissioning Funding | {{#Wiki_filter:Update on Interim Staff Guidance Decommissioning Funding Plans Materials Licensees | ||
*Evaluating events since the last Decommissioning Funding Plan (DFP) approval | |||
*Updates to financial instruments 2 | Interim Staff Guidance | ||
Interim Staff | |||
*Licensee owned | ===Background=== | ||
-contract in place where another party pays for packing, loading and shipping to an end destination | NMSS has been working on a draft ISG (ML18163A087) covering: | ||
*Customer owned -customer retains legal title to the material and is contractually responsible for packing, loading and shipping to an end destination | * Decommissioning Cost Estimate (DCE) reflecting current facility conditions | ||
*In-process inventory | * Evaluating events since the last Decommissioning Funding Plan (DFP) approval | ||
-justify a brief timeframe to process the material through into finished product, and then it will fall into licensee-owned or customer | * Updates to financial instruments 2 | ||
-owned | |||
Interim Staff | Interim Staff Guidance DCE reflecting current facility conditions Part 70 licensees covering inventory: | ||
*Spills of radioactive material impacting the subsurface | * Licensee owned - contract in place where another party pays for packing, loading and shipping to an end destination | ||
*Waste inventory that exceeds previous estimate | * Customer owned - customer retains legal title to the material and is contractually responsible for packing, loading and shipping to an end destination | ||
*Waste disposal costs that exceed previous cost estimated*Facility modifications | * In-process inventory - justify a brief timeframe to process the material through into finished product, and then it will fall into licensee-owned or customer-owned inventory The draft ISG considers NEIs previous letter (ML16229A175) and NRCs response (ML16307A014) regarding DCE reflecting current facility conditions 3 | ||
*Changes in possession limits*Remediation costs that exceed previous cost estimate | |||
*Onsite disposal*Use of a settling | Interim Staff Guidance Evaluating events since last DFP approval Make sure to include the 8 factors required by 30.35(e)(2), 40.36(d)(2) and CFR 70.25(e)(2): | ||
Interim Staff | * Spills of radioactive material impacting the subsurface | ||
*Send original hard copy financial instruments directly to site PM not NRC Document Control as DC does not maintain original hard | * Waste inventory that exceeds previous estimate | ||
-copy documents*For approval, NRC staff needs to review all agreements including any side letters to the financial instruments | * Waste disposal costs that exceed previous cost estimated | ||
*A template sight draft is being provided for staff use Banks typically require a sight draft to draw on the financial instrument | * Facility modifications | ||
*Guidance on addressing | * Changes in possession limits | ||
-balance sheet transactions for guarantees | * Remediation costs that exceed previous cost estimate | ||
*Supporting documents for Statements of Intent*Verifying trust operations are regulated and examined by a Federal or State agency 5 | * Onsite disposal | ||
Interim Staff | * Use of a settling pond To reduce RAIs provide a narrative covering the 8 factors 4 | ||
Interim Staff | |||
*Working towards publishing final ISG at the end of January 2019 7}} | Interim Staff Guidance Financial instruments | ||
* Send original hard copy financial instruments directly to site PM not NRC Document Control as DC does not maintain original hard-copy documents | |||
* For approval, NRC staff needs to review all agreements including any side letters to the financial instruments | |||
* A template sight draft is being provided for staff use Banks typically require a sight draft to draw on the financial instrument | |||
* Guidance on addressing CPAs opinion of off-balance sheet transactions for guarantees | |||
* Supporting documents for Statements of Intent | |||
* Verifying trust operations are regulated and examined by a Federal or State agency 5 | |||
Interim Staff Guidance Notices | |||
* August 1st Federal Register Notice (FRN) published seeking comments on draft ISG requesting comments by September 17, 2018 | |||
* NEI contacted NMSS and indicated they would be holding a meeting with industry and requested to extend the comment period until after this meeting; therefore, on August 21st an FRN was published extending the comment period to October 5, 2018 6 | |||
Interim Staff Guidance Next steps | |||
* NMSS looks forward to receiving comments on the draft ISG | |||
* Working towards publishing final ISG at the end of January 2019 7}} |
Latest revision as of 14:18, 20 October 2019
ML18267A195 | |
Person / Time | |
---|---|
Issue date: | 09/18/2018 |
From: | Dylanne Duvigneaud Programmatic Oversight and Regional Support Branch |
To: | |
Duvigneaud D | |
References | |
Download: ML18267A195 (7) | |
Text
Update on Interim Staff Guidance Decommissioning Funding Plans Materials Licensees
Interim Staff Guidance
Background
NMSS has been working on a draft ISG (ML18163A087) covering:
- Decommissioning Cost Estimate (DCE) reflecting current facility conditions
- Evaluating events since the last Decommissioning Funding Plan (DFP) approval
- Updates to financial instruments 2
Interim Staff Guidance DCE reflecting current facility conditions Part 70 licensees covering inventory:
- Licensee owned - contract in place where another party pays for packing, loading and shipping to an end destination
- Customer owned - customer retains legal title to the material and is contractually responsible for packing, loading and shipping to an end destination
- In-process inventory - justify a brief timeframe to process the material through into finished product, and then it will fall into licensee-owned or customer-owned inventory The draft ISG considers NEIs previous letter (ML16229A175) and NRCs response (ML16307A014) regarding DCE reflecting current facility conditions 3
Interim Staff Guidance Evaluating events since last DFP approval Make sure to include the 8 factors required by 30.35(e)(2), 40.36(d)(2) and CFR 70.25(e)(2):
- Spills of radioactive material impacting the subsurface
- Waste inventory that exceeds previous estimate
- Waste disposal costs that exceed previous cost estimated
- Facility modifications
- Changes in possession limits
- Remediation costs that exceed previous cost estimate
- Onsite disposal
- Use of a settling pond To reduce RAIs provide a narrative covering the 8 factors 4
Interim Staff Guidance Financial instruments
- Send original hard copy financial instruments directly to site PM not NRC Document Control as DC does not maintain original hard-copy documents
- For approval, NRC staff needs to review all agreements including any side letters to the financial instruments
- A template sight draft is being provided for staff use Banks typically require a sight draft to draw on the financial instrument
- Guidance on addressing CPAs opinion of off-balance sheet transactions for guarantees
- Supporting documents for Statements of Intent
- Verifying trust operations are regulated and examined by a Federal or State agency 5
Interim Staff Guidance Notices
- August 1st Federal Register Notice (FRN) published seeking comments on draft ISG requesting comments by September 17, 2018
- NEI contacted NMSS and indicated they would be holding a meeting with industry and requested to extend the comment period until after this meeting; therefore, on August 21st an FRN was published extending the comment period to October 5, 2018 6
Interim Staff Guidance Next steps
- Working towards publishing final ISG at the end of January 2019 7