- IR 05000302/1986031 + (339)
- 05000366/LER-1986-020, :on 860924,primary Containment Penetrations Failed Local Leak Tests.Caused by Normal Equipment Wear. Affected Valves of 34 Failed Penetration Tests Cycled, Repaired,Rebuilt or Replaced + (138)
- ML19294C023 + (9)
- 05000321/LER-1987-009, :on 870427,primary Containment Penetrations Found Leaking in Excess of Leakage Requirements.Caused by Normal Use & Wear.Valves Either Cycled,Repaired,Rebuilt, Replaced or Plugged Until Replacement + (210A)
- ML20063A050 + (2)
- ML20085M241 + (35)
- ML20203B092 + (35)
- ML20247B925 + (121)
- IR 05000369/2020001 + (35)
- LIC-05-0057, Revised Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors + (6)
- LIC-15-0069, Response to NRC Request for Additional Information Regarding Relief Request RR-14 + (31)
- ML11308A097 + (35)
- NOC-AE-07002180, Results of Reactor Head Penetration Inspection Pursuant to Revision 1 of Order EA-03-009 + (35)
- 05000336/LER-1997-011-02, :on 970402,improperly Adjusted Dual Function Valves Occurred.Caused by Insufficient Program to Ensure, Facility Procedures Clearly Addressed All Related Design Basis Functions.Affected Valves Will Be Adjusted + (2)
- ML071870415 + (35)
- DCL-06-019, To Relaxation Request for NRC Issuance of First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors + (35)
- ML030020565 + (54)
- ML032671199 + (35)
- ML16279A517 + (35)
- ML20155J270 + (353)
- IR 05000302/1998007 + (347)
- 05000302/LER-1984-001, :on 840113,during Refueling Outage,End Cap in Reactor Containment Bldg Incorrectly Cut Off.Caused by Personnel Failing to Follow Engineering Procedures. Engineering Evaluation to Be Performed + (3531)
- 05000302/LER-1984-001-01, Updated LER 84-001-01:on 840113,end Cap on Reactor Bldg Side of Spare Penetration 3531 Mistakenly Cut Off.Caused by Personnel Failure to Follow Applicable Engineering Procedures.Personnel Retrained + (3531)
- 05000366/LER-1986-020, :on 860924,primary Containment Penetrations Failed Local Leak Tests.Caused by Normal Equipment Wear. Affected Valves of 34 Failed Penetration Tests Cycled, Repaired,Rebuilt or Replaced + (138)
- 05000321/LER-1987-009, :on 870427,primary Containment Penetrations Found Leaking in Excess of Leakage Requirements.Caused by Normal Use & Wear.Valves Either Cycled,Repaired,Rebuilt, Replaced or Plugged Until Replacement + (210A)
- ML15217A143 + (36)
- ML20063A050 + (2)
- IR 05000255/2019002 + (33)
- L-PI-03-101, 60-Day Report Pursuant to NRC Bulletin 2003-02 for 2003, Lower Head Penetration Inspection + (36)
- ML18123A247 + (36)
- ML033500301 + (36)
- AECM-87-0201, Application for Amend to License NPF-29,changing Tech Specs to Support Design Change to Divisional Power Supplies for RWCU Sys Containment & Drywell Isolation Valves.Fee Paid + (87)
- ML13329A457 + (37)
- LIC-05-0057, Revised Relaxation Request for First Revised Order (EA-03-009) Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors + (6)
- IR 05000334/1982011 + (37)
- IR 05000302/1987026 + (11)
- ML16141A479 + (37B)
- GNRO-2003/00029, One Time Extension on Integrated Leak Rate Test & Drywell Bypass Test Interval + (38)
- IR 05000334/2022004 + (38)
- ML20128F607 + (38)
- ML20082N974 + (111)
- ML18152A305 + (38)
- ML20215K647 + (111)
- ML19317F245 + (38)
- LIC-15-0069, Response to NRC Request for Additional Information Regarding Relief Request RR-14 + (31)
- ML040300152 + (38)
- ML18152B104 + (38)