 Issue dateFromTitleProject stage
ML13189A05611 July 2013Billoch-Colon A
Plant Licensing Branch II
Request for Additional Information - Overall Integrated Plant in Response to Order EA-12-051 Reliable Spent Fuel Pool InstrumentationRAI
RNP-RA/13-0080, Response to NRC Request for Additional Information Regarding Overall Integrated Plan Submitted in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation8 August 2013Duke Energy
William Gideon
Response to NRC Request for Additional Information Regarding Overall Integrated Plan Submitted in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool InstrumentationResponse to RAI
ML13273A48119 November 2013Siva Lingam
Plant Licensing Branch II
Interim Staff Evaluation and Request for RAI Regarding Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool InstrumentationRAI
ML14027A06324 January 2014NRC/NRR/DPR/MSD
Mega-Tech Services
Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for H. B. Robinson Steam Electric Plant, Unit 2, TAC No.: MF0720Other
ML13365A29119 February 2014Jeremy Bowen
NRC/NRR/DPR/MSD/MSPB
Interim Staff Evaluation Regarding Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies)Acceptance Review
RNP-RA/14-0009, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)24 February 2014Duke Energy
William Gideon
Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)Other
RNP-RA/14-0082, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)26 August 2014Duke Energy
William Gideon
Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)Other
ML15020A38828 January 2015Jason Paige
Japan Lessons-Learned Division
Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051Other
RNP-RA/15-0015, Fourth Six-Month Status Reports in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)23 February 2015Duke Energy
Glover R
Fourth Six-Month Status Reports in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)Other
ML15154B09812 June 2015Jason Paige
Japan Lessons-Learned Division
Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051Other