ML20202J128 | 30 November 1998 | Technical Evaluation Rept Pump & Valve Inservice Testing Program Shearon Harris Nuclear Power Plant | Safe Shutdown Boric Acid Stroke time Excess Flow Check Valve Power Operated Valves Scaffolding |
ML20127E306 | 30 September 1992 | TER for Evaluation of ODCM Rev 3,Shearon Harris Nuclear Power Plant,Unit 1 | Offsite Dose Calculation Manual Anticipated operational occurrence Power change |
ML19332B584 | 30 September 1989 | Conformance to Generic Ltr 83-28,Item 2.2.1-Equipment Classification for All Other Safety-Related Components: Harris, Technical Evaluation Rept | |
ML18005A652 | 31 July 1988 | Technical Evaluation Rept on First 10-Yr Interval Inservice Insp Program:Shearon Harris Nuclear Power Plant,Unit 1. | Hydrostatic VT-2 Incorporated by reference Dissimilar Metal Weld |
ML18022A639 | 29 February 1988 | Rev 1 to Technical Evaluation Rept,Pump & Valve Inservice Testing Program. | Boric Acid Stroke time Cold shutdown justification Power Operated Valves Overspeed trip |
ML18004B837 | 31 March 1987 | Technical Evaluation Rept,Pump & Valve Inservice Testing Program,Shearon Harris Nuclear Power Plant,Unit 1, Informal Rept | Boric Acid Stroke time Cold shutdown justification Power Operated Valves Overspeed trip |
ML20215G270 | 31 March 1987 | Demonstration of Containment Purge & Vent Valve Operability, Informal Rept | |
ML20214F503 | 31 March 1987 | Conformance to Generic Ltr 83-28,Item 2.2.2, `Vendor Interface Programs (All Other Safety-Related Components),' Shearon Harris 1 & 2, Technical Evaluation Rept | |
ML20211N503 | 9 January 1987 | Reactor Trip Sys Reliability Conformance to Item 4.5.2 of Generic Ltr 83-28,HB Robinson Steam Electric Plant,Unit 2, Salem Generating Station Units 1 & 2,Shearon Harris Nuclear Power Plant Unit 1..., Technical Evaluation Rept | |
ML20205E399 | 31 July 1986 | Conformance to Generic Ltr 83-28,Item 2.1 (Part 1), Equipment Classification (Reactor Trip Sys Components) Ginna,Haddam Neck,Millstone 3 & Harris 1 | |
ML18003B241 | 30 April 1986 | Audit of Pump & Valve Operability Assurance Program for Shearon Harris Nuclear Power Plant,Informal Rept | Stroke time Hydrostatic Anchor Darling Overspeed trip |
ML18003B242 | 31 March 1986 | Sqrt Visit Rept, Informal Rept | Stroke time Safe Shutdown Earthquake Operating Basis Earthquake Earthquake |
ML20154G718 | 28 February 1986 | Review of the Shearon Harris Unit 1 Auxiliary Feedwater System Reliability Analysis | Stroke time Time to boil Earthquake Power-Operated Valves Power Operated Valves |
ML20136F653 | 31 December 1985 | Review of Tdi Diesel Generator Owners Group Engine Requalification Program,Final Rept, Technical Evaluation Rept | Nondestructive Examination |
ML20137F898 | 30 September 1985 | Conformance to Reg Guide 1.97,Shearon Harris Nuclear Power Plant,Units 1 & 2 | Grab sample |
ML20128H779 | 30 June 1985 | Rev 1 to Review of Engine Base & Bearing Caps for Tdi DSRV-12,DSRV-16 & DSRV-20 Diesel Engines, Technical Evaluation Rept | |
ML20126E986 | 31 May 1985 | Review of Emergency Diesel Generator Engine & Auxiliary Module Wiring & Terminations, Technical Evaluation Rept | |
ML20106A418 | 31 August 1984 | Control of Heavy Loads at Nuclear Power Plants,Shearon Harris Nuclear Power Plants,Units 1 & 2, Draft Technical Evaluation Rept | Safe Shutdown Safe Shutdown Earthquake Control of Heavy Loads |
ML20010F060 | 30 July 1981 | Power Coordination Agreement Between CP&L & Nc Municipal Power Agency Number 3 & Exhibits. | |
ML20010F067 | 30 July 1981 | Operating & Fuel Agreement Between CP&L & Nc Municipal Power Agency Number 3 & Exhibits. | Earthquake Uranium Hexafluoride |
ML20010F071 | 30 July 1981 | Purchase,Const & Ownership Agreement Between CP&L & Nc Municipal Power Agency Number 3 & Exhibits. | Earthquake Uranium Hexafluoride |
ML20010F075 | 30 July 1981 | Settlement Agreement Between VEPCO & Nc Municipal Power Agency Number 3 Including Agreement for Interim Electric Svc & Agreement for Transmission Use & Other Electric Svc. | Incorporated by reference Earthquake |