Enterfy Entergy Operations, Inc.
River Bend Station 5485 U.S. Highway 61N St. Francisville, LA 70775 Tel 225-381-4374 Jerry C. Roberts Director, Nuclear Safety Assurance RBG-47229 April 3, 2012 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Supplemental Information Concerning License Amendment Submittals.
River Bend Station, Unit 1 Docket No. 50-458 License No. NPF-47
REFERENCES:
- 1. Entergy Letter to NRC dated September 16, 2011; Supplemental Information - Changes to Technical Specification 3,3.6.1, "Primary Containment and Drywell Isolation Instrumentation" (RBG-47176)
- 2. Entergy Letter to NRC dated February 7, 2012; Response to Request for Information - Changes to Technical Specification 3.3.6.1, "Primary Containment and Drywell Isolation Instrumentation" (RBG-47207)
- 3. Entergy Letter to NRC dated February 24, 2012; Response to Request for Information - Changes to Technical Specification 3.3.6.1, "Primary Containment and Drywell Isolation Instrumentation" (RBG-47211)
- 4. Entergy Letter to NRC dated October 13, 2011; Supplemental Information - Proposed Emergency Plan Change - Alternate EOF Relocation (RBG-47183)
Dear Sir or Madam:
As a result of internal reviews, Entergy Operations, Inc. (Entergy) has determined submittals in support of requests for amendments to the Technical Specifications (TS) and the Emergency Plan (EP) for River Bend Station (RBS), Unit 1, did not include signatures by a designated officer of the company and an oath or affirmation. The inclusion of these two items is required in internal procedures. Additional guidance is included in NRC Regulatory Issue Summary 2001-18, Requirements for Oath or Affirmation. This subject has been discussed with the NRC Project Manager.
In three letters supplying supplemental information supporting a request to amend the TS concerning TS 3.3.6.1, "Primary Containment and Drywell Isolation Instrumentation," the designated officer and affirmations were not included (References 1, 2 and 3).
Aco(
RBG-47229 Page 2 of 3 In one letter supplying supplemental information supporting a request to change the EP alternate Emergence Operations Facility (EOF) the affirmation was not included (Reference 4).
This letter confirms that References 1, 2, 3, and 4 have been approved by a designated officer of the company and include an affirmation.
There are no new commitments in this letter. If you have any.questions or require additional information, please contact Mr. Joseph A. Clark at (225) 381-4177.
I declare under penalty of perjury that the foregoing is true and correct. Executed on April 3, 2012.
Sincerely, JCR/JAC/bmb cc: Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Blvd.
Arlington, TX 76011-4511 NRC Senior Resident Inspector P. 0. Box 1050 St. Francisville, LA 70775 U. S. Nuclear Regulatory Commission Attn: Mr. Alan B. Wang One White Flint MS 0-8 BI Washington, DC 20555-0001 Department of Environmental Quality Office of Environmental Compliance Radiological Emergency Planning and Response Section JiYoung Wiley P.O. Box 4312 Baton Rouge, LA 70821-4312
RBG-47229 Page 3 of 3 Public Utility Commission of Texas Attn: PUC Filing Clerk 1701 N. Congress Avenue P. O. Box 13326 Austin, TX 78711-3326