Submittal of Owners Activity Report Forms (OAR-1)
ML050540426
Person / Time
Site: River Bend Entergy icon.png
Issue date: 02/17/2005
From: Lorfing D
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RBF1-05-0028, RBG-46403
Download: ML050540426 (18)


Text

--dEn tgy Entergy Operations, Inc.

River Bend Station 5485 U. S. Highway 61N St. Francisville. LA 70775 Fax 225 635 5068 February 17, 2005 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Subject:

River Bend Station Docket No. 50-458 Submittal of Owner's Activity Report Forms (OAR-1)

File No.: G9.5 RBF 1-05-0028 RBG-46403 Ladies and Gentlemen:

Pursuant to ASME Code Case N-532-1, please find enclosed three Owner's Activity Report Forms (OAR-I) for River Bend Station (RBS). The reports reflect ASME Section XI program activities occurring during the second inspection period of the second ten year program interval (Cycles 10, 11 and 12) which ended October, 2004.

If you have any questions or require further information, please contact Mr. Bill Fountain at (225) 381-4625.

Sincerely, DNL/WJF enclosures

~( OL(

Submittal of Owner's Activity Report Forms (OAR-1)

RBG-46403 Page 2 of 2 cc:

U.S. Nuclear Regulatory Commission (2 copies)

Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011 NRC Sr. Resident Inspector P.O. Box 1050 St. Francisville, LA 70775 Mr. Michael K. Webb U. S. Nuclear Regulatory Commission M/S OWFN 7D1 Washington, DC 20555

i.

FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number:

Cycle 10 I Refueling RF-10 OAR-1 Owner:

Entergy Operations, Incorporated i>.O. Box 220, St. Francisville, Louisiana 70775 (Name and Address of Owner)

Plant:

River Bend Station P.O. Box 220, St. Francisville, Louisiana 70775 (Name and Address of Plant)

Unit No.:

I Commercial service 06/16/86 Refueling RF-10 date:

outage:

Current inspection 2nd Inspection Interval interval:

(1st, 2nd, 3rd, 4th. Other)

Current inspection period:

2nd Inspection Period (1st, 2nd, 3rd)

Edition & Addenda of Section XI 1980 Ed. to Winter 1981 Add.

applicable to inspection plan:

1992 Ed. thru select portions of 1993 Add.

1995 Ed. to 1996 Add.

Date and revision of inspection plan:

Rev. 1, dated 111512001 Edition & Addenda of Section Xl applicable to repairs &

N/A replacements, if different than the inspection plan:

CERTIFICATE OF COMPLIANCE I certify that the statements in this Owner's Activity Report are correct, and that the examinations, tests, repairs, replacements, evaluations, and corrective measures presented by this report conform to the requirements of Section Xl.

Certificate of Authorization No.:

N/A Expiration Date:

N/A Signed:

(ia

.(If applicable)

Date:

6 2r'? 2002.

'reo4,ICAK. SpeafItuV Owner or Owner's Designee, Title CERTIFICATE OF INSERVICE INSPECTION I, undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of Louisiana and employed by Factory Mutual Insurance Co. of Johnston. RI have inspected the items described in this Owner's Activity Report, during the period of April. 2001 to October, 2001 and states that to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section Xl.

By signing this certificate neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations, tests, repairs, replacements, evaluations and corrective measures described in this report. Furthermore, neither the inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection Commissions:

LA 1406, N, lIS

'"-4Rs~ector's Signature National Board, State, Province, and I-_

I A -

Endorsements Date:

Y/

° 2--

TABLE I ABSTRACT OF EXAMINATIONS AND TESTS Total Examinations Total Examinations Total Examinations Total Examinations Category Required for The Credited for The Credited (%) for The Date for The Remarks Second Interval Second Period Second Period Second Interval B-A 24 2

28.57%

41.66%

None B-D 62 0

0.00%

29.03%

None B-F 22 0

0.00%

13.63%

None B-G(1 304 80 100.00%

52.63%

None B-G-2 77 25 96.15%

67.53 None B-J 267 21 35.00%

35.58%

None B-K 14 0

0.00%

21.42%

None B-L-2__

0 0

N/A N/A None B-M-2" 0

0 N/A N/A None B-N-1_ __

3 0

0.00%

33.33%

None B-N-2__)

29 0

0.00%

0.00%

None B-O 16 0

0.00%

0.00%

None B-P 182 26 33.33%

42.85%

None C-A"'

2 0

0.00%

50.00%

None C-13"B_

2 0

0.00%

50.00%

None C-C 21 4

57.14%

52.38%

None C-F-1 28 0

0.00%

32.14%

None C-F-2 75 3

14.29%

33.33%

None C-G 21 6

100%

57.14%

None C-H 378 50 39.68%

46.56%

None D-A 16 0

0.00%

18.75%

None D-B 270 8

9.30%

39.25%

None E-A 3

0 0.00%

0.00%

None E(CML) 0 0

N/A N/A None E-D_ __

All See Note M See Note M See Note M None E-G__

53 16 45.71%

30.18%

None E-P All

  • Appendix J Program F-A F1.O1(K) 75 13 65.00%

33.33%

None F-A F1.201N) 134 46 100%

69.40%

None F-A F1.301K) 92 31 100%

83.69%

None F-A F1.40(KJ 14 0

0.00%

28.57%

None F-C 3.10-40 (snubbers) 160*

0 0.00%

33.33%

0.00%

35.44%

None April 2001 to October 2001 Page 1 of 2

TABLE I ABSTRACT OF EXAMINATIONS AND TESTS A. Items B06.020 and 806.030 are combined to achieve period percentages, since these items refer to the reactor pressure vessel closure studs.

Six studs are routinely removed during each refueling outage and receive a B06.030 examination.

B. Selections of items are based on Note 3 of B-G-1, where examinations are limited to components selected for examination under Categories B-J-2, and B-M-2.

C. Examinations are based on the number of components with B-G-2 bolting. For CRD housings when disassembled.

D. Note 2 of Examination Category B-G-2 allow bolting examination to valves be limited to components selected for examination under Examination Category B-M-2. Since valves under B-M-2 are only examined during disassembly for maintenance, one valve of multiple valves with the same design, size, and function have been selected for examination.

E. Pump casings and valve bodies' internal surface examinations are only required when the pump or valve is disassembled for maintenance; therefore, these components have not been selected. One pump or valve from each group will be examined if disassembly Is required for maintenance.

F. The reactor pressure vessel interior will be inspected (813.010) each inspection period.

G. Inspection of B-N-2, item Numbers B13.020, 813.030, and B13.040 are permitted to be examined at the end of the inspection interval.

H. Inspection of B-0, Item Number B14.010 is permitted to be examined at the end of the inspection interval.

I.

Selection of items are based on Note 3 of C-A or C-B, where examinations are limited to one component due to multiple components of the same design, size, and service.

J.

Items cannot be examined due to physical barriers or material configurations (refer to Relief Request RR2-0001, RR2-0002, and RR2-0003).

K. Items shall be examined during each inspection period.

L. No additional examinations were required due to degradation or repair/replacement activities.

M. Examinations performed per Relief Request IWE-03:Appendix J Program.

N. 16 examinations performed prior to 4/2001 for Item E8.10. Reference Relief Request IWE-02: No examinations required for Item E8.20.

April 2001 to October 2001 Page 2 of 2

TABLE 2 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Flaw Flaw or Relevant Condition Found Examination Item Item Characterization During Scheduled Section Xl Category Number Description (IWA-3300)

Examination or Test (Yes or No)

F-C F3.50 RHS-PSSP-3078-Al - piping snubber support N/A Yes F-C F3.50 RHS-PSSP-3161-AI - piping snubber support NIA Yes I.

I.

April 2001 to October 2001 Page 1 of 1

TABLE 3 ABSTRACT OF REPAIRS, REPLACEMENTS, OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE Flaw or Relevant

Repair, Condition Found During Replacement, Scheduled Section Xl Repair I Code or Corrective Item Description Examination or Test Date Replacement Class Measure Description of Work (Yes or No)

Complete Plan Number 1

Replacement RHS-PSSP-3078-A1 Replaced failed snubber Yes 10/04/01 Master - 007 SNUBBER test failure with pre-tested spare.

(MAI 336941)

Ref. CR-RBS-01-1285 1

Replacement RHS-PSSP-3161-Al Replaced failed snubber Yes 10/04/01 Master - 007 SNUBBER test failure with pre-tested spare.

(MAI 336940)

Ref. CR-RBS-01-1269 2

Replacement SW-Hose-1 75 Replaced flex hose No 10/09/01 IS-1-01-1331 R/O Flex hose leak (MAI 351456)

Ref. CR-RBS-01-1331 April 2001 to October 2001 Page 1 of 1

FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number:

Owner.

Cycle 11 1 Refueling RF-11 OAR-1 Entergy Operations, Incorporated P.O. Box 220, St. Francisville, Louisiana 70775 Plant:

(Name and Address of Owner)

River Bend Station P.O. Box 220, St. Francisville, Louisiana 70775 (Name and Address of Plant)

Unit No.:

I Commercial service 0611I date:

Current Inspection 2nd Inspection Interval interval:

(1st,:

Current inspection period:

2nd Inspection Period Edition & Addenda of Section Xl 1980 Ed. t applicable to inspection plan:

1992 Ed. t 1995 Ed. t 1/86 Refueling outage:

RF-11 2nd. 3rd. 4th, Other)

(Ist. 2nd, 3rd) o Winter 1981 Add.

,hru select portions of 1993 Add.

o 1996 Add.

Date and revision of inspection plan:

Rev. 1, dated 111512001 Edition & Addenda of Section Xl applicable to repairs &

N/A replacements, If different than the inspection plan:

CERTIFICATE OF COMPLIANCE I certify that the statements in this Owner's Activity Report are correct, and that the examinations, tests, repairs, replacements, evaluations, and corrective measures presented by this report conform to the requirements of Section Xl.

Certificate of Authorization No.:

NIA Expiration Date:

NIA Sine:

,-dIC*(it appDicable)

I Signed: (AJtL-t k

k

'-t4,1wHcei -

Date:

qlsIaoaq' Owner or Owner's Dedignee.1Title CERTIFICATE OF INSERVICE INSPECTION I, undersigned, holding a valid commission Issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of Louisiana and employed by ABS Group Inc. of Houston. TX have Inspected the Items described In this Owner's Activity Report, during the period of October. 2001 to April, 2003 and states that to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section Xl.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, conceming the examinations, tests, repairs, replacements, evaluations and corrective measures described In this report. Furthermore, neither the inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this inspection I

CI

-Commissions:

LA 1406. N. l. NS spez&s Signature c

1/g/20 v National Board, State, Province, and Endorsements L

PAGG St o F (

TABLE 1 ABSTRACT OF EXAMINATIONS AND TESTS Examination Category Total Examinations Total Examinations Total Examinations Total Examinations Remarks Required for The Credited for This Credited (%) For The Credited (%) To Date Interval Period Period for The Interval B-A 24 3

42.85%

45.83%

None B-D 62 0

0.00%

29.03%

None B-F 22 0

0.00%

13.63%

None B-G-1 {A-5) 304 80 100.00%

52.63%

None B-G-2 i

77 26 100%

68.83%

None B-J 267 32 53.33%

39.70%

None B-K 14 4

100.00%

50.00%

None B-L-2 I'0 0

N/A N/A None B-M-2 i

t 0

0 N/A N/A None B-N-1 3

0 0.00%

33.33%

None B-N-2 i

29 0

0.00%

0.00%

None B-O (")

16 0

0.00%

0.00%

None B-P 182 52 66.33%

57.14%

None C-Am 2

0 0.00%

50.00%

None C-B "a 2

0 0.00%

50.00%

None C-C 21 6

85.71%

61.90%

None C-F-1 28 2

22.22%

39.28%

None C-F-2 75 17 80.95%

52.00%

None C-G 21 6

100%

57.14%

1 duplicate in RF10 C-HIU) 378 88 69.84%

56.61%

None D-A 16 1

20.00%

25.00%

None D-B(M)270 49 56.97%

54.44%

None E-A 3

0 0.00%

0.00%

None E-C"L' 0

0 N/A N/A None E-D MiAll See Note M See Note M See Note M None E-G(

53 35 100%

66.03%

None October 2001 to April 2003 Page 2 of 6

TABLE 1 ABSTRACT OF EXAMINATIONS AND TESTS E-P All

  • Appendix J Program F-A F01.010(K^

75 20 100%

42.66%

None F-A F01.020('K 134 46 100%

69.40%

None F-A F01.030"'

92 31 100%

83.69%

None F-A F01.0401K) 14 2

100%

42.85%

None F-C 3.10-40 (Snubbers) 156**

156 100%

66.66%

    • Examined per GL90-F-C 3.50 (Snubbers) 72***

6 25.00%

47.22%

None

      • - Due to Snubber Reduction October 2001 to April 2003 Page 3 of 6

TABLE I ABSTRACT OF EXAMINATIONS AND TESTS River Bend Station OAR Table 1 Notes A. Items B06.020 and 806.030 are combined to achieve period percentages, since these items refer to the reactor pressure vessel closure studs. Six studs are routinely removed during each refueling outage and receive a B06.030 examination.

B. Selections of items are based on Note 3 of B-G-1, where examinations are limited to components selected for examination under CatagoriesB-J-2, and B-M-2.

C. Examinations are based on the number of components with B-G-2 bolting. For CRD housings when disassembled.

D. Note 2 of Examination Category B-G-2 allow bolting examination to valves be limited to components selected for examination under Examination Category B-M-2. Since valves under B-M-2 are only examined during disassembly for maintenance, one valve of multiple valves with the same design, size, and function have been selected for examination.

E. Pump casings and valve bodies' internal surface examinations are only required when the pump or valve ids disassembled for maintenance; therefore, these components have not been selected. One pump or valve from each group will be examined if disassembly is required for maintenance.

F. The reactor pressure vessel interior will be inspected (B13.010) each inspection period.

G. Inspection of B-N-2, item Numbers B13.020, B13.030, and B13.040 are permitted to be examined at the end of the inspection interval.

H. Inspection of B-O, Item Number B14.010 is permitted to be examined at the end of the inspection interval.

I.

Selection of items are based on Note 3 of C-A or C-B, where examinations are limited to one component due to multiple components of the same design, size, and service.

J. Items cannot be examined due to physical barriers or material configurations (refer to Request for Relief RR2-0001, RR2-0002, and RR2-0003).

K. Items shall be examined during each inspection period.

L. No additional examinations were required due to degradation or repair/replacement activities.

M. Examinations performed per Appendix J Program only in accordance with Relief Request IWE-03.

N. 16 examinations performed prior to 4/2001 for Item E8.10. Reference Relief Request IWE-02. No examinations required for Item E8.20.

0. 130 individual test packages per period P. 91 individual test packages per period October 2001 to April 2003 Page 4 of 6

TABLE 2 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Flaw Flaw or Relevant Condition Found Examination Item Item Characterization During Scheduled Section Xl Category Number Description (IWA-3300)

Examination or Test (Yes or No)

C-H C7.30 MSIV Accumulator Tank inspection port threaded N/A YES - VT-2 System Leakage Test connections leaking (ref. CR-RBS-2003-01004)

I I

I October 2001 to April 2003 Page 5 of 6

TABLE 3 ABSTRACT OF REPAIRS, REPLACEMENTS, OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE Flaw or Relevant

Repair, Condition Found During Replacement, Scheduled Section XI Repair Code or Corrective Item Description Examination or Test (Yes Date Replacement Class Measure Description of Work or No)

Complete Plan Number 3

Replacement 2.0" pipe MSS-002-163-3 Cut out and replace YES - VT-2 System 4/5/2003 IS-1 1368 R/1 for WO through wall leak (ref.

defective portion of pipe Leakage Test 50367851 CR-RBS-2003-01012) 2 Replacement 1.5" flex hose SW-Cut out and replace NO 4/4/2003 IS-1 1376 RIO for WO HOSE-164 leaking (ref.

leaking flex hose 50368358 CR-RBS-2003-1576 October 2001 to April 2003 Page 6 of 6

FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number:

Owner:

Cycle 12/ Refueling RF-12 OAR-I Entergy Operations, Incorporated 5485 U.S. Highway 61, St. Francisville, Louisiana 70775 Plant:

(Name and Address of Owner)

River Bend Station 5485 U.S. Highway 61, St. Francisville, Louisiana 70775 (Name and Address of Plant)

Unit No.:

I Commercial service date:

Current inspection 2nd Inspe interval:

06/16/86 Refueling outage:

ction Interval RF-12 (1st. 2nd, 3rd, 4th, Other)

Current inspection period:

2nd Inspection Period Edition & Addenda of Section XI applicable to inspection plan:

(1st. 2nd. 3rd) 1980 Ed. to Winter 1981 Add.

1992 Ed. thru select portions of 1993 Add.

1995 Ed. to 1996 Add.

Date and revision of inspection plan:

Rev.

Edition & Addenda of Section Xl applicable to repairs &

N/A replacements, if different than the inspection plan:

1, dated 1/15/2001 CERTIFICATE OF COMPLIANCE I certify that the statements in this Owner's Activity Report are correct, and that the examinations, tests, repairs, replacements, evaluations, and corrective measures presented by this report conform to the requirements of Section XI.

Certificate of Authorization No.:

N/A Expiration Date:

N/A (if applicable)

Signed: 6J0 t

Date:

2-1 71 2.ozS Owner or Owner's Designee. Title CERTIFICATE OF INSERVICE INSPECTION I, undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of Louisiana and employed by ABS Group Inc. of Houston. TX have inspected the items described in this Owner's Activity Report, during the period of April, 2003 to October, 2004 and states that to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section XI.

By signing this certificate neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations, tests, repairs, replacements, evaluations and corrective measures described in this report. Furthermore, neither the inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection Commissions:

LA 1406, N, l, NS r's Signature National Board, State, Province, and Date:Endorsements Date:...L/?/2Zoa

TABLE I ABSTRACT OF EXAMINATIONS AND TESTS Examination Total Examinations Total Examinations Total Examinations Total Examinations Catego Required for The Credited for This Credited (%) For The Credited (%) To Date Remarks ryInterval Period Period for The Interval B-A 24 3

42.85%

45.83%

See note P B-D 62 20 100.00%

61.29%

None B-F 22 10 100.00%

59.09%

None B-G-1 (A-1 304 80 100.00%

52.63%

None B-G-2 '

77 26 100.00%

68.83%

None B-J 267 59 98.33%

49.81%

See note Q B-K 14 4

100.00%

50.00%

None B-L-2 0('

0 N/A N/A None B-M-2 0(t_

1 N/A N/A None B-N-3 1 ____3100.00%

66.00%

None B-N-2 "'

29 0

0.00%

0.00%

None B-O F' 16 0

0.00%

0.00%

None B-P 182 78 100.00%

71.42%

None 2

0 0.00%

50.00%

None C-B "'J" 2

0 0.00%

50.00%

None C-C 21 7

100.00%

66.66%

None C-F-1 28 3

33.33%

42.85%

See note 0 C-F-2 75 21 100.00%

57.33%

None C-G 21 6

100.00%

57.14%

None C-H 378 126 100.00%

  • 66.66%

None D-A 16 5

100.00%

50.00%

None D-B 270 86 100.00%

68.14%

None E-A 3

1 100.00%

66.66%

None E-C (L) 0 0

N/A N/A None E__

-1___All See Note M See Note M See Note M None E-G(N) 53 35 100.00%

66.03%

None E-P All

  • Appendix J Program F-A F01.010 75 20 100.00%

42.66%

None F-A F01.020 134 46 100.00%

69.40%

None F-A F01.030 92 31 100.00%

83.69%

None F-A F01.040 14 (

2 100.00%

42.85%

See note R F-C 3.10-40 (Snubbers) 152*

152 100.00%

66.66%

'Examined per GL90-09 F-C 3.50 (Snubbers) 70*"

24 100.00%

74.28%

    • Due to snubber reduction April 2003 to October 2004 Page 2 of 5

TABLE I ABSTRACT OF EXAMINATIONS AND TESTS River Bend Station OAR Table I Notes A. Items B06.020 and B06.030 are combined to achieve period percentages, since these items refer to the reactor pressure vessel closure studs.

Six studs are routinely removed during each refueling outage and receive a 806.030 examination.

B. Selections of items are based on Note 3 of B-G-1, where examinations are limited to components selected for examination under Categories B-J-2, and B-M-2.

C. Examinations are based on the number of components with B-G-2 bolting. For CRD housings when disassembled.

D. Note 2 of Examination Category B-G-2 allow bolting examination to valves be limited to components selected for examination under Examination Category B-M-2. Since valves under B-M-2 are only examined during disassembly for maintenance, one valve of multiple valves with the same design, size, and function have been selected for examination.

E. Pump casings and valve bodies' internal surface examinations are only required when the pump or valve is disassembled for maintenance; therefore, these components have not been selected. One pump or valve from each group will be examined if disassembly Is required for maintenance. Percentages to not apply for this category.

F. The reactor pressure vessel interior will be inspected (813.010) each inspection period.

G. Inspection of B-N-2, item Numbers B13.020, B13.030, and 813.040 are permitted to be examined at the end of the inspection interval.

H. Inspection of B-0, Item Number 814.010 is permitted to be examined at the end of the inspection interval.

I.

Selection of items are based on Note 3 of C-A or C-B, where examinations are limited to one component due to multiple components of the same design, size, and service.

J.

Items cannot be examined due to physical barriers or material configurations (refer to Request for Relief RR2-0001, RR2-0002, and RR2-0003).

K. For multiple components other than piping, within a system of similar design, function, and service, the supports of only one multiple of the components are require to be examined.

L. No additional examinations were required due to degradation or repair/replacement activities.

M. Examinations performed per Appendix J Program only in accordance with Relief Request IWE-03.

N. 16 examinations performed prior to 4/2001 for Item E8.10.Reference Relief Request IWE-02. No examinations required for Item E8.20.

0. CEP-ISI-003-PCN-03 was written to identify six category C-F-1 welds which are located under water. Relief request will be generated base on no replacements being available.

P. CEP-ISI-003-PCN-17 was written to identify items B13-DO01-AC, BJ, BK, and BM that move to Period 3.

Q. CEP-ISI-003-PCN-18 was written to identify item FWS-038A-FW003 that move to Period 3.

R. CEP-ISI-003-PCN-24 was written to clarify periodic selection for this examination Category F-A-F01.040.

April 2003 to October 2004 Page 3 of 5

TABLE 2 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Flaw Flaw or Relevant Condition Found Examination Item Item Characterization During Scheduled Section Xl Category Number Description (IWA-3300)

Examination or Test (Yes or No)

F-C*

F3.50*

Mechanical snubber failed as-found initial running drag N/A YES - VT-3 Functional Test Iportion of functional test (ref. CR-RBS-2004-03284)

  • Code of Record for snubbers - ASME Xl, 1980 Edition with the Winter 1981 Addenda April 2003 to October 2004 Page 4 of 5

TABLE 3 ABSTRACT OF REPAIRS, REPLACEMENTS, OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE C'

Repair, Item Description Flaw or Relevant Date Repair I Code Replacement, Description of Work Condition Found During Complete Replacement Class or Corrective Scheduled Section XI Plan Number Measure Examination or Test (Yes or No) 2 Replacement Mechanical snubber S/N Replaced failed snubber YES - VT-3 Functional 12/14/04 M007-50358781 RIO for RHS-PSSP-2155-A2 with pre-tested spare Test WO 50358781 April 2003 to October 2004 Page 5 of 5