No. IV-08-006
Contact:
Victor Dricks Phone: (817) 860-8128 January 16, 2008 E-Mail: opa4@nrc.gov NRC CONDUCTING SPECIAL INSPECTION AT WOLF CREEK NUCLEAR PLANT The U.S. Nuclear Regulatory Commission is conducting a special inspection at the Wolf Creek nuclear plant in response to problems discovered in a safety system that provides cooling water for the reactor during an emergency. The plant, located near Burlington, Kan., is operated by the Wolf Creek Nuclear Operating Corp.
On Jan. 10, operators discovered pockets of gas in a pipe that should be filled with water.
The pipe is part of the emergency core cooling system which provides water to the reactor during an emergency. Workers shut the plant down on Jan. 11 to address the problem.
The problem is believed to have been caused by several leaky valves and a pocket of gas that remained in a pipe since the last refueling outage in the fall of 2006. The licensee has vented the gas from the piping and is in the process of restarting the reactor.
We want to take a look at the way the licensee has responded to the problem, said Region IV Administrator Elmo E. Collins. Its possible that the gas pockets may have prevented the emergency core cooling system from being able to perform its safety function had it been needed.
A two-person team of NRC specialists will review the circumstances related to the problem, the licensees root cause evaluation and the effect it had on the operability of the safety system. The team consists of a senior project engineer from the NRCs Region IV office in Arlington, Texas, and a resident inspector from the Waterford nuclear plant in Louisiana.
The inspection will begin today and is expected to take several days. The team will write a report about 30 - 45 days after completion of the inspection. The report will be available on the agencys online document library at: http://www.nrc.gov/reading-rm/adams/web-based.html.
NRC news releases are available through a free list serve subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region IV 611 Ryan Plaza Drive - Suite 400 Arlington, Texas 76011-4005 Telephone: (817) 860-8128