MONTHYEARML24047A0872023-05-0909 May 2023 News Release-II-23-015: NRC Schedules Meeting to Discuss Safety Performance of NFS Erwin Facility ML22305A5492022-10-17017 October 2022 News Release-II-22-027: NRC Conducts Special Inspection at Nuclear Fuel Services Facility Press Release-21-009, NRC to Hold Virtual Meeting to Discuss Safety Performance of NFS Erwin Facility2021-04-22022 April 2021 Press Release-21-009: NRC to Hold Virtual Meeting to Discuss Safety Performance of NFS Erwin Facility Press Release-II-19-028, NRC Schedules Open House to Discuss Safety Performance of Nfs Erwin Facility2019-05-0707 May 2019 Press Release-II-19-028: NRC Schedules Open House to Discuss Safety Performance of Nfs Erwin Facility Press Release-II-17-023, NRC Schedules Public Meeting to Discuss Safety Performance of Nfs Erwin Facility2017-04-13013 April 2017 Press Release-II-17-023: NRC Schedules Public Meeting to Discuss Safety Performance of Nfs Erwin Facility Press Release-II-15-005, NRC Returns Nfs Facility in Erwin, Tenn., to Normal Agency Oversight and Inspection2015-03-0505 March 2015 Press Release-II-15-005: NRC Returns Nfs Facility in Erwin, Tenn., to Normal Agency Oversight and Inspection Press Release-II-14-048, NRC Schedules Sept. 30 Public Outreach Meeting in Erwin2014-09-16016 September 2014 Press Release-II-14-048: NRC Schedules Sept. 30 Public Outreach Meeting in Erwin Press Release-II-14-036, NRC Begins Special Inspection at Nuclear Fuel Services2014-07-0101 July 2014 Press Release-II-14-036: NRC Begins Special Inspection at Nuclear Fuel Services Press Release-II-13-055, NRC Assigns Senior Resident Inspector to Nuclear Fuel Services in Erwin, Tenn2013-08-28028 August 2013 Press Release-II-13-055: NRC Assigns Senior Resident Inspector to Nuclear Fuel Services in Erwin, Tenn Press Release-II-13-020, NRC to Discuss Nfs Performance at Public Meeting in Erwin2013-04-18018 April 2013 Press Release-II-13-020: NRC to Discuss Nfs Performance at Public Meeting in Erwin Press Release-11-203, NRC Finds No Significant Environmental Impact from Proposed Renewal of Nfs Operating License2011-10-26026 October 2011 Press Release-11-203: NRC Finds No Significant Environmental Impact from Proposed Renewal of Nfs Operating License Press Release-II-11-043, NRC Schedules Meeting to Discuss Restart of Nfs Process Line2011-08-0404 August 2011 Press Release-II-11-043: NRC Schedules Meeting to Discuss Restart of Nfs Process Line Press Release-II-10-080, NRC Schedules Meeting to Discuss Restart of Nfs Line2010-11-22022 November 2010 Press Release-II-10-080: NRC Schedules Meeting to Discuss Restart of Nfs Line Press Release-10-185, NRC Seeks Comment on Draft Environmental Assessment of Nfs License Renewal; Public Meeting Scheduled Oct. 262010-10-15015 October 2010 Press Release-10-185: NRC Seeks Comment on Draft Environmental Assessment of Nfs License Renewal; Public Meeting Scheduled Oct. 26 Press Release-II-10-060, NRC Proposes $140,000 Fine Against Nuclear Fuel Services2010-09-0303 September 2010 Press Release-II-10-060: NRC Proposes $140,000 Fine Against Nuclear Fuel Services Press Release-II-10-001, NRC Issues Confirmatory Action Letter to Nuclear Fuel Services2010-01-0707 January 2010 Press Release-II-10-001: NRC Issues Confirmatory Action Letter to Nuclear Fuel Services Press Release-II-09-059, NRC Augments Inspection at Nuclear Fuel Services2009-10-22022 October 2009 Press Release-II-09-059: NRC Augments Inspection at Nuclear Fuel Services Press Release-II-09-036, NRC Reschedules Nuclear Fuel Services Meeting on Proposed New Line for July 222009-07-13013 July 2009 Press Release-II-09-036: NRC Reschedules Nuclear Fuel Services Meeting on Proposed New Line for July 22 Press Release-II-08-048, NRC Schedules Two Public Meetings to Discuss Nfs Nuclear Fuel Plant Performance2008-09-24024 September 2008 Press Release-II-08-048: NRC Schedules Two Public Meetings to Discuss Nfs Nuclear Fuel Plant Performance Press Release-03-090, NRC Approves License Amendment for Nuclear Fuel Services, Inc2003-07-0909 July 2003 Press Release-03-090: NRC Approves License Amendment for Nuclear Fuel Services, Inc Press Release-II-03-032, NRC to Hold Meeting June 6 at Nfs to Discuss Readiness Review Associated with Proposed Project Bleu2003-05-27027 May 2003 Press Release-II-03-032: NRC to Hold Meeting June 6 at Nfs to Discuss Readiness Review Associated with Proposed Project Bleu Press Release-03-015, NRC Licensing Board Decides to Rule on Three Nuclear Fuel Services., Inc., Amendment Applications at One Time2003-01-31031 January 2003 Press Release-03-015: NRC Licensing Board Decides to Rule on Three Nuclear Fuel Services., Inc., Amendment Applications at One Time Press Release-03-001, NRC Announces Opportunity for Hearing on Nuclear Fuel Services, Inc., Amendment Request2003-01-0303 January 2003 Press Release-03-001: NRC Announces Opportunity for Hearing on Nuclear Fuel Services, Inc., Amendment Request 2023-05-09
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region II 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No: II-11-043 August 4, 2011 CONTACT: Roger Hannah (404) 997-4417 E-mail: OPA2.Resource@nrc.gov Joey Ledford (404) 997-4416 NRC SCHEULES MEETING TO DISCUSS RESTART OF NFS PROCESS LINE The Nuclear Regulatory Commission has scheduled a public meeting for Tuesday, Aug.
16 to discuss the findings of its restart readiness assessment team that led to the decision last month to authorize restart of the uranium hexafluoride process at Nuclear Fuel Services in Erwin, Tenn.
The meeting is scheduled to begin at 6 p.m. at the Erwin Town Hall, 211 North Main Ave., in Erwin. The public can observe the business part of the meeting and the NRC staff will then host a formal question and answer session.
All process lines at NFS were shut down in late December 2009, and the NRC issued a confirmatory action letter the next month that was designed to address issues that contributed to earlier events at the nuclear fuel processing facility.
After separate readiness reviews, process lines at NFS were authorized to restart, one at a time. The Navy Fuel line was authorized to restart in March 2010, the uranium metal/uranium oxide line was authorized in May 2010, and the uranium/aluminum line was cleared in July 2010. A fourth process, the ammonium diuranate line, was approved for restart in October 2010.
The uranium hexafluoride process was the last of the NFS processes the company shut down in 2009.
Each of the readiness reviews, conducted by a team of NRC inspectors, was designed to provide reasonable assurance that performance deficiencies identified in 2009 were sufficiently addressed by NFS.
News releases are available through a free listserv subscription. The NRC homepage (www.nrc.gov) offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's website.