Press Release-I-08-054, NRC Issues Report on Vermont Yankee Engineering Inspection

From kanterella
Jump to navigation Jump to search
Press Release-I-08-054: NRC Issues Report on Vermont Yankee Engineering Inspection
ML082701064
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 09/26/2008
From:
Office of Public Affairs Region I
To:
Category:Press Release
References
Press Release-I-08-054
Download: ML082701064 (2)


Text

No. I-08-054

Contact:

Diane Screnci, 610/337-5330 Neil Sheehan, 610/337-5331 September 26, 2008 NRC ISSUES REPORT ON VERMONT YANKEE ENGINEERING INSPECTION The Nuclear Regulatory Commission has issued a report containing the results of a comprehensive engineering review conducted this summer at the Vermont Yankee nuclear power plant. Known as a Component Design Bases Inspection (CDBI), the review was carried out by a team of five NRC inspectors and three contractors. It involved three weeks of on-site assessments performed from July 21 to Aug. 14, 2008, at the Vernon, Vt., facility and entailed more than 700 hours0.0081 days <br />0.194 hours <br />0.00116 weeks <br />2.6635e-4 months <br /> of direct inspection activity.

Three green, or very low safety significance, inspection findings have been identified.

All three have been classified as non-cited violations. As a result, the plants owner, Entergy, will be required to enter them into the corrective action program for Vermont Yankee and complete a more comprehensive assessment of the issues. The corrective actions will be subject to review during future NRC inspections.

Component Design Bases Inspections are an important part of our regulatory toolkit, NRC Region I Administrator Samuel J. Collins said. We use these inspections, in tandem with our numerous other reviews, to gain insights into whether the way a plant is operated is consistent with the way it was designed. In this instance, we did not find any problems that rose above the level of very low safety significance.

The inspection findings are as follows: An issue involving the proper evaluation and documentation of test results for plant back-up power batteries, although actual battery capacity was found to be sufficient; an issue pertaining to a procedure deficiency that resulted in an incorrect assumption being used in the analysis dealing with the loss of all A.C. power for the plant, also known as a station blackout condition; and an issue involving the testing of plant emergency diesel generators at the maximum manual load (above emergency levels), although it was determined that the emergency diesel generators would be available in the event of a loss of off-site power. None of these issues would have resulted in safety equipment being unable to perform the intended function if needed.

NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region I 475 Allendale Road, King of Prussia, Pa. 19406 E-mail: opa1@nrc.gov Site: http://www.nrc.gov

All told, the CDBI team performed a detailed review of 23 plant components, four risk-significant actions by plant operators and three operating experience items.

CDBIs are part of the NRCs Reactor Oversight Process. They are carried out by the NRC about once every 3 years at each operating nuclear power plant in the U.S. In the case of the Vermont Yankee review, the Vermont Department of Public Service (DPS) observed the inspection, as well as a week of pre-inspection preparations. In addition, the NRC coordinated with the DPS on which components, actions and issues would be evaluated during the CDBI.

A copy of the report will be available in the NRCs Agencywide Documents Access and Management System (ADAMS) under accession number ML082700860. ADAMS is accessible via the agencys web site at: http://www.nrc.gov/reading-rm/adams.html. Help in using ADAMS is available by contacting the NRCs Public Document Room at 1-800-397-4209 or 301-415-4737, or by e-mail at PDR@NRC.GOV.

Separately, the NRC is continuing to review a license renewal application for Vermont Yankee. That application seeks a 20-year license extension for the plant, whose current 40-year operating license is set to expire on March 21, 2012.