NRC Bulletin 79-18, Audibility Problems Encountered on Evacuation of Personnel from High-Noise Areas

From kanterella
Jump to navigation Jump to search

Audibility Problems Encountered on Evacuation of Personnel from High-Noise Areas

August 7, 1979

text

Bulletin 79-18: Audibility Problems Encountered on Evacuation of Personnel from High-Noise Areas

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

WASHINGTON, D.C. 20555

August 7, 1979

IE Bulletin No. 79-18

AUDIBILITY PROBLEMS ENCOUNTERED ON EVACUATION OF PERSONNEL FROM HIGH-NOISE

AREAS

Description of Circumstances:

In January 1979, a number of licensee personnel were engaged in routine

activities in the auxiliary building at the Florida Power Corporation,

Crystal River Unit 3 nuclear plant. While these individuals were working in

the auxiliary building, in a high-noise (fan) area, an unplanned release of

radioactive noble gases was detected by building monitors within the

auxiliary building at concentrations which caused the licensee to initiate

the facility emergency plan auxiliary building evacuation procedure. The

facility Emergency Officer (Shift Supervisor) assessed the monitor readings

and initiated an auxiliary building evacuation. The evacuation announcement,

made over the licensee's PA system, was not heard by the personnel working

in the high-noise area. Licensee personnel did evacuate the auxiliary

building upon observing that other personnel had left, and after calling the

control room to inquire if an evacuation had been initiated. During these

occurrences, licensee personnel were not exposed to quantities of

radionuclides above regulatory guidance. However, the potential existed for

inadvertent unnecessary exposure of individuals to radioactive materials.

Subsequent to the NRC followup inspection of this occurrence, Florida Power

Corporation initiated an assessment of this situation and performed an

engineering evaluation and identified several plant areas where the

annunciator system needed audibility improvement. The licensee has installed

a new auxiliary building evacuation tone signal and may add visual alarm

indicators in areas of very high noise.

Action to be Taken by the Licensees:

For all power reactor facilities with an operating license:

1. Determine whether current alarm systems and evacuation announcement

systems are clearly audible or visible throughout all plant areas with

emphasis on high-noise areas. Determination in high-noise areas must be

made with the maximum anticipated noise level.

2. Determine what corrective action is necessary to assure that areas

identified as inaudible areas in (1) above, will receive adequate

audible/ visual evacuation signals. In areas where adequate audible/visual

evacuation signals cannot be assured by hardware changes, determine

what additional administrative measures are necessary to assure

personnel evacuation.

3. Submit within 45 days of the date of issuance of this Bulletin, a

written report of the findings on item (1), and delineate completed or

proposed corrective actions per item (2). For operating facilities in

a refueling or extended outage, the written report must be submitted

within 30 days after plant startup following the outage.

4. For accessible areas, all corrective actions determined per item (2)

must be completed within 120 days of the date of issuance of this

Bulletin. For inaccessible areas, the written report must include a

time schedule for completion of corrective actions in this area.

Reports should be submitted to the Director of the appropriate NRC Regional

Office and a copy should be forwarded to the NRC Office of Inspection and

Enforcement, Division of Reactor Operations Inspection, Washington, D.C.

20555.

For all power reactor facilities with a construction permit, this Bulletin

is for information only and no written response is required.

Approved by GAO, B180225 (R0072); clearance expires 7/31/80. Approval was

given under a blanket clearance specifically for identified generic

problems.