H Nebraska Public Power District Always there when you need us NLS2013090 October 3, 2013 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001

Subject:

Implementation of License Renewal Commitments Cooper Nuclear Station, Docket No. 50-298, DPR-46

Reference:

1. Letter from Stewart B. Minahan, Nebraska Public Power District, to U.S.

Nuclear Regulatory Commission, dated September 24, 2008, "License Renewal Application" (NLS2008071)

2. NUREG-1944, "Safety Evaluation Report Related to the License Renewal of Cooper Nuclear Station," dated September 2010
3. Letter from Brian J. O'Grady, Nebraska Public Power District, to U.S.

Nuclear Regulatory Commission, dated April 28, 2010, "Response to Open and Confirmatory Items from the Safety Evaluation Report Related to the License Renewal of Cooper Nuclear Station" (NLS2010044)

4. Letter from Brian J. O'Grady, Nebraska Public Power District, to U.S.

Nuclear Regulatory Commission, dated May 4, 2010, "Response to Open Items from the Safety Evaluation Report and Request for Additional Information Related to the License Renewal of Cooper Nuclear Station" (NLS2010050)

5. Letter from Demetrius L. Willis, Nebraska Public Power District, to U.S.

Nuclear Regulatory Commission, dated July 23, 2010, "Revisions and Supplements to Responses to Requests for Additional Information Related to the License Renewal of Cooper Nuclear Station" (NLS2010062)

Dear Sir or Madam:

The purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) that the final thirteen License Renewal Commitments with due dates prior to the period of extended operation have been implemented. This submittal is made pursuant to License Condition 2.F of the Cooper Nuclear Station (CNS) renewed Operating License, which requires written NRC notification of the implementation of License Renewal commitments.

COOPER NUCLEAR STATION P.0. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 ww.nppd.com

NLS2013090 Page 2 of 3 In the CNS License Renewal Application (Reference 1), the Nebraska Public Power District made a number of commitments to either develop new Aging Management Programs, or to enhance existing ones, as revised under subsequent correspondence. In Appendix A of the Safety Evaluation Report Related to the License Renewal of Cooper Nuclear Station (Reference 2), these were itemized in tabular form. The following commitments from that table have been implemented.

Updated Safety Analysis Aging Management Commitment Number Committed Date Report Supplement Program Section/LRA Section A.I.l.3/B.1.3 Buried Piping and NLS2008071-03 January 18, 2014 Tanks Inspection A.l.l.21/B.1.21 Masonry Wall NLS2008071-13 January 18, 2014 A.1.l.25/B.1.25 Non-EQ Inaccessible NLS2008071-16 Rev. 3' January 18, 2014 Medium-Voltage Cable A.1.1.29/B.1.29 One-Time Inspection NLS2008071-20 Rev. 3' January 18, 2014 A.I.1.30/B.I.30 One-Time Inspection NLS2008071-21 January 18, 2014

- Small-Bore Piping A.1.I.34/B.1.34 Selective Leaching NLS2008071-24 Rev. 11 January 18, 2014 A.l.l.36/B.1.36 Structures Monitoring NLS2008071-25 Rev. 2' January 18, 2014 and Supplement 1 The following commitments were made in References 3, 4, and 5 and have been implemented.

Updated Safety Analysis Aging Management Commitment Number Committed Date Report Supplement Program Section/LRA Section A.l.l.3/B.1.3 Buried Piping and NLS2010050-04 Rev. 1 January 18, 2014 Tanks Inspection NLS2010050-05 Rev. I NLS2010050-06 NLS2010062-01 NLS2010062-02 A.l.l.30/B.1.30 One-Time Inspection - NLS2010044-01 January 18, 2014 Small Bore Piping These commitments were revised subsequent to receipt of the renewed Operating License under the provisions of 10 CFR 50.59, in accordance with License Condition 2.E.

NLS2013090 Page 3 of 3 No new commitments have been made in this submittal. Should you have any questions regarding this submittal, please contact David Bremer, License Renewal Implementation Project Manager, at (402) 825-5673.

Sincerely, David W. Van Der Kamp Licensing Manager

/wv cc: Regional Administrator USNRC - Region IV Cooper Project Manager USNRC - NRR Project Directorate IV-1 Senior Resident Inspector USNRC - CNS NPG Distribution CNS Records