Charles R. Pierce Regulatory Affairs Director OCT 2 6 2016 Docket Nos.: 50-321 50-366 Southern Nuclear Operating Company, Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmingham, AL 35242 Tel 205.992.7872 Fax 205.992.7601 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant

~ Southern Nuclear NL-16-2267 Proposed Alternative HNP-ISI-ALT-05-03 Version 1.0 Supplemental Response Ladies and Gentlemen:

By letter dated July 6, 2016, Southern Nuclear Operating Company (SNC) submitted proposed Alternative HNP-ISI-ALT-05-03 Version 1.0 regarding Reactor Pressure Vessel Flange Seal Leak-off Piping Testing. This letter is to clarify that HNP-ISI-AL T 03 Version 1.0 is being requested pursuant to 10 CFR 50.55a(z)(2).

This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at 205.992.7369.

C. R. Pierce Regulatory Affairs Director CRP/RMJ cc:

Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Bast, Executive Vice President & Chief Nuclear Officer Mr. D. R. Vineyard, Vice President-Hatch Mr. M. D. Meier, Vice President-Regulatory Affairs Mr. D. R. Madison, Vice President-Fleet Operations Mr. B. J. Adams, Vice President-Engineering Mr. G. L. Johnson, Regulatory Affairs Manager-Hatch RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Ms. C. Haney, Regional Administrator Mr. M. D. Orenak, NRR Project Manager-Hatch Mr. D. H. Hardage, Senior Resident Inspector-Hatch