- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance
|
MONTHYEARND-22-0830, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816)2022-10-26026 October 2022 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816) Project stage: Request ND-22-0689, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53)2022-11-0303 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53) Project stage: Request ND-22-0862, ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561)2022-11-0808 November 2022 ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561) Project stage: Request ND-22-0730, ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319)2022-11-10010 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319) Project stage: Request ND-22-0657, ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480)2022-11-17017 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480) Project stage: Request ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)2022-11-18018 November 2022 ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751) Project stage: Request ND-22-0714, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171)2022-11-22022 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171) Project stage: Request ND-22-0711, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2022-11-23023 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ND-22-0821, ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819)2022-11-29029 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819) Project stage: Request ML22334A0752022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 Project stage: Request ND-22-0920, ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678)2022-12-0707 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678) Project stage: Request ND-22-0899, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214) Project stage: Request ND-22-0656, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348) Project stage: Request ND-22-0600, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291)2022-12-16016 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291) Project stage: Request ND-22-0747, ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33)2022-12-21021 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) Project stage: Request ND-22-0967, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802) Project stage: Request ND-22-0964, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800) Project stage: Request ND-22-0965, Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801) Project stage: Request ND-22-0895, ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90)2022-12-28028 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90) Project stage: Request ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company Project stage: Request ND-23-1001, ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684)2023-01-0505 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684) Project stage: Request ND-22-0848, ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317)2023-01-10010 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317) Project stage: Request ND-22-0869, ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462)2023-01-12012 January 2023 ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) Project stage: Request ND-23-0030, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-23-0026, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216) Project stage: Request ND-23-0029, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762) Project stage: Request ND-22-0649, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-22-0893, ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12)2023-01-16016 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12) Project stage: Request ND-22-0700, ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248) Project stage: Request ND-22-0521, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179) Project stage: Request ND-22-0585, ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154)2023-01-23023 January 2023 ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154) Project stage: Request ND-23-0041, ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219)2023-01-26026 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219) Project stage: Request ND-23-0078, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)2023-01-27027 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133) Project stage: Request ND-22-0739, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415) Project stage: Request ND-22-0876, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776) Project stage: Request ND-23-0079, ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285)2023-02-0202 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285) Project stage: Request ND-23-0039, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181) Project stage: Request ND-23-0043, ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32) Project stage: Request ND-22-0670, ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504)2023-02-0707 February 2023 ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504) Project stage: Request ND-22-0733, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350) Project stage: Request ND-23-0130, ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408) Project stage: Request ND-22-0737, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352) Project stage: Request ND-23-0124, ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879)2023-02-13013 February 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879) Project stage: Request ND-23-0153, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421) Project stage: Request ND-23-0141, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332) Project stage: Request ND-23-0071, ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259) Project stage: Request ND-23-0118, ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396) Project stage: Request ND-22-0919, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799)2023-02-24024 February 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799) Project stage: Request ND-23-0159, ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613)2023-03-0101 March 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613) Project stage: Request 2023-01-12
[Table View] |
Text
Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel June 2, 2023 Docket No.:
52-026 ND-23-0437 10 CFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of 2.3.04.04.ii [Index Number 331]
Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria ITAAC item 2.3.04.04.ii [Index Number 331]
for verifying the flow rate from the two highest fire-hose stations when aligned to the Passive Containment Cooling Water Storage Tank (PCCWST) is not less than 75 gallons per minute (gpm).
The closure process for this ITAAC is based on the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.3.04.04.ii [Index Number 331]
JMC/MKO/sfr
U.S. Nuclear Regulatory Commission ND-23-0437 Page 2 of 2 cc:
Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)
Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4
U.S. Nuclear Regulatory Commission ND-23-0437 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-23-0437 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.3.04.04.ii [Index Number 331]
U.S. Nuclear Regulatory Commission ND-23-0437 Enclosure Page 2 of 3 ITAAC Statement Design Commitment
- 4. The FPS provides for manual fire fighting capability in plant areas containing safety-related equipment.
Inspections/Tests/Analyses ii) Testing will be performed by measuring the water flow rate as it is simultaneously discharged from the two highest fire-hose stations and when the water for the fire is supplied from the PCS storage tank.
Acceptance Criteria ii) Water is simultaneously discharged from each of the two highest fire-hose stations in plant areas containing safety-related equipment at not less than 75 gpm.
ITAAC Determination Basis Multiple ITAAC are performed to demonstrate the Fire Protection System (FPS) provides for manual fire fighting capability in plant areas containing safety-related equipment. This ITAAC performed testing by measuring the water flow rate as it was simultaneously discharged from the two highest fire-hose stations when the water for the fire system was supplied from the Passive Containment Cooling System (PCS) storage tank.
Testing was performed as documented in Reference 1 using instruction in the Unit 4 preoperational test to confirm that when the water for the FPS was supplied from the PCS storage tank, water was simultaneously discharged from each of the two highest fire-hose stations in plant areas containing safety-related equipment at not less than 75 gallons per minute (gpm). The 2 highest fire-hose stations in plant areas containing safety-related equipment was determined to be F151A (room 12506) and F151B (room 12504). The flow measurement was performed at a level above the Primary Containment Cooling Water Storage Tank (PCCWST) technical specification minimum since the level in the tank will have negligible impact on gravity flow. There is a 1.1 foot elevation difference between the maximum PCCWST level and the technical specification minimum and a 187 foot elevation difference between the maximum PCCWST level and the highest fire-hose stations. The fire protection system was aligned to isolate the normal fire protection from the tested fire hose stations and the PCS storage tank was aligned to provide water to the fire-hose stations being tested. Ultrasonic flow instruments were installed upstream of the fire-hose stations and the fire hose was run and secured to a suitable drain. The fire-hose station isolation valves were opened, flow was monitored at each flow instrument and recorded approximately every 10 seconds and 30 readings were taken. The flow readings were corrected for measurement uncertainty and compared to the acceptance criteria. The flow for Unit 4 F151A was 113.1 gpm and 104.8 gpm for Unit 4 F151B. The completed test results, contained in Reference 1, confirm that water was simultaneously discharged from each of the two highest fire-hose stations in plant areas containing safety-related equipment at not less than 75 gpm.
Reference 1 is available for NRC inspection as part of the ITAAC 2.3.04.04.ii Completion Package (Reference 2).
U.S. Nuclear Regulatory Commission ND-23-0437 Enclosure Page 3 of 3 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.3.04.04.ii (Reference 2) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.3.04.04.ii was performed for VEGP Unit 4 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV4-FPS-ITR-800331, Rev 0, Unit 4 Recorded Results of PCS Storage Tank Discharge to Two Highest Fire-Hose Stations: ITAAC 2.3.04.04.ii
- 2. 2.3.04.04.ii-U4-CP-Rev0, ITAAC Completion Package