Notice of Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Fermi Power Plant, Unit 2 for Performance for 2020 Calendar Year
ML21152A296
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/01/2021
From: Nestor Feliz-Adorno
Reactor Projects Region 3 Branch 4
To:
DTE Electric Company
Shared Package
ML21050A341 List:
References
Download: ML21152A296 (4)


Text

June 01, 2021 NOTICE OF PUBLIC MEETING Licensee: DTE Energy Company Facility: Fermi Power Plant, Unit 2 Docket No.: 50-341 Date/ Time: Thursday, June 24, 2021 6:00 p.m. EDT Location: Webinar (via Microsoft Teams)

Purpose:

The NRC staff will host a webinar to present the NRCs assessment of safety performance at the Fermi 2 Power Plant for 2020, as described in the 2020 annual assessment letter. Following the presentation, the NRC will respond to questions specific to the safety performance of the plant and the NRCs role in ensuring safe plant operations.

NRC Attendees: N. Féliz Adorno, Chief, Division of Reactor Projects, Branch 4 T. Briley, Senior Resident Inspector, Fermi 2 T. Taylor, Resident Inspector, Fermi 2 S. Arora, Project Manager, Nuclear Reactor Regulation R. Ng, Senior Project Engineer, Branch 4, Division of Reactor Projects V. Mitlyng, Senior Public Affairs Officer P. Chandrathil, Public Affairs Officer Others, as designated Public Participation: This is an Information Meeting with a question and answer session. The purpose of this meeting is for the NRC staff to meet directly with individuals to discuss regulatory and technical issues. Attendees will have an opportunity to ask questions of the NRC staff, or to make comments about the issues discussed throughout the meeting; however, the NRC is not actively soliciting comments toward regulatory decisions at this meeting. The NRC staff will provide guidance during the webinar on the methods available to ask a question. Alternatively, questions may be submitted in advance to Nestor.Feliz-Adorno@nrc.gov.

Notice of Significant 2 Licensee Meeting This is a Microsoft Teams public meeting where participants will be able to see the presentation on a computer screen and hear the presenters through their telephone. Interested members of the public must call in at 1-888-677-1820, passcode 5601803, in order to listen to the presentation because the video application will have no sound.

The link for the EOC public meeting is:

Click here to join the meeting on your computer or mobile app.

System Requirements for Attendees for the webinar:

https://docs.microsoft.com/en-us/microsoftteams/hardware-requirements-for-the-teams-app If you have any questions, please call or email the meeting contact.

Meeting

Contact:

Néstor J. Féliz Adorno, Chief DRP, Branch 4 (630) 829-9739 Nestor.Feliz-Adorno@nrc.gov The NRCs annual assessment letters regarding the performance of the Fermi 2 Power Plant during 2020 can be found using ADAMS Accession No. ML21057A284. Additional information related to the NRCs annual assessment process and the safety performance of each site can be found on the NRCs website at: https://www.nrc.gov/reactors/operating/oversight.html.

The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective March 19, 2021, applies to this meeting. The policy statement may be found on the NRC website https://www.nrc.gov/reading-rm/doc-collections/commission/policy/index.html and on Federal Register 14964 https://www.govinfo.gov/content/pkg/FR-2021-03-19/pdf/2021-05787.pdf.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in this webinar or need the meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact. Determinations on requests will be made on a case-by-case basis.

Persons requiring assistance to attend the webinar shall make their requests known to the NRC meeting contact no later than two business days prior to the June 24, 2021, meeting.

Notice of Significant 3 Licensee Meeting Meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances.

Please confirm the meeting schedule on the NRC website (www.NRC.gov) under public meetings.

Approved by: ____/RA/___________

Néstor J. Féliz Adorno, Chief Branch 4 Division of Reactor Projects Meeting

Contact:

Néstor J. Féliz Adorno, Chief DRP, Branch 4 (630) 829-9739 Nestor.Feliz-Adorno@nrc.gov

Notice of Significant 4 Licensee Meeting DISTRIBUTION:

Aaron McCraw, Region III Coordinator, OEDO Russell Felts, Deputy Director, Division of Reactor Oversight, NRR RidsNrrDorlLpl3 RidsNrrPMFermi2 Resource Julio Lara, Director, Division of Reactor Projects, RIII Jamie Heisserer, Deputy Director, Division of Reactor Projects, RIII David Curtis, Acting Director, Division of Reactor Safety, RIII Néstor Féliz Adorno DRP Branch Chief Thomas Briley SRI, Fermi DRS Branch Chiefs:

Ann Marie Stone Karla Stoedter Richard Skokowski Patricia Pelke Steven Orth Allan Barker, Regional State Liaison Officer, RIII Viktoria Mitlyng, RIII Public Affairs Prema Chandrathil, RIII Public Affairs ADAMS Accession Number: ML21152A296 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII NAME RNg:ve via email NFéliz Adorno via email DATE 05/28/2021 06/01/2021 OFFICIAL RECORD COPY