Requests Addl Info Re 970225 Application for Amend to Coc for Portsmouth Gaseous Diffusion Plant.Responses Requested to Listed Comments within 30 Days of Ltr
ML20248J537
Person / Time
Site: Portsmouth Gaseous Diffusion Plant
Issue date: 07/08/1997
From: Yawar Faraz
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: John Miller
UNITED STATES ENRICHMENT CORP. (USEC)
References
TAC-L32014, NUDOCS 9707110116
Download: ML20248J537 (2)


Text

_ _ . . - . .

l

,. c=g g 2

.. 2t UNITED STATES

g y NUCLEAR REGULATORY COMMISSION ,

o & WASHINGTON. D.C. 20666-0001 i 8 July 8,1997 l

'k*****,o l Mr. James H. Miller i Vice President, Production U. S. Enrichment Corporation 2 Democracy Center 6903 Rockledge Drive Bethesda, MD 20817

SUBJECT:

PORTSMOUTH CERTIFICATE AMENDMENT REQUEST - INCREASED DOSE FOR HYPOTHETICAL CRITICALITY CASE IN BUILDING X-333 j (TAC NO. L32014) l 1

l

Dear Mr. Miller:

This refers to your application dated February 25,1997, requesting an amendment to the l Certificate of Compliance for the Portsmouth Gaseous Diffusion Plant, by increasing the l calculated dose for a hypothetical criticality case in Building X-333 described in section 4.1.1.2.5 of the Portsmouth Gaseous Diffusion Plant's Safety Analysis Report.

Our review of your application has identified a need for additionalinformation and i questions that need to be resolved before final action can be taken on your request. It I concerns information required for the NRC staff to independently assess the calculated dose. Please provide responses to the following comments.

( 1. Why did the increase in enrichment in the X-333 cascade result in a change in location of the assessed criticality accident? In pr.nciple, the reason is understood.

l However, a more explicit explanation is needed to show that the closest location

was correctly identified.

I

2. What is the basis for assuming that the criticalities of interest occur in X-33-6 at 40 feet or at X-33-8 at 240 feet?

l 3. Show all the steps in the calculation of 49 rem in ACR-1.

Please provide the additionalinformation within 30 days of this letter. Please reference the above TAC No. in future correspondence related to this request.

l f

pf*

NRC FILE CENTER COPY

\ b 9707110!.16 970700 llfllll[ll.lll,ll,{fll PDR Ain)CK 07007002 . .

C PDR

.- - -- - ~ . - -.. . - - . - - - ~_ - - - - . - . . - - . - . ~ . - _ . ~ _ . . . -

?- ,..

, Mr.' James H. Miller If you have any questions regarding this matter, please contact me at (301) 415-8113.

. Sincerely, g 9gned BY Yawar H. Faraz Project Manager Enrichment Section Special Projects Branch Division of Fuel Cycle Safety ,

and Safeguards, NMSS Docket 70-7002 -i Certificate GDP-2 )

i cc: Mr. Dale Allen, PORTS  !

Mr. Randy DeVault, DOE Mr. Rob Woolley, USEC DISTRIBUTION: (Control No. 060S) I Docket 70-7002 NRC File Center ~ PUBLIC Rlli ,

KO'Brien, Rlil CCox, Rlli JDavis, FCOB WSchwink, FCOB -

' MHorn RPierson DHeartland, Rlli KWinsberg NMSS r/f FCSS r/f SPB r/f PHiland, Rlli G:\RAIPOR.A3 i OFC SPB C FCLB 6 'SPB, ( SPgy,, .

NAME YFarak DDamN DAHhPM [rtin DATE. - (r/30/97 '/ d /97 7 / '/ /97 7/7 /97 j C = COVER E = COVliR & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY j