Forwards Rept, Rereview of Plant Instrumentation & Control for IE Bulletin 79-27 & Rev 0 to Engineering Rept ERPT-0229, Rept on Response to NRC IE Circular 79-02. Rereview Indicates That Plant Is in Compliance W/Bulletin
ML20235Y588
Person / Time
Site: Rancho Seco
Issue date: 10/12/1987
From: Firlit J
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Miraglia F
Office of Nuclear Reactor Regulation
Shared Package
ML20235Y592 List:
References
RTR-NUREG-1195 AGM-NPP-87-298, IEB-79-27, IEC-79-02, IEC-79-2, NUDOCS 8710200418
Download: ML20235Y588 (2)


Text

-

$SMUDSACRAMENTO MUNICIPAL UTILITY DISTRICT C P. O. Box 1583o, Sacramento CA 95852-1830,(916) 452-3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA October 12, 1987 AGM/NPP 87-298 U. .S. Nuclear Regulatory Commission Attn: Frank J. Miraglia, Jr.

Associate Director for Projects Philips Bldg.

7920 Norfolk Avenue Bethesda, MD 20014 DOCKET 50-312 RANCHO SECO NUCLEAR GENERATING STATION LICENSE NO. DPR-54 RE-REVIEW 0F IE BULLETIN 79-27 Dear Mr. Miraglia 1

! As a result of the December 26, 1985 event at Rancho Seco the NRC issued

( NUREG-1195. One of the findings noted in the NRC's review was a concern with respect to the District's response to IEB 79-27. In response to this concern the original submittal of the Bulletin was reviewed by the Precursor Review Group. Their review indicated a need for further evaluation of the concerns identified in the Bulletin. As a result, the District has performed and (

completed a comprehensive re-review of IEB 79-27.

} Attachment 1 contains the report which describes the results of this effort.

In this report items 1 and 2 of IEB 79-27 are addressed. The District's response to the recommendations found in Section 2.2 of the report are discussed in attachment 2. The Bulletin, item 3, also required the licensee to re-review IE Circular 79-02. The results of this effort has been included as attachment 3 to this letter. Thus, the District has re-reviewed the concerns found in IEB 79-27 and has determined Rancho Seco is in compliance with the requirements of the IE Bulletin.

Please contact me if you have any questions. Members of your staff with questions requiring additional information or clarification may contact Joh Atwell at extension 3906.

. Sincerely,

[

/ Joseph F. Firlit Assistant General Manager, Nuclear Power Production %gI Attachments i I cc: G. Kalman, NRC, Bethesda w/atch A. D'Angelo, NRC, Rancho Seco w/atch RANCHO sECO NUCLEAR GENERATING STATION 14440 Twin Cities Road, Herald, CA 95638-9799;(209) 333-2935 Y __ - )

/' . l ATTACHMENT 1 Re-review of Plant Instrumentation and Control for IEB Bulletin 79-27 4