ML20216B839
| ML20216B839 | |
| Person / Time | |
|---|---|
| Site: | Arkansas Nuclear |
| Issue date: | 03/10/1998 |
| From: | Collins E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Hutchinson C ENTERGY OPERATIONS, INC. |
| Shared Package | |
| ML20216B842 | List: |
| References | |
| 50-313-98-02, 50-313-98-2, 50-368-98-02, 50-368-98-2, NUDOCS 9803130200 | |
| Download: ML20216B839 (5) | |
See also: IR 05000313/1998002
Text
e
gemas % ,
f
.t
NUCLEAR REGULATORY COMMISSION
.
.
R EGION IV
611 RYAN PLAZA DRIVE, SUITE 400
9....*[
V
5
AR LINGTON, T E XAS 76011-8064
MAR I 01998
C. Randy Hutchinson, Vice President
Operations
Arkansas Nuclear One
Entergy Operations, Inc.
1448 S.R. 333
Russellville, Arkansas 72801-0967
SUBJECT: NRC INSPECTION REPORT 50-313/98-02; 50-368/98-02 AND NOTICE OF
VIOLATION
Dear Mr. Hutchinson:
From January 4 through February 14,1998, a routine resident inspection was conducted at your
Arkansas Nuclear One, Units 1 and 2, reactor facility. The enclosed report presents the scope
and results of that inspection.
During the 6-week period covered by this inspection, your conduct of activities at the ANO
facility was generally characterized by safety-conscious operations, sound engineering and
maintenance practices, and appropriate radiological controls. One violation of NRC
requirements was identified. The violation resulted from the failure of Unit 1 instrumentation and
control technicians to remove three electricaljumpers prior to restoring a reactor protection
system channel to service following surveillance testing.
The violation is cited in the enclosed Notice of Violation (Notice) and the circumstances
surrounding this violation are described in detail in the enclosed report. Please note that you are
required to respond to this letter and should follow the instructions specified in the enclosed
Notice when preparing your response. The NRC will use your response, in part, to determine
j
whether further enforcement action is necessary to ensure compliance with regulatory
requirements. In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this
c[
letter, its enclosure (s), and your response will be placed in the NRC Public Document
Room (PDR).
Should you have any questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
i1
w,)
)duc
2
.
c
l
w
Elmo E. Collins, Chief
Project Branch C
Division of Reactor Projects
9803130200 900310
ADOCK 05000313
g
'
,,
.
Entergy Operations, Inc.
-2
Docket Nos.: 50-313
50-368
License Nos.: DPR-51
NPF-6
Enclosures:
2. NRC Inspection Report
50-313/98-02; 50-368/98-02
cc w/ enclosures:
Executive Vice President
& Chief Operating Officer
Entergy Operations, Inc.
P.O. Box 31995
Jackson, Mississippi 39286-1995
Vice President
Operations Support
Entergy Operations, Inc.
P.O. Box 31995
Jackson, Mississippi 39286
Manager, Washington Nuclear Operations
ABB Combustion Engineering Nuclear
Power
12300 Twinbrook Parkway, Suite 330
Rockville, Maryland 20852
County Judge of Pope County
Pope County Courthouse
Russellville, Arkansas 72801
Winston & Strawn
l
1400 L Street, N.W.
Washington, D.C. 20005-3502
David D. Snellings, Jr., Director
Division of Radiation Control and
Emergency Management
4815 West Markham Street, Mail Slot 30
Little Rock, Arkansas 72205-3867
}
-
.
Entergy Operations, Inc.
3-
Manager
i
Rockville Nuclear Licensing
Framatome Technologies
1700 Rockville Pike, Suite 525
Rockville, Maryland 20852
.
.
Entergy Operations, Inc.
-4-
E-Mail report to T Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to Richard Correia (RPC)
E-Mail report to Frank Talbot (FXT)
bec to DCD (IE01)
bec distrib. by RIV:
Regional Administrator
Resident inspector
DRP Director
MIS System
Branch Chief (DRP/C)
RIV File
Project Engineer (DRP/C)
DRS-PSB
Branch Chief (DRP/TSS)
DOCUMENT NAME: R:\\_ANO\\AN802RP.KMK
To receive copy of document, indicate in box:"c" = Copy without enclosures "E" = Copy with enclosures "N" = No copy
RIV:RI
RIV:RI
RIV: SRI
C:D@/S
SCBurton
JFMelfi
KMKennedy
EECollins
2/27/98
2/27/98
2/27/98
2Q98
OFFICIAL RECORD CORP
.a
.e
N I b '"~
Entergy Operations, Inc.-
-4
E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to Richard Correia (RPC)
E-Mail report to Frank Talbot (FXT)
bec to DCD (IE01)
bec distrib. by RIV:
Regional Administrator
Resident inspector
DRP Director
MIS System
Branch Chief (DRP/C)
RIV File
Project Engineer (DRP/C)
DRS-PSB
Branch Chief (DRP/TSS)
l
!
l
DOCUMENT NAME: R:\\_ANO\\AN802RP.KMK
To receive copy of document, indicate in box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy
RIV:RI
RIV:RI
RIV: SRI
C:DfilP/f
f.
SCBurton
JFMelfi
KMKennedy
EEColiins
2/27/98
2/27/98
2/27/98
JLf98
OFFICIAL RECORD COFF
130020