Insp Rept 50-395/87-01 on 870101-31.No Violations or Deviations Noted.Major Areas Inspected:Licensee Action on Previous Insp Findings,Onsite Followup of Events & Subsequent Written Repts & Monthly Maint Observation
ML20211A823
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 02/09/1987
From: Dance H, Hopkins P, Modenos L, Prevatte R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20211A678 List:
References
50-395-87-01, 50-395-87-1, IEB-85-001, IEB-85-002, IEB-85-1, IEB-85-2, NUDOCS 8702190240
Download: ML20211A823 (7)


See also: IR 05000395/1987001

Text

n--

.

En af t

UNITED STATES

'

NUCLEAR REGULATORY COMMISSION'

o

[ *'

REGION ll

3

'A

.y

,j

101 MARIETTA STREET,N.W.'

' *

ATLANTA, GEORGI A 30323.-

4

o

.....

-

Report No.:

50-395/87-01

- Licensee: South Carolina Electric and Gas Company

Columbia, SC 29218

Docket'No.: 50-395

License No.: NPF-12

Facility Name : V. C. Summer

Inspection Conducted : January

-31, 1987

'

I

Z

f'7

Inspect s:

Richard L. Prevatte

D&te Signed

y

L f A%

zhlt,

'

, w Peiry C. Hopkins

Date Signed

"

b

9

]

Leo

Mo enos

Date Si ned

Approved by:

.

bu

9 [7

'^

Hugh C/ Dance, Sbccion Chief

D/te ' Signed

Division of Reactor Projects

l

SUMMARY

Scope: This routine, announced inspection was conducted by the resident

inspectors onsite, in the areas of licensee action on previous inspection

findings, onsite followup of events and subsequent written reports, monthly

surveillance observations, engineered safety features system walkdown, monthly

maintenance observation, operational safety verification, cold weather prepara-

tions and other areas.

Results: No violations or deviations were identified.

?$$2190$$ltaggo?

o

O

AD

$h

4

j

_

%

S

%

'

.

.

3

,

e

,

REPORT DETAILS

.'

,

1.

Persons Contacted

'

,

Licensee Employees

D. Nauman, Vice President, Nuclear Operations

0. Bradham, Director, Nuclear Plant Operations

J. Skolds, Deputy Director, Operations and Maintenance

G. Soult, Manager, Operations

M. Browne, Group Manager, Technical and Support Services

M. Quinton, Manager, Maintenance Services

A. Koon, Manager, Technical Support

G. Putt, Manager, Scheduling and Materials Management

K. Woodward, Manager, Nuclear Education and Training

L. Blue, Manager, Support Services

S. Hunt, Manager, Quality Assurance Surveillance Systems

W. Higgins, Associate Manager, Regulatory Compliance

J. Sefick, Manager, Nuclear Security

B. Williams, Supervisor, Operations

Other licensee employees contacted included engineers, technicians,

opera ors, mechanics, security force members, and office personnel.

2.

ExitInterview(30702,30703)

The inspection scope and findings were summarized on January 30, 1987, with

those persons indicated in paragraph 1 above. The inspectors described the

areas inspected and discussed the inspection findings. The licensee did not

identify as proprietary any of the materials provided to or reviewe,d by the

inspectors during the inspection.

\\

3.

Licensee Action on Previous Inspection Findings (92701, 92702)

(Closed) Unresolved Item 84-14-02, Adequacy of sra45er walkdown inspection.

LER 84-018, Steam _ generator system snubber and %dpa rt failures, identified

multiple snubber failures attributed to syrtEr. crr s ients.

The unresolved

item was a result of the snubber failures tir atif a in the above LER. The

inspector questioned the adequacy of the walkdown inspection following the

snubber failures.

The licensee has developed a Design Guide Procedure

ME-07, Evaldation of Technical Specification Snubbers, that provides a

,

detailed description of how an engineering evaluation shall be performed to

satisfy Technical Spcification (TS) Section 4.7.7.g.

The inspector

selected two NCN's 2082 and 2094, related to snubber failures, for review.

The NCN's were written prior to issuance of ME-07 but were dispositioned

utilizing the methods in the procedure while the procedure was in draft.

The inspector verified that the evt.luation was performed to satisfy the TS

requirements.

LER 84-018 was closed in inspection report 85-02. This item

is closed.

I

.

.

2

(Closed)

Bulletin 85-01, Steam binding of Auxiliary Feedwater (AFW) pump.

The inspector reviewed the licensee's response to items in the bulletin and

verified that the procedures required to monitor fluid conditions within the

AFW system were accomplished by the revision of the station logs on June 9,

1985.

This revision requires recording each emergency pump discharge

temperature once per eight hour shift.

Item 2 of the bulletin was satisfied

on January 2, 1986, when the Emergency Feedwater System Operating Procedure

(SOP-211) was revised to address recognition and corrective action for steam

binding of Emergency Feedwater pumps.

The inspector verified that a lesson

plan was incorporated into the training program to address the Auxiliary

Feedwater pumps disabled by back leakage. This item is closed.

(Closed)

Bulletin 85-02, Undervoltage trip attachments of Westinghouse

DB-50 type reactor trip breakers.

This bulletin is not applicable to the

V. C. Summer Station, since DS-416 type reactor trip breakers are installed,

instead of 08-50 type breakers, as addressed in this bulletin. This item is

closed.

(Closed)

Inspector Followup Item 83-15-07, Qualified reviewer problem with

technical specifications. This item addressed an inspector concern with the

qualification requirements of procedure reviewers as specified in technical

specifications.

The applicable section of ANSI Standard 18.1 (1971),

referenced in technical specifications, did not include qualifications for

procedure reviewers in the area of operations, managers and supervisors.

Amendment 57 to technical specifications, item 6.5.3.1 and item 6.5.3.1(e),

issued on December 22, 1986, corrects this discrepancy.

This item is

closed.

(Closed)

Violation 86-15-01, Failure to perform a 50.59 review prior to

implementing changes to plant operations.

The licensee provided a written

response to this violation in a letter to Region II, dated October 23, 1986.

The inspector reviewed the licensee's response and the corrective actions

implemented to prevent recurrence of this item.

The revisions to Station

Administrative Procedure (SAP-204), appear to provide adequate guidance to

plant personnel. This item is closed.

4.

Monthly Surveillance Observation (61726)

The inspectors observed surveillance activities of safety related systems

and components to ascertain that these activities were conducted in

accordance with license requirements.

The inspectors observed portions of

selected surveillance tests including all aspects of one major surveillance

test involving safety related systems.

The inspectors also verified that

the required administrative approvals

were obtained prior to initiating

the test, that the testing was accomplished by qualified personnel, that

required test instrumentation was properly calibrated, that data met TS

requirements, that test discrepancies were rectified, and that the systems

were properly returned to service.

The following specific surveillance

activities were observed:

. . - _ , ._ .

--

__

-

-

. - -

.-

- _ _ - .

-

.

,

3

STP 355.001

Waste gas system catalytic hydrogen recombiner

inlet hydrogen analyzer (HARC-1104) calibration

i

STP 113.001

Remote shutdown instruments channel check

STP 133.001

Axial flux difference calibration

STP 125.001

Electrical power system weekly test

,

f

STP 360.008

Reactor building area radiation monitor (RM-G18)

l

operational test

STP 302.006

Pressurizer pressure instrument (PT-457)

operational test

STP 396.013

Emergency feed pump suction pressure instrument

(PT-3634) operational test

STP 502.002

480 VAC switchgear circuit breaker test

ICP 160.030

Component cooling water surge tank level

ILT 7092 operational test

STP 508.003

Molded case circuit breaker test

STP 360.038

Reactor building purge exhaust atmospheric

radiation monitor (RM-A4) Calibration

STP 302.040

NIS power range (N-43) operational test

STP 302.019

Steam generator "A" narrow range level transmitter

operational test

No violations or deviations were identified.

5.

Monthly Maintenance Observation (62703)

The inspectors observed maintenance activities of safety related systems and

components to ascertain that these activities were conducted in accordance

with approved procedures, TS and appropriate industry codes and standards,

i

The inspectors also determined that the procedures used were adequate to

control the activity, and that these activities were accomplished by

qualified personnel.

The inspectors independently verified that equipment

was properly tested before being returned to service.

Additionally, the

inspectors reviewed several outstanding job orders to determine that the

licensee was giving priority to safety related maintenance and a backlog

which might affect its performance was not developing on a given system.

._.

-

- - . - - _ _ _ _ .

-

- -

.

.

4

The following specific maintenance activities were observed:

MWR 8600596

Repair clarifier agitator

MWR 86M0419

Replace rocker arm lube oil pump on "A" diesel

generator

PMST P0082283 Inspect and clean batteries

MWR 210910001 Install equipment and prewire panel XPN55321

MWR 210910007 Terminate circuits for XFN0067 "A" & "C" and perform

functional test

MWR 207200003 Fabricate and install supports for security

card readers

MWR 203050101 Install, remove and retag equipment and conduit

for doors CB 319, CB 309, CB 311, CB 317 and

CB 315

MWR 203050116 Install conduit for XXS0080-PS as required

MWR 87E0004

Replace broken secondary disconnect (XSW1DB1)

MWR 85E0147

Verify torque on studs for service water pump "B"

speed switch

MWR 317380016 Modification on wiring of speed switch on the service

water pump

MWR 207890001 Modification and testing of the service water pumps

PMST P0082304 Inspect, repair and lubricate water warmup pump on

diesel generator "B"

PMST P0083589 Check and set intake and exhaust valve backlash on

diesel generator "B"

No violations or deviations were identified.

6.

Operational Safety Verification (71707)

The inspectors toured the control room, reviewed plant logs, records and

held discussions with plant staff personnel to verify that the plant was

being operated safely and in conformance with applicable requirements.

Specific items inspected in the control room included:

adequacy of staffing

and attentiveness of control room personnel; TS and procedural adherence;

.

.

5

operability of equipment and indicated control room status; control room

logs, tagout books, operating orders, jumper / bypass controls; computer

printouts and annunciators.

Tours of other plant areas were conducted to

verify equipment operability; control of ignition sources and combustible

materials; the condition of fire detection and extinguishing equipment; the

control of maintenance and surveillance activities in progress; the

implementation of radiation protective controls and the physical security

plan. Tours were conducted during normal and random off hour periods.

No violations or deviations were identified.

7.

ESF System Walkdown (71710)

The inspectors verified the operability of an engineered safety features

(ESF) system by performing a walkdown of the accessible portions of the

Offsite Power System.

The inspectors confirmed that the licensee's system

lineup procedures matched plant drawings and the as-built configuration.

The inspectors looked for cquipment conditions and items that might, degrade

performance (hangers and supports were operable, housekeeping, etc.) and

inspected the interiors of electrical and instrumentation cabinets for

debris, loose material,' jumpers, evidence of rodents, etc.

The inspectors

verified that valves, including instrumentation isolation valves, were in

proper position, power was available, and valves were locked as appropriate.

The inspectors compared both local and remote position indications.

No violations or deviations were identified.

8.

Onsite Followup of Events and Subsequent Written Reports (92700, 93713,

93702)

The inspectors reviewed the following Licensee Event Reports (LER's) to

ascertain whether the licensee's review, corrective action and report of the

identified event or deficiency was in conformance with regulatory require-

ments, technical specifications, license conditions, and licensee procedures

and controls. Based upon this review the following items are closed.

LER 86-10

Charging / safety injection pump misalignment

LER 86-14

Turbine trip / reactor trip as a result of control

valve testing

No violations or deviations were identified.

9.

Cold Weather Preparations (71714)

The inspectors conducted a review of licensee cold weather preparations to

ascertain that the licensee maintained effective implementation of the

program of protective measures for extreme cold weather.

During the

inspection, the inspectors verified that the licensee had inspected systems

su:ceptible to freezing to verify the presence of heat tracing, space

. . -

6

heaters, and/or insulation; the proper setting of thermostats; and that the

heat tracing and space heating circuits were energized. The inspectors also

determined that, for systems which had been subjected to aaintenance and/or

modification during the past year, that any required protective measures

were reestablished, and during periods of prolonged shut down, that areas

that are no longer kept warm by normal plant operations are adequately

protected.

No violations or deviations were identified.

10. Semi-annual Effluent and Waste Disposal Report (84723, 84724)

The report listed below was reviewed by Regional inspectors to verify

reporting requirements, technical content, data collection, acceptance

criteria, and handling of deficiencies noted.

Completed report reviewed was as follows:

V.

C.

Summer Simi-annual Effluent and Waste Disposal Report, dated

August 29, 1986.

No violations or deviations were identified.

11. Other Areas

The resident inspectors assisted NRR and contractor personnel while in an

inspection for control room habitability during the weeks of January 5, and

January 12, 1987.

The results of this inspection will be documented in a

'

separate report.

The resident inspectors observed the practice emergency plan exercise

conducted on January 26, 1987.

This exercise was in preparation for an

emergency drill to be conducted on February 4, 1987.

.

-

.

.-

-

-

,

-

.

- _ -.-_-._ - -- .- -

- - . - -