Corrects Certain Info Submitted in 870127 Request for Expedited Issuance of Tech Spec Changes Re Snubber Operability Criteria.Snubber Insp Outage Actually Commenced on 861114 & Unit Returned to Svc on 861121
ML20209B503
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 01/29/1987
From: Gucwa L
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
SL-1934, TAC-64157, TAC-64158, TAC1-64157, NUDOCS 8702040060
Download: ML20209B503 (1)


Text

_.-_ - . . . - - . , . . _ . - . .. .. . ~ _ . .

.I Georgia Fbwer Compaq 333 P'edmont Avance s . Atlanta, Georgia 30308 Telephone 404 52G6526 Mailing Address:

Post Office Box 4545 Atlanta. Georgia 30302 1-Georgia Power L. T. Gucwe the southern electnc system a

Manager Nuclear Safety and ucensing SL-1934 1098C l January 29, 1987 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 NRC DOCKET 50-321

OPERATING LICENSE DPR-57 EDWIN I. HATCH NUCLEAR PLANT UNIT 1 RE0 VEST FOR EXPEDITED ISSUANCE i 0F TECFNICAL SPECIFICATIONS AMENDMENT

ADDITIONAL INFORMATION i

Gentlemen:

Georgia Power Company's letter of January 27, 1987 requested

expedited issuance of Plant Hatch Unit 1 Technical Specification changes l pertaining to snubber operability criteria. This letter serves to
correct certain information supplied in the request for expedited issuance.

i The subject letter states that a snubber inspection outage was entered on November 28, 1986 at Plant Hatch Unit 1. The subject outage actually commenced on November 14, 1986. The Unit was returned to L service on November 21, 1986. Therefore, the November 20, 1986 Technical j Specification change submittal was made concurrent with the snubber inspection outage, and not subsequent to the outage, as stated in the letter. The clock for the snubber re-inspection started November 18, 1986, and will expire February 5,1987, as stated.

I We regret that this information was presented incorrectly and

appreciate your efforts to grant the the November 20, 1986 Technical Specifications change request in a timely fashion. Please contact this office if you have any questions regarding this matter.

I Sincerely, l

l g7g2040go870129 D AD K 05000321

  1. 4- -

P PDR L. T. Gucwa 4

i REB /lc l c: Georria Power Company U. S. Nuclear Regulatory Commission t

{ Mr. i. P. O'Reilly Dr. J. N. Grace, Regional Administrator l

Mr. J. T. Beckham, Jr. Mr. P. Holmes-Ray, Senior Resident \

l Mr. H. C. Nix, Jr. Inspector - Hatch D

GO-NORMS Mr. G. Rivenback, Licensing Project \

l Manager w- mn --- - . , - - . . , , , - , , . , . _ - _ , - , , ,n , , , , , , . , _ , , , _ . _ _ , , , , _ , ,

_