Mod 28,increasing Funds & Extending Period of Performance to 870414,to Technical Assistance in Support of NRC Reactor Licensing Actions Program 2
ML20206M623
Person / Time
Issue date: 06/06/1986
From: Muzio B, Wiggins E
NRC OFFICE OF ADMINISTRATION (ADM), SCIENCE APPLICATIONS INTERNATIONAL CORP. (FORMERLY
To:
Shared Package
ML20206M581 List:
References
CON-FIN-B-8011, CON-FIN-D-1344, CON-NRC-03-82-096, CON-NRC-3-82-96 NUDOCS 8607010239
Download: ML20206M623 (3)


Text

4. CONT AACT 4D CODE PAGE OF PAGE.5
  1. .MENDMENT OF SOLICITATION / MODIFICATION OF CONTRACT 1

l 3

3. AMENOMENT/MODiraCATsON peO.

3.EFFLCTevt DAtt e, mEQuasit SON /PURCHAst mEQ NO.

6. PROJECT No. (if appheaters 28 6/6/86 NRR-86-056 NRR-82-096
4. IS$' #ED e v T. ADMIN 15TE AED eV (J/ ett.er egen item 6 A

[

US Nuclear Regulatory Comission Division of Contracts Washington, DC 20555

8. N AME AND ADDRESS OF CONT R ACTOR (No... trees, coun ty, aeore end 147 Code /

y)

DA. AMENDMENT OF 50LicaT ATION NO.

Science Applications International Corporation P. O. Box 1454 Ladolla, CA 92038

'"- ^ ' ' ' ' * " " '

loa. M DiF eCATION OF CONT R ACT/O$iDER X

NRC-03-82-096 Sots. DAt CD (SEE ITEM 23)

CODE lF ACIUTY CODE 11/23/81

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS The above numbered solicitation is emended as set forte in item 14 The hour and date specified for recect of OHers is ea tenses, is not o te,d.d.

Offers must acknowledge receipt of this emendment prior to the hour and date specified in the solicitation or es amended, by one of the forlowing meinods (e) By completing leems 8 and 15. and returning copies of the amendment: (b) By acknowledging receipt o' this amendment on each copy cd the o"e*

Submitted or (c) By separete letter or telegram e hich includes e reference to the solicitation and amendment numbers FAILURE OF YOUR ACKNOWLEDG-MENT TO BE RECEIVED AT THE PLACE DEslGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN hEJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change en offe* eiready submittes, such change may be made by te* yam o' ttier, provided each selegram or letter mes es reference to the wt. citation and this amendment, and is received preor to the opening houe and date somed ed i

12. ACCOUNT 6NG A,s0 APPROPR6ATsON DATA (Jf regnested)

See Below Increase:

$460,000

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTR ACTS / ORDERS.

IT MODIFIES THE CONTRACT / ORDER NO. AS DESCRIBED IN ITEM 14.

_E " N 'Ci"On"8En N S E M 'M N E N "'"^"' '

^ ' "

'"'##*"***#'""^~'' "'"'"" """'"*""'"

  • N,"J.**J,T.u." #,",'a f ?"Oli M,/?T a'".., E'4N8 7Jn'u'TLi#JT v t,"m"e'ode'"^" "" " '*""' " ' *""'

^

C. THiS SUPPLEMENTAL AGREEMENT f5 ENT ERED INTO PURivANT TO AUTNostaT v OF 4 X

the mutual apreement of the parties O. OTHLk (Speett> type of modmeerson end eenthents)

E. IMPORTANT: Contractor is not, b is required to sign this document and return 2

Copies to the issuing of fice.

WbEsCaseTion Or AMENDMENT /MODir iCATiON vore.assed my 31Cr. nets. ne.d.ne...nci.d ne.oi.ess.tionicon e.sce..avere meestr e,here fe i6ie.s The purpose of this modification is to provide funds for a within scope work change, which as a result increases the cost ceilino, to provide increnental funding, to extend the period of perfonnance, and to revise the accounting and appropriation data to show actual oblications to date.

Whereas. the contractor submit ed a proposal No. 1-263-71-870 '13, dated April 9, 1986 associated with the issuance of Task Order No. 24 under this contract, and 8607010239 860606 PDR CONTR NRC-03-82-096 PDR g.g,.,., e eeie.. h...in. ei, t.,,n s an..en.iue os e, tn..e.

m.n....,.... in..m. A o, i A, e s... e.e.. en..e...,n eins n.n.... e n. in...

.e,..

15A. PsAME AND ToTLE OF SIGNE A (Type er PNat) 16A. NAML AND T e TLE OF CONT R AC TING OF F 6CER (Type er snats Betty J. Muzio Elois J. liiggins Senior Contract Representative 155.CopTRAC 0 ERO 36C.D E seGNEO l68.UNtf O ST ATES OF AME ICA 16C.DATE ssGNth gY b

p{hb

/r inarnetu*eferrer.fn euthorsnod tr ehrns tssen tire et ContQ/fY Offseerb PetN T64043192 8070 I

PREVtoul EDIT 40N UNUSASLE ST.ANDARD FORM 30 (REv.10-8 3) go.10s

p. scribe by GSA F Am 140 CF M) $3.24 3

.. 1 Whereas, the parties mutually agreed to the amount of $499,421.00 to cover reimbursable costs only, and as further agreed, established a maximum award fee pool of $49,942.10 for this action, Now therefore, the subject contract is hereby revised to reflect changes associated with the issuance of this task order, and other non-associated

-changes.

I.

Article 3.1, Estimated Cost and Award Fee, Paragraphs 1, 2, and 4 of Section 3.0 are hereby deleted in their entirety and the following revised paragraphs 1, 2, and 4 are substituted in lieu thereof:

1.

The estimated cost to the Government for all allowable costs and award fee shall not exceed $7,558,295.21 for performance of this contract.

Note: This increases the ceiling of $7,008,932.11 established in Modification No. 27 by $549,363.10.

2.

The contractor shall be reimbursed for all allowable costs incurred, and accepted by the Contracting Officer, not to exceed the estimated amount of $6,878,674.11. This amount is inclusive of the $499.421.00 which covers reimbursable costs only for Task Order No. 24.

3.

Total funds currently available for payment and allotted to this contract are $7,020,245.88 of which $6,483,633.11 represents reimbursable costs and of which $536,612.77 represents available award fee through May 31, 1986.

For further provisions of funding, see General Provision No. 5.2 entitled " Limitation of Funds" and Article 5.11 entitled " Incremental Funding."

Note:

1) Total funds available for paynent through Modification No. 27 were $6,560,245.88.

This figure is therefore increased by $460,000.00.

Likewise, the figure of

$6,023,633.11 appearing in Modification No. 27 and representing reimbursable costs has been increased by

$460,000.00. Available award fee remains unchanged at

$536,612.'77.

2) The amount of $460,000.00 in incremental funding is obligated under the following FIN Numbers:

$360,000.00 (FIN No. D1344), and $100,000.00 (FIN No. B8011).

See also Paragraph IV below.

3)

The amount of $100,000.00 (FIN No. 88011) is furnished for continuation of work on assignment Nos.19,21, and 23.

II. Paragraph D. On-Call Assistance of the Statement of Work as found in Modification No. 22 is deleted in its entirety and the following paragraph is substituted in lieu thereof:

[

e

  • On-Call assistance will be required in the area of probabilistic risk analysis to perfom Integrated Safety Assessment Program (ISAP) reviews for Millstone Unit I and Haddam Neck, respectively, i

Note:

These reviews have been initiated by Task Order No. 23 (Millstone Unit 1) and Task Order No. 24 (Haddam Neck).

III. Section 2.0 Perfomance and Delivery, Article 2.1 " Period of Performance" is changed to read as follows:

The performance of this work shall comence on November 23, 1981, and continue through April 14, 1987 IV. As a result of this Modification No. 28, the total amount obligated under this contract is now $7,020,245.88.

The following is a breakdown of total contract obligations by FIN Number:

FIN Number Amount Obligated B-8011

$5,188,245.88 i

B-8609 840,000.00 B-8012 302,000.00 1

B-8013 130,000.00 1

D-1344 360,000.00 D-1336 200,000.00 Total Amount 37,020,245.88 i

i 4

,