Text

...

s 1

TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 37401 4

SN 1578 Lookout Place WAY 261988 U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Hashington, D.C.

20555

'Gentleien:

y In the Matter of

)

Docket Nos. 50-327 Tonnessee Valley Authority

)

50-328 SEQUOYAH NUCLEAR PLANT (SQN) - NRC INSPECTION REPORT 50-327/87-48 AND 50-328/87 INTEGRATED DESIGN INSPECTION (IDI) - SYSTEMS ENGINEERING PROGRAM UPDATE i

In TVA's response to the IDI programmatic issue, "Lack of System Integration,"

contained in the letter from S. A. White to NRC dated December 29, 1987, TVA committed to pNvide to NRC by April 1,1988, an update of the systems engineering program that was being developed for SQN. On April 1, 1988, TVA notified NRC that this schedule would not be met. This letter summarizes the current status of the SQN program.

As noted in TVA's December 29, 1987 letter, three types of systems engineers were to be established: plant systems engineers in the plant, project systems engineers in the design project onsite, and discipline staffed systems engineering specialists in the branches in Knoxville.

As of April 29, 1988, a plant systems engineer and a design project systems engineer have been assigned to each of the 92 systems at SQN. Discipline staffed systems engineering specialists have been assigned to 84 of the 92 systems at SQN.

A procedure has been implemented at SQN that defines the responsibilities of the plant systems engineer.

TVA will provide NRC with another update of the SQN systems engineering program by April 3, 1989.

The commitment made in this submittal is stated on tne enclosure.

Very truly yours, TENNESSEE VA LEY AUTHORITY kb

$0$0k h!Oh$ h R. Gridley, rector Q

DCD Nuclear Licensing and Regulatory Affairs p0(

Enclosure cc:

See page 2

)

An Equal opportunity Employer

s,.

U.S. Nuclear Regulatory Conunission cc (Enclosu'a' Mr. K. " Barr, Acting Assistant Director for Inspection Programs TVA_ Projects Division U.S. Nuclear Regulatory Comission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323' Mr. G. G. Zech, Assistant Director for Projects TVA Projects Division U.S. Nuclear Regulatory Comission One White Fitnt, North 11555 Rockville Pike Rockville, Maryland 20852 Sequoyah Resident Inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road Soddy Datsy, Tennessee 37379-i 1

1 ENCLOSURE NEW COMMITMENT FOR SQN 1.

TVA will provide NRC with another update of the SQN systems engineering program by April 3, 1989.

)