|
---|
Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML20138Q3871985-12-13013 December 1985 Ack Receipt of 851115 IE Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. Valve Operability Program & Rept Scheduled to Be Completed Prior to OL Issuance ML20127N3891985-01-31031 January 1985 Rev 1 to Midland Energy Ctr Project Shutdown Plan ML20127N3941985-01-31031 January 1985 Rev 0 to Midland Energy Ctr,Surveillance & Maint Plan ML20092C8541984-06-15015 June 1984 Midland Idcvp Auxiliary Feedwater Sys Performance Requirements ML20093D2131984-04-30030 April 1984 Rev 18 to Procedure RS-084-01, Interface Control for Interorganizational Processes ML20084E1701984-04-27027 April 1984 Instruction Manual for Model DSRV-12-4 Diesel Engine/ Generator,Midland Plants 1 & 2 ML20081C4031984-03-0707 March 1984 Plan to Conduct Independent Mgt Appraisal of Midland Nuclear Project ML20081A5991983-08-26026 August 1983 Rev 1 to Procedure ATP-12-Q, Procedure for Performing Calculations & Technical Studies ML20081A6141983-08-26026 August 1983 Rev 1 to Procedure 8301 WTP-4-Q, Procedure for Resolution of Spatial Sys Interaction Program/Seismic Postulated Interactions ML20081A6261983-08-26026 August 1983 Rev 1 to Procedure ATP-13-Q, Procedure for Preparation of Project Technical Repts ML20078K2841983-08-0505 August 1983 Rev 1 to third-party Const Implementation Overview Approval ML20078K2941983-08-0505 August 1983 Rev 1 to Quality Control Instruction 15.01, Nonconformance Identification & Reporting ML20078K3061983-08-0505 August 1983 Rev 1 for third-party Const Implementation Overview Re QA Plan ML20078K2781983-07-21021 July 1983 Rev 0 to Verification Attribute Checklist P-2.20V, Pipe Supports ML20024F6111983-07-15015 July 1983 Rev 4 to Project QA Plan for Midland Independent Design Const & Verification Program. ML20076N1401983-07-15015 July 1983 Rept of Overhead Fluid Grouting Test Program ML20024F6171983-07-15015 July 1983 Rev 3 to Engineering Program Plan Project Instruction P1-3201-009 Midland Independent Design & Const Verification Program. ML20080A2521983-07-0505 July 1983 Rev 1 to Third-Party Const Implementation Overview Procedure ML20077D5271983-07-0505 July 1983 Rev 1 to Third-Party Const Implementation Overview ML20024C0941983-06-30030 June 1983 Core Damage Assessment Procedure Station 9918.1, Estimation of Extent of Core Damage. ML20072L2411983-06-30030 June 1983 Offsite Dose Calculation Manual for Midland Plant ML20078K2701983-06-27027 June 1983 Rev 1 to Quality Control Instruction 10.01, Const Implementation Overview Assessment ML20024B6221983-06-27027 June 1983 Rev 1 to QC Instruction Qci 10.01, Const Implementation Overview Assessment. ML20072J4681983-06-10010 June 1983 Rev 1 to Const Completion Program. Viewgraphs Encl ML20072J4781983-06-10010 June 1983 Rev 2 to Quality Verification Program ML20076G0401983-06-0606 June 1983 Rev 1 to Program Manual Spatial Sys Interaction Program/ Seismic Midland Energy Ctr ML20072A8501983-06-0303 June 1983 Const Completion Program ML20076G2591983-06-0101 June 1983 Rev 1 to ATP-10-Q, Procedure for Document Control ML20076G2431983-06-0101 June 1983 Rev 2 to ATP-8-Q, Procedure for Control of Computer Programs ML20076G2211983-06-0101 June 1983 Rev 2 to ATP-7-Q, Procedure for Training Mgjec Audit Team Members ML20076G2671983-06-0101 June 1983 Rev 1 to ATP-11-Q, Procedure for Identification, Documentation & Corrective Action for Nonconformances ML20076G2041983-06-0101 June 1983 Rev 2 to ATP-6-Q, Procedure for Performing Internal QA Audits ML20076G1391983-06-0101 June 1983 Rev 3 to ATP-2-Q, Procedure for Distribution & Verifying Implementation of Quality Related Procedures ML20076G1211983-06-0101 June 1983 Rev 2 to 8301-WTP-3-Q, Procedure for Performing Walkdowns of Ssip/S Targets ML20076G1061983-06-0101 June 1983 Rev 2 to 8301-WTP-2-Q, Procedure for Training of Ssip/S Walkdown Team Members ML20076G0851983-06-0101 June 1983 Rev 2 to STD-1-Q, Qualifications of QA Audit Personnel ML20076G0671983-06-0101 June 1983 Rev 2 to 8301-PIP-1-Q, Procedure for Project Interface Control ML20072B2521983-06-0101 June 1983 Rev 2 to Field Instruction FIC-5.100, Excavation Permit Sys ML20076G0941983-06-0101 June 1983 Rev 2 to 8301-WTP-1-Q, Procedure for Documentation of Postulated Interactions ML20076G1371983-05-26026 May 1983 Rev 2 to ATP-1-Q, Procedure for Control of Project Correspondence ML20076G2521983-05-26026 May 1983 Rev 1 to ATP-9-Q, 10CFR21-Procedure for Reporting of Defects & Noncompliance ML20023D5201983-05-18018 May 1983 Rev 2 to Engineering Program Plan Project Instruction PI-3201-009 Midland Independent Design & Const Verification Program,Project 3201. ML20023D1331983-05-0505 May 1983 Evaluation of Pressures in Lines of Grouting Equipment - Crack Repair Borated Water Storage Tank Foundations. ML20081J6571983-04-12012 April 1983 Test Program Status & Rev 12 - Test Schedule ML20071D6161983-03-0909 March 1983 Reactor Protection Sys Setpoint Methodology ML20071D6371983-03-0909 March 1983 Safety-Related Instrument Setpoint Methodology for Balance of Plant Equipment ML20072B2031983-02-0909 February 1983 Engineering Program Plan,Project Instruction PI-3201-009, Midland Independent Design & Const Verification Program, Project 3201. Corrected Pages Encl ML20071D9361983-02-0202 February 1983 Rev 1 to Hydraulic Snubbers ML20071D9271983-02-0202 February 1983 Rev 1 to Reactor Bldg Spray Sys Hydrazine Addition Positive Displacement Pump ML20071D9031983-02-0202 February 1983 Rev 1 to Reactor Bldg Spray Sys Centrifugal Pump 1985-12-13
[Table view] Category:TEST/INSPECTION/OPERATING PROCEDURES
MONTHYEARML20138Q3871985-12-13013 December 1985 Ack Receipt of 851115 IE Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. Valve Operability Program & Rept Scheduled to Be Completed Prior to OL Issuance ML20127N3891985-01-31031 January 1985 Rev 1 to Midland Energy Ctr Project Shutdown Plan ML20127N3941985-01-31031 January 1985 Rev 0 to Midland Energy Ctr,Surveillance & Maint Plan ML20092C8541984-06-15015 June 1984 Midland Idcvp Auxiliary Feedwater Sys Performance Requirements ML20093D2131984-04-30030 April 1984 Rev 18 to Procedure RS-084-01, Interface Control for Interorganizational Processes ML20084E1701984-04-27027 April 1984 Instruction Manual for Model DSRV-12-4 Diesel Engine/ Generator,Midland Plants 1 & 2 ML20081C4031984-03-0707 March 1984 Plan to Conduct Independent Mgt Appraisal of Midland Nuclear Project ML20081A5991983-08-26026 August 1983 Rev 1 to Procedure ATP-12-Q, Procedure for Performing Calculations & Technical Studies ML20081A6141983-08-26026 August 1983 Rev 1 to Procedure 8301 WTP-4-Q, Procedure for Resolution of Spatial Sys Interaction Program/Seismic Postulated Interactions ML20081A6261983-08-26026 August 1983 Rev 1 to Procedure ATP-13-Q, Procedure for Preparation of Project Technical Repts ML20078K2841983-08-0505 August 1983 Rev 1 to third-party Const Implementation Overview Approval ML20078K2941983-08-0505 August 1983 Rev 1 to Quality Control Instruction 15.01, Nonconformance Identification & Reporting ML20078K3061983-08-0505 August 1983 Rev 1 for third-party Const Implementation Overview Re QA Plan ML20078K2781983-07-21021 July 1983 Rev 0 to Verification Attribute Checklist P-2.20V, Pipe Supports ML20024F6111983-07-15015 July 1983 Rev 4 to Project QA Plan for Midland Independent Design Const & Verification Program. ML20024F6171983-07-15015 July 1983 Rev 3 to Engineering Program Plan Project Instruction P1-3201-009 Midland Independent Design & Const Verification Program. ML20077D5271983-07-0505 July 1983 Rev 1 to Third-Party Const Implementation Overview ML20080A2521983-07-0505 July 1983 Rev 1 to Third-Party Const Implementation Overview Procedure ML20072L2411983-06-30030 June 1983 Offsite Dose Calculation Manual for Midland Plant ML20024C0941983-06-30030 June 1983 Core Damage Assessment Procedure Station 9918.1, Estimation of Extent of Core Damage. ML20024B6221983-06-27027 June 1983 Rev 1 to QC Instruction Qci 10.01, Const Implementation Overview Assessment. ML20078K2701983-06-27027 June 1983 Rev 1 to Quality Control Instruction 10.01, Const Implementation Overview Assessment ML20072J4681983-06-10010 June 1983 Rev 1 to Const Completion Program. Viewgraphs Encl ML20072J4781983-06-10010 June 1983 Rev 2 to Quality Verification Program ML20076G0401983-06-0606 June 1983 Rev 1 to Program Manual Spatial Sys Interaction Program/ Seismic Midland Energy Ctr ML20072A8501983-06-0303 June 1983 Const Completion Program ML20076G0851983-06-0101 June 1983 Rev 2 to STD-1-Q, Qualifications of QA Audit Personnel ML20076G0941983-06-0101 June 1983 Rev 2 to 8301-WTP-1-Q, Procedure for Documentation of Postulated Interactions ML20076G1061983-06-0101 June 1983 Rev 2 to 8301-WTP-2-Q, Procedure for Training of Ssip/S Walkdown Team Members ML20076G1211983-06-0101 June 1983 Rev 2 to 8301-WTP-3-Q, Procedure for Performing Walkdowns of Ssip/S Targets ML20076G1391983-06-0101 June 1983 Rev 3 to ATP-2-Q, Procedure for Distribution & Verifying Implementation of Quality Related Procedures ML20076G0671983-06-0101 June 1983 Rev 2 to 8301-PIP-1-Q, Procedure for Project Interface Control ML20076G2041983-06-0101 June 1983 Rev 2 to ATP-6-Q, Procedure for Performing Internal QA Audits ML20076G2211983-06-0101 June 1983 Rev 2 to ATP-7-Q, Procedure for Training Mgjec Audit Team Members ML20076G2431983-06-0101 June 1983 Rev 2 to ATP-8-Q, Procedure for Control of Computer Programs ML20076G2591983-06-0101 June 1983 Rev 1 to ATP-10-Q, Procedure for Document Control ML20076G2671983-06-0101 June 1983 Rev 1 to ATP-11-Q, Procedure for Identification, Documentation & Corrective Action for Nonconformances ML20072B2521983-06-0101 June 1983 Rev 2 to Field Instruction FIC-5.100, Excavation Permit Sys ML20076G2521983-05-26026 May 1983 Rev 1 to ATP-9-Q, 10CFR21-Procedure for Reporting of Defects & Noncompliance ML20076G1371983-05-26026 May 1983 Rev 2 to ATP-1-Q, Procedure for Control of Project Correspondence ML20023D5201983-05-18018 May 1983 Rev 2 to Engineering Program Plan Project Instruction PI-3201-009 Midland Independent Design & Const Verification Program,Project 3201. ML20071D6161983-03-0909 March 1983 Reactor Protection Sys Setpoint Methodology ML20071D6371983-03-0909 March 1983 Safety-Related Instrument Setpoint Methodology for Balance of Plant Equipment ML20072B2031983-02-0909 February 1983 Engineering Program Plan,Project Instruction PI-3201-009, Midland Independent Design & Const Verification Program, Project 3201. Corrected Pages Encl ML20071D9361983-02-0202 February 1983 Rev 1 to Hydraulic Snubbers ML20071D9271983-02-0202 February 1983 Rev 1 to Reactor Bldg Spray Sys Hydrazine Addition Positive Displacement Pump ML20071D9031983-02-0202 February 1983 Rev 1 to Reactor Bldg Spray Sys Centrifugal Pump ML20076G1841983-01-28028 January 1983 Rev 1 to ATP-5-Q, Procedure for Providing Project Orientation ML20076G1651983-01-28028 January 1983 Rev 1 to ATP-4-Q, Procedure for Providing Mgjec QA Program ML20069Q4131982-10-25025 October 1982 to QA Dept Procedure B-3M-1, Qualification & Certification of Insp & Test Personnel 1985-12-13
[Table view] |
Text
T- 3 P I
'- QCl No. REV. DATE PREPARco BY STONE & WEBSTER 10.01 1 6/27/A1 J.C. Thompson olvl SloN LOCATION FOE f"lDP
( QUALITY APPLICABILITY APPROVE 45Y CONTROL ruA -
kw us SAz/Ar INSTRUCT 10N Nu SUBJECT CONSTRUCTION IMPLEMENTATION OVERVIEW ASSESSMENT 1.0 PURPOSE AND SCOPE 1.1 To establish a program for management planning, conducting and documenting the Construction Implementation Overview (CIO) assessment of the Con-struction Completion Program (CCP). This QCI shall be applicable to all phases of the CCP and may cover additonal activities as directed by the SWEC Program Manager.
2.0 REFERENCES
2.1 SWEC Third Party Construction Implementation Overview Procedure 5/19/83 2.2 SWEC Project Quality Assurance Plan 2.3 Construction Completion Program 3.0 ATTACHMENTS 3.1 Evaluation Checklist (Sample)
{
3.2 Verification Checklist (Sample) 4.0 GENERAL 4.1 This CIO program shall assure proper implementation of the CCP through a systemmatic assessment of procedures, instructions, directives, cor-respondence, specifications, drawings and commitments as applicable.
Assessment shall confirm conformance in the development, approvals and implementation of the CCP and shall encompass program evaluation and physical verification.
4.2 CIO shall provide for the evaluation of the CCP in a planned and system-atic manner, i.e., prepare schedules for preparation of checklists, develop checklists applicable to specific Project Quality Control Instructions (PQCI) and perform evaluations of documented inspections / activities.
4.3 CIO shall use the checklists to perform evaluations and/or verification of the documented inspection or activity.
4.4 Results of assessments shall be documented in accordance with Section 6 of this QCI .
8310190034 830901 hD 449 PDR
('
N A/s
. , }
/
QCI 10.01 '
- REVISION 1 PAGE 2 b
5.0 RESPONSIBILITIES 5.1 The ProgramManager is responsible for:
- Implementation and control of-the overview of the CCP activities
- Evaluating compliance and effectiveness of the program Approval of checklists Participating in Management Reviews
- Preparation of reports of progress and nonconformances for presentation to the US NRC and CPCo -
- Documenting those meetings and telephone conversations that pertain to the CCP -
5.2 The Evaluation Supervisor'shall be responsible for:
- Developing checklists comprised of attributes based upon activities described in PQCI's, commitments and other project directives.
Maintaining and up-dating checklist matrices Directing the implementation of the Evaluation Program 5.3 The Verification Supervisor shall be responsible for:
Developing checklists comprised of attributes based upon activities described in PQCI's, commitments and other project directives
- Maintaining and up-dating checklist matrices
- Directing the implementation of the Physical Verification Program l 6.0 PROCEDURE
! 6.1 Evaluation / Verification shall be performed in accordance with the l
following instructions:
6.1.1 Attribute checklists shall be prepared utilizing the PQCI and l
appropriate additional data. Attribute checklists may include direction for information and guidance to the evaluator. Attributes shall be numbered sequentially, shall be clear, concise, without ambiguity and shall indicate the precise source of the attribute by page and paragraph. In addition the source data shall address any of the 18 criteria of 10CFR50 Appendix B as applicable. The CPCo team number shall be indicated in the " Responsible Organization" Column.
.(
E' , QCI 10.01 -
REVISION 1 PAGE 3 I
6.1.2 Review referenced documents, including correspondence, procedures, and inspection records pertinent to the CCP.
6.1.3 Complete the checklist attribute sheets during the assessment by entering the total number of observations made of each attribute and the number of observations found unsatisfactory, noting any remarks under " Comments". Remarks shall contain sufficient in-formation to ensure repeatability of the observation. This in-formation shall include identification of specifications, drawing procedures, reports, test results and nonconforming conditions and shall include copies of supporting documentation as necessary.
Attributes determined to be not applicable shall be mai?ed "N/A" and explained.
6.1.4 Each attribute.noted as unsatisfactory shall be evaluated by the Program Manager to determine if the unsatisfactory observation warrants the issuance of a Nonconformance Identification Report (NIR).
6.1.5 Checklists with attributes noted as unsatisfactory that do not re-sult in the issuance of an NIR shall be kept in an active file until reinspection determined that the attribute is considered satisfactory.
6.1.6 The checklist attribute sheets shall be considered as a guide for
( performing assessments. Attributes maybe modified or added or deleted (with explanation) as necessary to satisfy the objectives of References 2.1 and 2.2.
7.0 Records 7.1 Upon completion of all activities asssociated with a specific PQCI, the completed package (with copies of NIRs) shall be transmitted to CPCo Permanent Plant Files. .
7.2 CIO shall maintain a working Tile of all documentation transmitted to CPCo Permanent Plant Files. This file maybe used for reference or review by the US NRC.
Y T
(
i
- p. .
. STONE AND WEBSTER MICHIGAN INC MIDLAND ENERGY CENTER PROJECT EVALUATION ATTRIBUTE CHECKLIST
~
ATTRIBUTE CHECXLIST N' TITLE REY DATE PQCI N'/ REFERENCE TITLE REV DATE This' Attribute Checklist shall be completed in accordance with the following procedures.
Stone & Webster Quality Assurance Plan Third Party CIO procedure.
QCI 10.01' Construction Implementation Overview Assessment QCI 15.01 Nonconformance Identification Report S.W. Baranow Program Manager Attribute Checklist prepared by SIGN , DATE Checklist Approved by SIGN DATE
. s Checklist Completed by SIGN DATE l
l l .
Comp.leted Checklist Approved SIGN DATE l .
(' Attachment 3.1 l
[
p -
~
~
byONE AND W BSTER MICHibAN INC MIDLAND ENERGY CENTER Ph0 JECT VERIFICATION ATTRIBUTE CHECKLIST ATTRIBUTE CHECKLIST N* TITLE REV DATE
~
TITLE REV OATE PQUIN'/ REFERENCE This Attribute Checklist shall be completed in accordance with the following procedures.
-- - Stone-&-Webster-Quality Assurance Plan Third Party CIO procedure.
QCI 10.01 Construction Implementation Overview Assessment
. QCI 15.01 Nonconformance Identification Report S.W. Baranow
' Program Manager Attribute Checklist prepared by SIGN DATE Checklist Approved by SIGN . DATE Checklist Completed by SIGN DATE Completed Checklist Approved SIGN DATE
( ,
Attachment 3.2 t
t v,
~
F O
O _
E G
A P
G T.
A S S N N O
I U.
T o A N V
R .
E p S u )
B c O . T
. o E N E l
T i S . S I
P o.
mC L K
E t
i C
Sn E
R o I
N O
T A
E U T N U I B T I
R N T O T C A (
W e
S E
T U o B
I N
R T T S 1
T A % 9 l
K C
E l
I l
- t C
E T
4 U B
I R
T e T O A 3
m M .
l 0 9
EO 0 TN I
O T