Proposes Changes to Independent Review Program Submitted at 821005 Meeting & Discussed in 821025 & 1108 Meetings W/Tera & Mgt Analysis Co
ML20069P972
Person / Time
Site: Midland
Issue date: 12/03/1982
From: Jackie Cook
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Harold Denton, James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III), Office of Nuclear Reactor Regulation
References
19750, NUDOCS 8212080392
Download: ML20069P972 (4)


Text

e O Consumers Power James W Cook C0mpBHy v,,, e,,,u,.,- m j,,,,, r.f.,s.,

a.d Construction General offices: 1945 West Pernell Road, Jackson, MI 49201 e (517) 78&O453 Dt:cember 3,1982 Harold R Denton, Director Office of Nuclear Reactor Regulation Division of Licensing US Nuclear Regulatory Commission Washington, DC 20555 J G Keppler Administration, Region III US Nuclear Regulatory Comirission 799 Roosevelt Road Glen Ellyn, IL 60137 MIDLAND NUCLEAR C0 GENERATION PLANT MIDLAND DOCKET NOS 50-329, 50-330 MIDLAND PLANT INDEPENDENT REVIEW PROGRAM FILE:

B1.1.5 SERIAL:

19750

REFERENCES:

(1) J W COOK LETTER TO H R DENTON AND J G KEPPLER, SERIAL 18879 DATED 10/5/82 (2) NRC

SUMMARY

DATED 11/8/82 0F 10/25/82 MEETING ON INDEPENDENT DESIGN VERIFICATION Reference (1) provided a description of the Midland Plant Independent Review Program. Reference (2) summarized the October 25, 1982 meeting wherein Consumers Power Company and their contractors, Management Analysis Company (MAC) and Tera, discussed in more detail the Independent Review Program.

During this meeting, questions posed by the Staff were responded to by the Company and its contractors.

At the end of the meeting, Consumers Power Company requested the Staff to provide the applicant with policy guidance on the proposed Independent Review Program. The Staff agreed to provide preliminary feedback to Consumers Power Company by October 29, 1982 and to arrange for additional meetings as deemed appropriate. This was subsequently done and an additional meet.ing was held on November 5,1982 to provide the NRR Staff more details of the Stone and Webster third party assessment of the implementation of the soils underpinning work.

oc1182-0272a100 8212080392 821203 PDR ADOCK 05000329 A

PDR

+

~.

m. ?'~

/*

,s y.7,

,y 2

Based upon the meeting of October 25,-1982 and subsequent feedback from the NRC Staff, Consumers Power proposes the following change.s to the Independent Review Program as submitted in Reference-(1) and discussed at the October 25, 1982 meeting:

(1) The three specific evaluations will not be combined into a single program with coordination of the individual reports by MAC.

(2) The Tera Independent Design Verification'(IDV) effort will be.comnletely separate from the MAC effort with neither subcontractor having membe'rs from their company involved in the other company's efforts.'

(3) The Tera IDV will be on the Auxiliary Feedwater System.(AFWS) as s

originally planned, and will also be implemented on,aftother system which

- ~.

the Staff is to select based on three candidates provided by: Consumers i

Power Company on a risk assessment: basis. The thre(candidate systems

~

proposed by Consumers Power Company are:

a.

Electric Power System (Diesel Generator) b.

Safeguards Chilled Water System

~

~

c.

Containment Isolation System

_f (4) The Tera IDV will b-led to include a more in-depth review of-construction activ:'

__. provide assurance of as-built construction adequacy of the systems incl'uded in the Tera (IDV).

9 (5) For the IDV, any discussions between project personnel and Tera on confirmed findings will take place in formal meetings with the NRC-being'

'q notified of the meetings in time to attend, if they desire.

(6) For the INP0 Construction Project Evaluation, a copy of the final repo5L will be given to the NRC when it is sent to INPO.

7 We believe that this letter documents the conclusions reached between our organizations regarding the Midland Independent Review.

s m

' ~

JWC/GSK/bjb

~ "

CC Atomic Safety and Licensing Appeal Board CBechhoefer, ASLB 9

i',

MMCherry, Esq e

FPCowan, ASLB RJCook, Midland Resident Inspector RSDecker, ASLB SGadler, Esq JHarbour, ASLB GHarstead, Harstead Engineering

(

g oc1182-0272a100

~

~

s J

./.

3 le s

l DSilood, NRC

~

FJKelley, Ecq Wi&!a rshall WDPatton, Esq WDShafer, NRC BStamitis MSinclair LLBishop 1

1 l

l l

l I

i oc1182-0272a100 i

l I

9

'r CONSUMERS POWER COMPANY s

Midland Units 1 and 2 Docket No 50-329, 50-330 Letter Serial 19750 Dated December 3,1982 At the request of the Commission and pursuant to the Atomic,Encrgy Act of 1954, and the Energy Reorganization Act of 1974, as amended and the Commission's Rules and Regulations thereunder, Consumers Power Company submits MLiland Plant Independent Review Program.

CONSUMERS PG; R COMPAFY By J

Cook, Vice President Proje s, Engineering and Construction Swor and subscribed before me this J _ day of December, 1982 n

Notary Public

)

Jackson County, Michigan My Commission Expires September 8, 198h oc0982-0249a100

.