Amends 67 & 72 to Licenses DPR-24 & DPR-27,respectively, Adding Requirement to Maintain Security Force Training & Qualification Plan
ML20069L245
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 11/15/1982
From: Clark R
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20069L247 List:
References
NUDOCS 8211170141
Download: ML20069L245 (5)


Text

M'..

h+

UNITED STATES 3

NUCLEAR F EGULATORY COMMISSION g

' SHINGTON. D. C. 20555

- r WISCONSIN ELECTRIC POWER COMPANY POINT BEACH NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-266 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 67 License No. DPR-24 1.

The Nuclear Regulatory Comission (the comission) has found that:

A.

The filing (which is being handled by the Comission as an application) by Wisconsin Electric Power Company (the lictasee) dated April 7,1981 as revised July 28, 1981 and August 6, 1982, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Comission's rules-and regulations set forth in 10 CFR Chapter I; B.Mhe facility will' operate in conformity with the filing, the

^

provisions of the Act, anc the rules and regulations of the Comission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Comission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, Facility Operating License No. DPR-24 is hereby amended by renumbering and reformating the existing Paragraph 3.F to 3.F.(1) and (2) and by a.dding new paragraph 3.F.(3) to read as follows:

~B211170141 821115

~

PDR ADOCK 05000266 P

PDR

.:,9 3.F Physical Protection The licensee shall fully implement and maintain in effect all provisions of the following Commission approved documents, including amendments and changes made pursuant to the authority of 10 CFR 50.54(p).

These approved documents consist of Safeguards Information required to be protected from public disclosure pursuant to 10 CFR 73.21.

(1)

" Point Beach Nuclear Plant Physical Security Plan" dated May 24, 1977 as revised September 25, 1978, February 2, 1979, March 29,1979, December 7,1979 and May 29, 1980.

(2)

" Safeguards Contingency Plan" (identified as revised Chapter 8, Revision 3 to the Security Plan) dated March 6,1981 submitted pursuant to 10 CFR 73.40. The Plan shall be fully implemented, in accordance with 10 CFR 73.40(b), within 30 days of this approval by the Commission.

(3)

" Point Beach Nuclear Plant Security Force Training and Qualification Plan" transmitted by letter dated April 7,1981 as revised by letters dated July 28,1981 and August 6, 1982. This plan shall be followed in accord-ance with 10 CFR 73.55(b)(4), 60 days after approval

    • ~

by the Commission. All security personnel, as required in the above plan, shall be qualified within two years of this approval. The licensee may make changes to this plan without prior Commission approval if the changes do not decrease the safeguards effectiveness of the. plan.

The licensee shall maintain records of and submit reports concerning such changes in the same manner as required' for changes made to the Safeguards Contingency _ Plan l

pursuant to 10 CFR 50.54(p).

1 3.

This license amendment is effective as of its date of issuance.

l FOR THE NUCLEAR REGULATORY COMMISSION 71%R Robert A. Clark, Chief Operating Reactors Branch #3 Division of Licensing l

Date of Issuance: November 15', 1982 e

~

/.

![*O seag);

UNITED STATES

',g NUCLEAR REGULATORY COMMISSION 5

sp j WASHINGTON, D. C. 20555

%,.,p. f 1-

....+

WISCONSIN ELECTRIC POWER COMPANY POINT BEACH NUCLEAR POWEli PLANT, UNIT N0. 2 DOCKET NO. 50-301

)

AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 72 License No. DPR-27 1.

The Nuclear Regulatory Comission (the Comission) has found that:

A.

The filing (which is being handled by the Comission as an application) by Wisconsin Electric Power Company (the licensee) dated April 7,1981 as revised July 28, 1981 and August 6,1982, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Comission's rules and regulations set forth in 10 CFR Chapter I; B.Nhefacilitywilloperateinconformitywiththefiling,the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be

~

conducted in compliance with the Comission's regulations; l

D.

The issuance of this amendment will not be inimical to the comon l

defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have l

been satisfied.

2.

Accordingly, Facility Operating License No. DPR-27 is hereby amended by renumbering and reformating the existing Paragraph 3.F to 3.F.(1) and (2) and by adding new paragraph 3.F.(3) to read as follows:

,-,-c.,-

,?..

3.F Physical Protection I

The licensee shall fully implement and maintain in effect all provisions cf the following Commission approved documents, including amendmants and changes made pursuant to the authority of 10 CFR 50.54(2). These approved documents consist of Safeguards Information required to be protected from public disclosure pursuant to 10 CFR 73.21.

(1)

" Point Beach Nuclear Plant Physical Security Plan" dated May 24,1977 as revised September 25, 1978, February 2, 1979, March 29,1979, December 7,1979 and May 29, 1980.

(2)

" Safeguards Contingency Plan" (identified as revised Chapter 8, Revision 3 to the Security Plan) dated March 6,1981 submitted pursuant to 10 CFR 73.40. The Plan shall be fully implemented, in accordance with 10 CFR

~

73.40(b), within 30 days of this approval by the Commi ssion.

l (3)

" Point Beach Nuclear Plant Security Force Training and Qualification Plan" transmitted by letter dated April 7,1981 as revised by letters dated July 28,1981 and August 6,1982. This plan shall be followed in accord-e=-

ance with 10 CFR 73.55(b)(4), 60 days after approval by the Commission.

All security personnel, as required in the above plan, shall be qualified within two years of this approval.

The licensee may make changes to this plan without prior Commission approval if the changes do not decrease the safeguards effectiveness of the plan.

The licensee shall maintain records of and submit reports concerning such changes in the same manner as required for changes made to the Safeguards Contingency. Plan '

pursuant to 10 CFR 50.54(p).

l 3.

This license amendment is effective as of its date of issuance.