's MONTHLY NARRATIVE REPORT OF OPERATING Ahv MAJOR MAINTENANCE EXPERIENCE This report describes the operating and major maintenance experience for the month of April, 1982. This narrative report was prepared by the plant staff and is submitted in accordance with Section 6.9.1.10 of the plant Technical Specifications.
Reassembly of Safety Injection pumps 1-1 and 1-2 was completed during April.
The pumps were inspected and realigned after the impeller locknut on pump 1-1 came loose and allowed the 6th stage impeller to move and gall the wear rings. Loktite was applied to tee locknuts as recommended by the manufacturer.
Perfomance test results show satisfactory pump perfomance.
There was no significant operating experience to report.
No challenges to the PORV's or safety valves have been made.
Furthermore, no changes have been made in the Offsite Dose Calculation Procedure, the Environmental Radiological Monitoring Procedure, or any radioactive waste treatment systems.
8206010hN
. 69-10810 (25) 9/77.
/,
AVERAGE DAILY UNIT POWER LEVEL 50-275 DOCKET NO.
UNIT Diablo Canyon Unit 1 bl4/82' DATE COMPLETED 8Y W B. Kaefer (805) 595-7351 TELEPHONE APRIL, 1982 MONE DAY AVERACE DAftY POWER LEVEL day AVER AGE DAILY POWER LEVEL (Mide-Net)
(MWe Net) t 0
I
/,
17 0
0
- _18 0
2 0
3 j,
0 20 0
0 S
1 2s 0
6 22 7
23 O
0 24 0
9 25 0
4 l
0 0
30 26 0
j 11 0
0 i,-
28 O
13 2,
0 I4 30 0
0 15 31 z'
0 16 w
INSTRUCTIONS On this fortnat.hst the average daily unit power level in MWe-Net for eachday in the reporting anonth. Cornpute to the nearest whole megawait.
I i
(4/77) i'.
t 1
i-
69-10807 (25) 9/77 OPERATING DATA REPORT DOCKET NO; 50-275 _
DATE 84/4/A2 COMPLETED BY UR Eaafer TELEPHONE (805) 595-7351 OPERATING STATUS Notes
- 1. Unit Name: DIABLO CANYON UNTT 1
- 2. Reporting Period:
April,1982
- 3. Licensed Thermal Power (MWt):
166.9 1170
- 4. Nameplate Rating (Gross MWe):
1084
- 5. Design Electrical Rating (Net MWe):
- 6. Maximum Dependable Ca'pecity (Gross MWe):
1134 1084
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes Occur in Capacity Ra. -gs (Items Number 3 Through T,Since Last Report, Give Reasons:
-NONE-
'9. Power LevelTo Which Restricted.If Any(Net MWe): 10. Reasons For Restrictions,1f Any:
Suspended low Power Test License This Month Yr. to Date Cumulative 0
0 0
- 11. Hours In Reporting Period 0
0 n
- 12. Number Of Hours Reactor Was Critical
- 13. Reactor Reserve Shutdown Hours n
0 0
- 14. Hours Generator On Line 0
0 0
- 15. Unit Reserve Shutdown Hours 0
0 0
0 0
0
- 16. Gmss Thermal Energy Generated (MWH)
- 17. Gross Electrical Energy Generated (MWH) 0 0
0
- 18. Net Electrical Energy Generated (MWif) 0 0
0
- 19. Unit Service Factor N/A
- 20. Unit Availability Factor N/A N/A
- 21. Unit Capacity Factor (Using MDC Net)
N/A
- 22. Unit Capacity Factor (Using DER Net)
- 23. Unit Forced Outage Rate N/A
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and Duration of Eachl:
-NONE-
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
Indeterminate i
- 26. Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY Indetermiinate
~
i INITIAL ELECTRICITY Indeterminate Indeterminate COMMERCIAL OPERATION o
(9/77 )
69-10809 (25) 9/77 e
I DOCKET NO.
50-275 UNIT SilUTDOWNS AND POWER REDUCTIONS UNIT NAME niabln h nvnn I! nit 1 DATE S/4/82
~
COMPLETED BY W_B. Kapfer REPORT MONTH APRII_1982 TELEPHONE f R05MM 7151 "r
E., ?
3
.E Licensee
,E r, he, Cause & Corrective No.
Date g
3g
,g&
Event g?
g3 Action to H
y:
5 jgg Report #
mo u
Prevent Recurrence g
6 810928 F
0 H
4 81-002/01T ZZ ZZZZZZ Halted fuel loading preparations upon discovery of seismic calcul-ation errors. Reanalysis and reviews are being conducted in accordance with Commissions's instructions.
I 2
3 4
F: Forced Reason:
Method:
Exhibit G - Instructions S: Scheduled A Equiprnent Failure (Explain) 1 Manual for Preparation of Data B-Maintenance of Test 2 Manual Scram.
Entry Sheets for Licensee C-Refueling 3 Automatic Scram.
Event Report (LER) File (NUREG-D-Regulatory Restriction 4-Other (Explain) 0161)
E-Operator Training & Ucense Examination F Adrninistrative 5
G-Operational Error (Explain)
Exhibit I Same Source (9/77)
Il Other (Explain)