' THE CLEVELAND ELECTRIC ILLUMIN ATING COMPANY P O BOX 5000 m CLEVEL AND. OHIO 44101 m TELEPHO'4E (216; 622-9800 m ILLUMINATING BLOG e 55 PUBLIC SOUARE Serving The Best location in the Nation Dalwyn R. Davidson yCE MdESCENT
' f 5iE M F P.Gnf EHWG AND CONSTHUCTION May 6, 1982 Mr. James G. Keppler Director, Region III Offi e of Inspection and Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137 Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Revised Response to I. E. Bulletin No. 80-16
Dear Mr. Keppler:
In our response to I. E. Bulletin No. 80-16 dated August 11, 1980, we committed to e replacement schedule of all 1152 pressure transmitters with output codes of "A" and "D", to be completed by January 1, '981.
Our commitment also includes replacement of all 1151 pressure transmitters with output codes of "A" and "D",
although the 1151 transmitters were not mentioned in our August 11, 1980, response.
Due to the equipment lead time, installation time, and check out time, the schedule is being revised to a more realistic completion date of April 1, 1983.
If you require additional information, please let me know.
Very truly yours, fdNP Dalwyn R. Davidson Vice President System Engineering and Construction DRD: mlb cc: